2020-08-31 08:30:41DATE: MON. JULY 27TH/ AUGUST 31ST/ / 2020
 ACTION:BUILDING PROVISO
  
 1) SHEET A1 INDICATES THE AIR HANDLER IS TO BE
 REPLACED, NOTE 5 INDICATES DUCT WORK TO REMAIN.
 IF THE BI-FOLD DOORS ARE USED TO TRANSFER THE RETURN
 AIR TO THE UNIT THEN THE LOUVER DOORS NEED TO BE METAL.
 2017 FBC-B SECTION 2801.1 MECHANICAL EQUIPMENT AND
 SYSTEMS SHALL BE CONSTRUCTED, INSTALLED AND MAINTAINED
 IN ACCORDANCE WITH THE FBC-M AND FBC-B FOR PLENUMS.
 JAMES A. WITMER BN, PX, SFP, CBO