| Date |
Text |
| 2021-05-24 14:09:35 | NEW SFR |
| | REVIEWED BY ROGER MCPHERSON |
| | 561-805-6716 |
| | [email protected] |
| | CODE USED FOR REVIEW - 2017 FBC WITH WPB CHAPTER 1 |
| | AMENDMENTS |
| | |
| | |
| | CORRECTIONS NEEDED - FBC WPB AMENDMENTS 107 |
| | |
| | 1) 2ND REVISION OF THE ROOFING PRODUCT APPROVAL |
| | PROVIDED DOES NOT SHOW A ROOFING SYSTEM TO BE USED - |
| | PLEASE CIRCLE A ROOFING SYSTEM TO BE USED ON THE |
| | PRODUCT APPROVAL - STARTING ON PAGE 8 OF THE PRODUCT |
| | APPROVAL. ROOFING SYSTEM TO BE USED ON THE PROVIDED |
| | PRODUCT APPROVAL MAY REQUIRE ADDITIONAL SIGNED AND |
| | SEALED ATTACHMENT DETAILS FROM AN ARCHITECT OR ENGINEER |
| | FOR ROOF WIND ZONES 2 AND 3 WHICH REQUIRE A HIGHER |
| | PRESSURE THAN THE MAXIMUM SHOWN ON THE PRODUCT APPROVAL |
| | ( ) - SEE GENERAL LIMITATION NOTE NUMBER 7 ON THE |
| | PRODUCT APPROVAL.) |
| | |
| | 2) ROOFING SYSTEMS PRODUCT APPROVALS MAY BE DEFERRED |
| | SUBMITTALS BY LISTING ITEMS TO BE DEFERRED ON THE |
| | CONSTRUCTION DOCUMENTS - 107.3.4.1 DEFERRED SUBMITTALS. |
| | FOR THE PURPOSES OF THIS SECTION, DEFERRED SUBMITTALS |
| | ARE DEFINED AS THOSE PORTIONS OF THE DESIGN THAT ARE |
| | NOT SUBMITTED AT THE TIME OF THE APPLICATION AND THAT |
| | ARE TO BE SUBMITTED TO THE BUILDING OFFICIAL WITHIN A |
| | SPECIFIED PERIOD. DEFERRAL OF ANY SUBMITTAL ITEMS SHALL |
| | HAVE THE PRIOR APPROVAL OF THE BUILDING OFFICIAL. THE |
| | REGISTERED DESIGN PROFESSIONAL IN RESPONSIBLE CHARGE |
| | SHALL LIST THE DEFERRED SUBMITTALS ON THE CONSTRUCTION |
| | DOCUMENTS FOR REVIEW BY THE BUILDING OFFICIAL. |
| | DOCUMENTS FOR DEFERRED SUBMITTAL ITEMS SHALL BE |
| | SUBMITTED TO THE REGISTERED DESIGN PROFESSIONAL IN |
| | RESPONSIBLE CHARGE WHO SHALL REVIEW THEM AND FORWARD |
| | THEM TO THE BUILDING OFFICIAL WITH A NOTATION |
| | INDICATING THAT THE DEFERRED SUBMITTAL DOCUMENTS HAVE |
| | BEEN REVIEWED AND FOUND TO BE IN GENERAL CONFORMANCE TO |
| | THE DESIGN OF THE BUILDING. THE DEFERRED SUBMITTAL |
| | ITEMS SHALL NOT BE INSTALLED UNTIL THE DEFERRED |
| | SUBMITTAL DOCUMENTS HAVE BEEN APPROVED BY THE BUILDING |
| | OFFICIAL. |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |