| 2020-09-02 14:12:51 | 09/02/20 1ST PLUMBING REVIEW**DENIED** WITH COMMENTS |
| | |
| | NOTE - A COMPREHENSIVE REVIEW COULD NOT BE DONE AT THIS |
| | TIME AND ADDITIONAL PLAN REVIEW COMMENTS MAY BE |
| | GENERATED UPON THE RE-REVIEW OF SUBMITTED CORRECTIONS. |
| | |
| | 1. PLEASE SHOW THE DISTANCE BETWEEN THE SHOWER, WATER |
| | CLOSET AND BIDET TO BE 30" BETWEEN FIXTURES PER THE |
| | 2017 FBC SEC. R 2705.1 GENERAL. |
| | |
| | 2. BIDET SHALL HAVE A WATER TEMPERATURE NOT GREATER |
| | THAN 110 F BY A WATER-TEMPERATURE-LIMITING DEVICE |
| | CONFORMING TO ASSE 1070 OR CSA B125.3 PER THE 2017 FBC |
| | SEC. R 2721.2 BIDET WATER TEMPERATURE. |
| | |
| | 3. ROMAN TUB HOT WATER SUPPLIED SHALL BE LIMITED TO A |
| | TEMPERATURE OF NOT GREATER THAN 120 F BY A WATER |
| | TEMPERATURE LIMITING DEVICE THAT CONFORMS TO ASSE 1070 |
| | OR CSA B125.3, EXCEPT WHERE SUCH PROTECTION IS |
| | OTHERWISE PROVIDED BY A COMBINATION TUB/SHOWER VALVE IN |
| | ACCORDANCE WITH SECTION P2708.4. IF TEMPERING VALVE IS |
| | INSTALLED IT SHALL HAVE AN ACCESS TO IT. |
| | |
| | WHEN RESUBMITTING PLANS PLEASE INDICATE THE REVISION & |
| | REMOVE ANY VOIDED SHEETS & REPLACE ANY PAGES AS |
| | NECESSARY. A TRANSMITTAL LETTER LISTING THE ORIGINAL |
| | REVIEW COMMENT NUMBER, WITH A DESCRIPTION OF THE |
| | REVISION, MADE, IDENTIFYING THE SHEET OR SPECIFICATION |
| | PAGE WHERE THE CHANGES CAN BE FOUND WILL HELP TO |
| | EXPEDITE YOUR PERMIT. THANK YOU FOR YOUR ANTICIPATED |
| | COOPERATION. |
| | |
| | LUIS A. CRESPO |
| | PLUMBING PLAN EXAMINER / INSPECTOR |
| | EMAIL: [email protected] OFFICE: 561 805-6720 |
| | |