| 2021-01-12 16:10:47 | BUILDING REVIEW COMMENTS: |
| | |
| | W.P.B. PERMIT: 20031093 |
| | 2ND REVIEW: JANUARY 12, 2021 |
| | ROBERT MCDOUGAL, CBO |
| | COMMERCIAL COMBINATION PLANS EXAMINER |
| | (561) 805-6714 |
| | [email protected] |
| | |
| | FLORIDA BUILDING CODE,6TH EDITION (2014) |
| | FBC[AMENDED] = 2017 CHAPTER 1 WPB AMENDMENTS (SEE LINK |
| | BELOW) |
| | HTTPS://WPB.ORG/DEPARTMENTS/DEVELOPMENT-SERVICES/FORMS/ |
| | BUILDING-PERMIT-FORMS |
| | FBC[B] = FBC BUILDING |
| | FBC[A] = FBC ACCESSIBILITY |
| | FBC[E] = FBC ENERGY CONSERVATION |
| | |
| | REVISION DENIED. |
| | |
| | 1) THE SHOP DRAWINGS AND PRODUCT APPROVALS HAVE NOT |
| | BEEN REVIEWED AND APPROVED IN WRITING BY THE DESIGNER |
| | OF RECORD (SHOP DRAWING APPROVAL STAMP). ON A THRESHOLD |
| | BUILDING THEY ARE TYPICALLY REVIEWED BY THE ENGINEER, |
| | ARCHITECT AND CONTRACTOR AND STAMPED APPROVED BEFORE |
| | THE ARE SUBMITTED TO THE BUILDING DEPARTMENT FOR |
| | REVIEW. THIS HELPS TO ENSURE THAT EVERYONE IS ON THE |
| | SAME PAGE. FBC 107.3.4 [AMENDED] - PROVIDE TWO SETS OF |
| | PRODUCT APPROVALS FOR THOSE PRODUCTS WHICH ARE |
| | REGULATED BY FAC 61G20-3.001 PER FLORIDA STATUTE |
| | 553.842 (5) THAT HAVE BEEN REVIEWED AND APPROVED IN |
| | WRITING BY THE DESIGNER OF RECORD. PROVIDE TWO COMPLETE |
| | PRODUCT APPROVALS WITH FL OR NOA NUMBERS INCLUDING |
| | INSTALLATION INSTRUCTIONS AND MAXIMUM DESIGN PRESSURES |
| | FOR EACH OF THE DIFFERENT ROOFING MATERIALS, WINDOW |
| | (GLASS TYPES), STRUCTURAL MULLIONS AND EXTERIOR DOOR |
| | TYPES. THESE ITEMS CAN BE DEFERRED IF REQUESTED, |
| | HOWEVER, THE DOCUMENTS MUST BE SUBMITTED AND APPROVED |
| | BY THE BUILDING DEPARTMENT BEFORE THEY CAN BE |
| | INSTALLED. ONLY ONE SET IS REQUIRED TO BE UPLOADED FOR |
| | ELECTRONICALLY SUBMITTED DOCUMENTS. |
| | |
| | 2) 107.3.4.1 FBC[AMENDED]THERE ARE PRODUCT APPROVALS IN |
| | 18100540 THAT ARE UNDER REVIEW. IF THOSE ARE TO BE PART |
| | OF CURRENT REVISION THEN THOSE WILL NEED TO BE PROVIDED |
| | SINCE THIS REVISION IS FOR 16060825 |
| | PLEASE MAKE SURE THAT ANY PRODUCT APPROVAL IS STAMPED |
| | REVIEWED AND APPROVED BY THE DESIGNER OF RECORD. |
| | |
| | 3) I DID NOT SEE THE PRODUCT APPROVAL FOR THE STORE |
| | FRONT SWING DOORS IN THE SUBMITTAL DOCUMENTS. PLEASE |
| | SUBMIT THE PRODUCT APPROVALS STAMPED APPROVED BY THE |
| | D.O.R. FBC 107.3.4 [AMENDED] |
| | |
| | 4) ON SHEET C02 #S 5 AND 6 UNDER PRODUCTS IT STATES |
| | THAT THE TEST REPORT FOR GL-5 (SLIDING GLASS DOORS AND |
| | WINDOW WALL SYSTEMS) IS PENDING. PLEASE CLARIFY. FBC |
| | 107.3.4 [AMENDED] |
| | |
| | 5) ALSO ON SHEET C02 UNDER PRODUCTS, NOA NO. 09-0812.14 |
| | IS SPECIFIED. THIS IS AN EXPIRED NOA. IT WAS REPLACED |
| | BY NOA NO. 18-0926.04, WHICH IS THE ONE THAT WAS |
| | SUBMITTED WITH THE WINDOW AND DOOR SUBMITTAL DOCUMENTS. |
| | PLEASE NOTE ON PLANS. FBC 107.3.4 [AMENDED] |
| | |
| | 6) IF THERE ARE ANY ITEMS INCLUDED IN THIS REVISION |
| | THAT REQUIRE SHOP DRAWINGS, PRODUCT APPROVALS OR |
| | ENGINEERING REPORTS THAT YOU WISH TO DEFER TO A LATER |
| | TIME, PROVIDE A LIST OF THOSE ITEMS ON THE PLANS. THESE |
| | ITEMS WILL STILL HAVE TO BE SUBMITTED AND APPROVED BY |
| | THE BUILDING DEPARTMENT BEFORE THEY ARE INSTALLED. FBC |
| | 107.3.4.1[AMENDED] DEFERRED SUBMITTALS. FOR THE |
| | PURPOSES OF THIS SECTION, DEFERRED SUBMITTALS ARE |
| | DEFINED AS THOSE PORTIONS OF THE DESIGN THAT ARE NOT |
| | SUBMITTED AT THE TIME OF THE APPLICATION AND THAT ARE |
| | TO BE SUBMITTED TO THE BUILDING OFFICIAL WITHIN A |
| | SPECIFIED PERIOD. DEFERRAL OF ANY SUBMITTAL ITEMS SHALL |
| | HAVE THE PRIOR APPROVAL OF THE BUILDING OFFICIAL. THE |
| | REGISTERED DESIGN PROFESSIONAL IN RESPONSIBLE CHARGE |
| | SHALL LIST THE DEFERRED SUBMITTALS ON THE CONSTRUCTION |
| | DOCUMENTS FOR REVIEW BY THE BUILDING OFFICIAL. THE |
| | REGISTERED DESIGN PROFESSIONAL IN RESPONSIBLE CHARGE |
| | SHALL LIST THE DEFERRED SUBMITTALS ON THE CONSTRUCTION |
| | DOCUMENTS FOR REVIEW BY THE BUILDING OFFICIAL. |
| | DOCUMENTS FOR DEFERRED SUBMITTAL ITEMS SHALL BE |
| | SUBMITTED TO THE REGISTERED DESIGN PROFESSIONAL IN |
| | RESPONSIBLE CHARGE WHO SHALL REVIEW THEM AND FORWARD |
| | THEM TO THE BUILDING OFFICIAL WITH A NOTATION |
| | INDICATING THAT THE DEFERRED SUBMITTAL DOCUMENTS HAVE |
| | BEEN REVIEWED AND FOUND TO BE IN GENERAL CONFORMANCE TO |
| | THE DESIGN OF THE BUILDING. THE DEFERRED SUBMITTAL |
| | ITEMS SHALL NOT BE INSTALLED UNTIL THE DEFERRED |
| | SUBMITTAL DOCUMENTS HAVE BEEN APPROVED BY THE BUILDING |
| | OFFICIAL. |
| | |
| | 7) DUE TO THIS REVISION BEING APPLICABLE TO SPECIFIC |
| | PORTIONS OF THE BUILDING, PLEASE PROVIDE A NARRATIVE |
| | FROM THE DESIGNER OF RECORD THAT IS SPECIFIC AND |
| | CLEARLY DETAILS THE PARAMETERS OF THIS REVISION. FBC |
| | 107.2.1 [AMENDED] |
| | |
| | 8) PLEASE PROVIDE A RESPONSE LETTER THAT EXPLAINS HOW |
| | EACH OF THE COMMENTS HAS BEEN ADDRESSED. THIS IS VERY |
| | HELPFUL TOWARDS GETTING YOUR DOCUMENTS APPROVED IN A |
| | TIMELY MANNER. THANKS. IF YOU HAVE ANY QUESTIONS PLEASE |
| | CONTACT ME. MY CONTACT INFORMATION IS PROVIDED AT THE |
| | TOP OF THIS REVIEW. |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |