 1) VALUE FOR A 60KW GENERATOR AND TRANSFER SWITCHES ON
 PERMIT TOO LOW. (22,000) PLEASE SUBMIT A SIGNED
 CONTRACT FOR THE GENERATOR INSTALLATION.
  
 109.3 BUILDING PERMIT VALUATIONS. IF, IN THE OPINION OF
 THE BUILDING OFFICIAL, THE CLAIMED VALUATION OF
 BUILDING, ALTERATION, STRUCTURE, ELECTRICAL, GAS,
 MECHANICAL OR PLUMBING SYSTEMS APPEARS TO BE
 UNDERESTIMATED ON THE APPLICATION, THE PERMIT SHALL BE
 DENIED, UNLESS THE APPLICANT CAN SHOW DETAILED,
 QUANTITY ESTIMATES, AND/OR BONA FIDE SIGNED CONTRACTS
 (EXCLUDING LAND VALUE) TO MEET THE APPROVAL OF THE
 BUILDING OFFICIAL. FOR PERMITTING PURPOSES, VALUATION
 OF BUILDINGS AND SYSTEMS SHALL BE TOTAL REPLACEMENT
 VALUE TO INCLUDE STRUCTURAL, ELECTRIC, PLUMBING,
 MECHANICAL, INTERIOR FINISH, RELATIVE SITE WORK,
 ARCHITECTURAL AND DESIGN FEES, MARKETING COSTS,
 OVERHEAD AND PROFIT; EXCLUDING ONLY LAND VALUE.
 VALUATION REFERENCES MAY INCLUDE THE LATEST PUBLISHED
 DATA OF NATIONAL CONSTRUCTION COST ANALYSIS SERVICES
 (MARSHALL-SWIFT, MEANS, ETC.), AS PUBLISHED BY
 INTERNATIONAL CODE CONGRESS. FINAL BUILDING PERMIT
 VALUATION SHALL BE SET BY THE BUILDING OFFICIAL.
  
 2) NEED TO SUBMIT A RISER DIAGRAM SHOWING ALL
 ELECTRICAL COMPONENTS OF THIS SYSTEM 215.5