| 2020-09-21 14:14:51 | FAILED |
| | |
| | 1) THANK YOU FOR PROVIDING PHOTOS OF THE EXISTING ROOF |
| | TO VERIFY THAT THERE IS A PARAPET; HOWEVER, NO |
| | INFORMATION WAS PROVIDED AS TO THE HEIGHT OF THE |
| | PARAPET AND THE HEIGHT OF THE NEW OARTU-1. BASED ON THE |
| | SHOP DRAWINGS, THE MAU-1 APPEARS TO BE OVER 8 FEET IN |
| | HEIGHT WITH THE CURB, WHICH WOULD TAKE A TALL PARAPET |
| | TO SCREEN. THE CU-3 HEIGHT (BUT WITHOUT THE CURB) AND |
| | EF-1 HEIGHT WERE PROVIDED. WITHOUT THE HEIGHT OF THE |
| | PARAPET, STAFF CANNOT VERIFY SCREENING. A CROSS SECTION |
| | DRAWING, WITH DIMENSIONS, WOULD BE VERY HELPFUL. ----- |
| | IN ACCORDANCE WITH THE CITYPLACE DRI, PLEASE PROVIDE |
| | VERIFICATION THAT ALL ROOFTOP MECHANICAL EQUIPMENT, |
| | INCLUDING BUT NOT LIMITED TO SUCH ITEMS AS PUBLIC AND |
| | PRIVATE UTILITY SERVICE CONNECTIONS; HEATING, |
| | VENTILATING, AND AIR CONDITIONING SYSTEMS; |
| | COMMUNICATIONS DEVICES; AND RELATED EQUIPMENT, SHALL BE |
| | SCREENED FROM PUBLIC VIEW THROUGH ANY COMBINATION OF |
| | LANDSCAPING, WALLS AND EQUIPMENT LOCATION. PLEASE |
| | PROVIDE PLANS OR OTHER EVIDENCE THAT THE NEW ROOFTOP |
| | MECHANICAL EQUIPMENT WILL BE SCREENED FROM PUBLIC VIEW. |
| | IF VERIFICATION THAT THE NEW ROOFTOP MECHANICAL |
| | EQUIPMENT IS NOT SCREENED, ZONING WILL NOT APPROVE THIS |
| | INTERIOR BUILD OUT PERMIT. |
| | |
| | CONTACT ERIC SCHNEIDER @ (561) 822-1446 |
| | [email protected] |
| | |