| 2020-05-21 14:58:24 | 2ND REVIEW FBC-2017 |
| | PERMIT 20040217 |
| | 5/21/2020 |
| | |
| | CODES IN EFFECT: |
| | |
| | FBC RES- FLORIDA RESIDENTIAL BUILDING CODE SIXTH |
| | EDITION 2017 |
| | FBC B- FLORIDA BUILDING CODE SIXTH EDITION 2017 |
| | FBC M- FLORIDA MECHANICAL CODE SIXTH EDITION 2017 |
| | FBC EC- FLORIDA ENERGY CONSERVATION CODE SIXTH EDITION |
| | 2017 |
| | FBC FG- FLORIDA FUEL GAS CODE SIXTH EDITION 2017 |
| | FBC EX- FLORIDA EXISTING BUILDING CODE SIXTH EDITION |
| | 2017 |
| | FBC P- FLORIDA PLUMBING CODE SIXTH EDITION 2017 |
| | FBC ACC- FLORIDA ACCESSIBILITY CODE SIXTH ADDITION 2017 |
| | FS- FLORIDA STATUTES |
| | FAC- FLORIDA ADMINISTRATIVE CODE |
| | WPB- WEST PALM BEACH AMENDMENTS TO THE FBC SIXTH |
| | EDITION 2017 |
| | PLAN REVIEW RESULTS: DENIED. |
| | |
| | COMMENTS FROM THE 1ST REVIEW BELOW WILL BE MARKED AS |
| | PASSED OR FAILED. SEE NOTES ADDED FOR FAILED COMMENTS. |
| | |
| | 1) PASSED. |
| | 2) PASSED. |
| | |
| | 3.) FAILED. LIST THE BTU LOAD OF EACH APPLIANCE AND THE |
| | TOTAL BTU LOAD ON THE SYSTEM. REFER TO THE 2017 |
| | FBC-FUEL GAS SECS.401.8, 402.2, AND TABLES 402.4 (1) |
| | THRU 402.4 (37) OR 2017 FBC-RES. SEC. G2413.3, G2413.4 |
| | AND TABLES G2413.4 (1 ) THROUGH G2413.4 (21). TOTAL BTU |
| | LOAD OF THE SYSTEM NOT INDICATED. |
| | |
| | 4.) FAILED. SHOW THE DISTANCE FROM THE POINT OF |
| | DELIVERY, (GAS METER / MP REGULATOR / LP TANK) TO THE |
| | MOST REMOTE OUTLET IN THE BUILDING AND / OR SYSTEM PER |
| | THE 2017 FBC-FUEL GAS SEC.402.4.1, 402.4.2, OR 2017 |
| | FBC-RES. SEC. G 2413.4.1, G2413.4.2. TOTAL DEVELOPED |
| | LENGTH NOT PROVIDED. A THOUROUGH REVIEW OF PIPE SIZING |
| | CANNOT BE COMPLETED W/O TOTAL DEVELOPED LENGTH. |
| | |
| | 5.) FAILED SUBMIT CALCULATIONS FOR COMBUSTION AIR. |
| | PROVIDE VERIFICATION & CALCULATIONS AS TO HOW THE |
| | REQUIREMENTS ARE BEING MET. PROVIDE THE CODE SECTIONS |
| | FROM THE GAS CODE THAT YOU ARE USING IN THE DESIGN OF |
| | THE COMBUSTION AIR REQUIREMENTS PER THE 2017 FBC-FUEL |
| | GAS CODE SEC.304.1, 614.6 (CLOTHES DRYERS) OR 2017 |
| | FBC-RES. SEC.G 2407.1 AND G2439.4 (CLOTHES DRYERS). |
| | REFER TO SECTION G2407.1 EXCEPTION: MAKEUP AIR SHALL BE |
| | PROVIDED FOR DRYERS WITH EXHAUST CAPACITIES OF 200 CFMS |
| | OR MORE. PLEASE SUBMIT THE REQUESTED SPECS FOR THE |
| | DRYER. |
| | |
| | 6) PASSED |
| | |
| | 7) FAILED. SUBMIT TWO COPIES OF A DETAIL SHOWING THE |
| | TYPE OF VENT, LOCATION, SIZE, TERMINATION POINT, HEIGHT |
| | ABOVE THE ROOF AND ANCHORING DETAILS OF THE GAS VENT(S) |
| | PER 2017 FBC-FUEL GAS SECS. 502 THRU 505 OR 2017 |
| | FBC-RES. SEC.G2426 THROUGH G2439. THE ISO AND PLAN |
| | INDICATE THE WH WILL BE LOCATED ON THE EXTERIOR WALL, |
| | BUT THE DETAIL INDICATES A METAL FLUE UP THROUGH THE |
| | ROOF. WILL THE FLUE PASS THROUGH THE SOFFIT AND THEN |
| | THROUGH THE ROOF? PLEASE MODIFY THE DETAIL TO SHOW THE |
| | ACTUAL LOCATION OF THE WH AND VENT, AND INCLUDE THE |
| | REQUESTED ANCHORING DETAILS FOR THE FLUE VENT. |
| | |
| | 8) FAILED. SUBMIT TWO COPIES OF THE MANUFACTURER'S |
| | SPECIFICATION SHEETS / INSTALLATION MANUAL FOR ALL GAS |
| | EQUIPMENT TO VERIFY COMPLIANCE WITH STANDARDS NFPA 54, |
| | NFPA 58, AND FBC-2017 FUEL GAS CODE SEC. 402.2, AND |
| | 301.3 OR 2017 FBC-RES. SEC. G2404.3. GAS APPLIANCES |
| | SHALL BE LISTED AND LABELED. THE INSTALLATION MANUALS |
| | FOR ALL GAS APPLIANCES / EQUIPMENT SHALL BE ONSITE AT |
| | THE TIME OF INSPECTION. FGC SEC.305.1, FBC-RES. |
| | SEC.G2408.1. THE REQUESTED SPECIFICATIONS AND |
| | INSTALLATION MANUALS WERE NOT PROVIDED. |
| | |
| | 9) FAILED. SUBMIT TWO COPIES OF THE APPLICABLE SIZING |
| | TABLES USED TO SIZE THE GAS SYSTEM OR PLACE A NOTE ON |
| | THE PLANS/DRAWINGS SPECIFYING WHICH SIZING TABLE(S) |
| | FROM THE GAS CODE OR OTHER STANDARD THAT WERE USED IN |
| | THE DESIGN OF THIS GAS SYSTEM. REFER TO THE 2017 |
| | FBC-FUEL GAS SECS. 401.4, 401.8, 402.3, AND TABLES |
| | 402.4 (1) THRU 402.4 (37) OR 2017 FBC-RES. SEC. |
| | G2413.3, G2412.8, G2413.1, G2413.2, & G2413.3. TABLE |
| | 402.4(9) CALLED OUT ON THE ISO IS FOR SEMI-RIGID COPPER |
| | TUBING, BUT SCHEDULE 40 METALLIC PIPE IS CALLED OUT FOR |
| | INSTALLATION. |
| | |
| | WHEN RESUBMITTING, IT IS HELPFUL TO PROVIDE A RESPONSE |
| | LETTER ADDRESSING EACH ITEM ALONG WITH THE CITY |
| | RE-SUBMITTAL FORM. |
| | |
| | CHRISTOPHER L. COLE |
| | MECHANICAL/PLUMBING PLANS EXAMINER |
| | 401 CLEMATIS STREET |
| | WEST PALM BEACH FL 33401 |
| | 561-805-6719 |
| | [email protected] |
| | |