| 2020-04-13 11:12:01 | 1) SUBMIT TWO COPIES OF AN ISOMETRIC DRAWING THAT |
| | CLEARLY SHOWS THE LENGTH OF ALL CUT SECTIONS OF PIPE |
| | PER 2017 FBC-FUEL GAS, SECS. 402.4.1, 402.4.2. OR 2017 |
| | FBC-R SEC. G2413.4.1, G2413.4.2. |
| | 2) SHOW THE TYPE OF PIPE MATERIAL BEING INSTALLED, ALL |
| | PIPE SIZES, TYPE OF GAS (LP OR NATURAL). WPB AMEND. TO |
| | FBC SEC. 107.2.1. |
| | 3.) LIST THE BTU LOAD OF EACH APPLIANCE AND THE TOTAL |
| | BTU LOAD ON THE SYSTEM. REFER TO THE 2017 FBC-FUEL GAS |
| | SECS.401.8, 402.2, AND TABLES 402.4 (1) THRU 402.4 (37) |
| | OR 2017 FBC-RES. SEC. G2413.3, G2413.4 AND TABLES |
| | G2413.4 (1 ) THROUGH G2413.4 (21). |
| | 4.) SHOW THE DISTANCE FROM THE POINT OF DELIVERY, (GAS |
| | METER / MP REGULATOR / LP TANK) TO THE MOST REMOTE |
| | OUTLET IN THE BUILDING AND / OR SYSTEM PER THE 2017 |
| | FBC-FUEL GAS SEC.402.4.1, 402.4.2, OR 2017 FBC-RES. |
| | SEC. G 2413.4.1, G2413.4.2. |
| | 5.) SUBMIT CALCULATIONS FOR COMBUSTION AIR. PROVIDE |
| | VERIFICATION & CALCULATIONS AS TO HOW THE REQUIREMENTS |
| | ARE BEING MET. PROVIDE THE CODE SECTIONS FROM THE GAS |
| | CODE THAT YOU ARE USING IN THE DESIGN OF THE COMBUSTION |
| | AIR REQUIREMENTS PER THE 2017 FBC-FUEL GAS CODE |
| | SEC.304.1, 614.6 (CLOTHES DRYERS) OR 2017 FBC-RES. |
| | SEC.G 2407.1 AND G2439.4 (CLOTHES DRYERS). |
| | 6) INDICATE THE DELIVERY PRESSURE (PSI) OF THE SYSTEM |
| | ON THE PLAN PER 2017 FBC-FUEL GAS SEC.402.1, 402.4.3 |
| | THRU 402.6 OR 2017 FBC RES. SEC. G2413.2, G2413.4.3. |
| | 7).SUBMIT TWO COPIES OF A DETAIL SHOWING THE TYPE OF |
| | VENT, LOCATION, SIZE, TERMINATION POINT, HEIGHT ABOVE |
| | THE ROOF AND ANCHORING DETAILS OF THE GAS VENT(S) PER |
| | 2017 FBC-FUEL GAS SECS. 502 THRU 505 OR 2017 FBC-RES. |
| | SEC.G2426 THROUGH G2439. |
| | 8.) SUBMIT TWO COPIES OF THE MANUFACTURER?S |
| | SPECIFICATION SHEETS / INSTALLATION MANUAL FOR ALL GAS |
| | EQUIPMENT TO VERIFY COMPLIANCE WITH STANDARDS NFPA 54, |
| | NFPA 58, AND FBC-2017 FUEL GAS CODE SEC. 402.2, AND |
| | 301.3 OR 2017 FBC-RES. SEC. G2404.3. GAS APPLIANCES |
| | SHALL BE LISTED AND LABELED. THE INSTALLATION MANUALS |
| | FOR ALL GAS APPLIANCES / EQUIPMENT SHALL BE ONSITE AT |
| | THE TIME OF INSPECTION. FGC SEC.305.1, FBC-RES. |
| | SEC.G2408.1. |
| | 9) SUBMIT TWO COPIES OF THE APPLICABLE SIZING TABLES |
| | USED TO SIZE THE GAS SYSTEM OR PLACE A NOTE ON THE |
| | PLANS/DRAWINGS SPECIFYING WHICH SIZING TABLE(S) FROM |
| | THE GAS CODE OR OTHER STANDARD THAT WERE USED IN THE |
| | DESIGN OF THIS GAS SYSTEM. REFER TO THE 2017 FBC-FUEL |
| | GAS SECS. 401.4, 401.8, 402.3, AND TABLES 402.4 (1) |
| | THRU 402.4 (37) OR 2017 FBC-RES. SEC. G2413.3, G2412.8, |
| | G2413.1, G2413.2, & G2413.3. |
| | 10) A SEPARATE PERMIT IS REQUIRED FOR THE GAS |
| | INSTALLATION. |
| | |
| | TIM LARGE |
| | CHIEF PLUMBING INSPECTOR |
| | PLUMBING PLAN REVIEW |
| | 561-805-6692 |
| | [email protected] |
| | |
| | NOTE - A COMPLETE AND THOROUGH REVIEW COULD NOT BE DONE |
| | AT THIS TIME DUE TO THE LACK OF REQUIRED INFORMATION ON |
| | THE PLANS / DRAWINGS AND ADDITIONAL PLAN REVIEW |
| | COMMENTS MAY BE GENERATED UPON THE RE-REVIEW OF |
| | SUBMITTED CORRECTIONS. |
| | |
| | |