| Date |
Text |
| 2021-08-10 17:11:02 | FAILED |
| | |
| | PROVIDE WRITTEN RESPONSES TO PLANS. |
| | |
| | 1) THE MINOR PLANNED DEVELOPMENT AMENDMENT REVIEWED BY |
| | STAFF DID NOT PASS PLANNING AS THE BUILDING HAS SHIFTED |
| | AND NO LONGER MEETS MANY OF THE MINIMUM SETBACK |
| | REQUIREMENTS. ZONING WILL NOT PASS THE FOUNDATION |
| | PERMIT UNTIL THE MINOR PLANNED DEVELOPMENT AMENDMENT |
| | PASSES. ALL PLANS RESUBMITTED WITH THIS PERMIT MUST |
| | MATCH THE PLANS APPROVED AS PART OF THE MINOR PLANNED |
| | DEVELOPMENT AMENDMENT. PREVIOUSLY RAISED COMMENTS FOR |
| | THIS PERMIT THAT WILL BE COVERED AS PART OF THE MINOR |
| | PLANNED DEVELOPMENT AMENDMENT REVIEW/APPROVAL HAVE BEEN |
| | REMOVED. |
| | |
| | 2) UPDATED COMMENT: RESOLUTION 13-19, WHICH APPROVED |
| | THE PROJECT INCLUDED THE REQUIREMENT THAT CERTAIN ITEMS |
| | REQUIRED PRIOR TO THE SUBMITTAL OF THE BUILDING PERMIT |
| | FOR SITE IMPROVEMENTS, WHICH INCLUDES THE FOUNDATION |
| | PERMIT. PROVIDE EVIDENCE THAT THE FOLLOWING HAVE BEEN |
| | COMPLETED: |
| | |
| | A. ABANDON OR RELOCATE THE FPL EASEMENT ALONG THE SOUTH |
| | PROPERTY LINE. THE DEVELOPER, BASED ON DISCUSSIONS WITH |
| | FPL, PRESENTED A TEMPORARY POWER ROUTING PLAN TO CITY |
| | STAFF; HOWEVER, THE FINAL PLAN AND FPL'S SIGN OFF ARE |
| | NOT INCLUDED WITH THE RESUBMITTAL. SHEET E1.050 DOES |
| | NOT SPECIFY WHEN THE EASEMENT WILL BE ABANDONED. |
| | |
| | 3) REPEAT COMMENT: PROVIDE INFORMATION ON THE PILING |
| | INSTALLATION: RESOLUTION 13-19 REQUIRES THAT THE |
| | PROJECT SHALL NOT USE HYDRAULIC HAMMERS TO SET |
| | FOUNDATION PILES. IF FOUNDATION PILES ARE PROPOSED THEY |
| | SHALL BE AUGURED, DRILLED, VIBRATED, OR PRESSED INTO |
| | PLACE. SHEET PILING MAY BE INSTALLED USING VIBRATORS, |
| | HYDRO JETTING, OR HYDRAULIC JACK PRESSING EQUIPMENT TO |
| | STABILIZE THE PERIMETER OF THE SITE TO ACCOMMODATE THE |
| | EXCAVATION AND CONSTRUCTION OF THE SUBGRADE BASEMENT |
| | AND RETAINING WALLS. |
| | |
| | 4) REPEAT COMMENT: PROVIDE INFORMATION ON THE REQUIRED |
| | CONDITION SURVEY: RESOLUTION 13-19 REQUIRES THAT THE |
| | DEVELOPER SHALL PERFORM A CONDITION SURVEY OF THE |
| | ADJOINING PROPERTIES PRIOR TO THE COMMENCEMENT OF ANY |
| | CONSTRUCTION OR DEMOLITION ACTIVITIES. THE DEVELOPER |
| | SHALL CONFORM TO THE APPROPRIATE INDUSTRY STANDARDS |
| | APPROVED BY THE CITY'S BUILDING DIVISION IN MONITORING |
| | THE VIBRATION EFFECTS ON THE ADJOINING PROPERTIES; THIS |
| | MAY INCLUDE, BUT IS NOT LIMITED TO, THE PLACEMENT OF |
| | SEISMIC METERS, INSPECTIONS, AND SIMILAR ACTIVITIES. |
| | |
| | 5) EV PROVISIONS - ZONING STAFF HAS REVIEWED AND NEEDS |
| | CLARIFICATION NARRATIVE ON THE EV PROVISION. COMMENTS |
| | BELOW MAY CHANGE BASED ON THE NARRATIVE. THE NARRATIVE |
| | SHALL VERIFY THE RESOLUTION NO. 13-19 EV REQUIREMENTS. |
| | |
| | A. THE B1 ELECTRIC PLANS DO NOT SHOW EV LEVEL 1 |
| | CIRCUITS TO THE GARAGE SPACES ALONG THE SOUTH WALL. |
| | PLEASE EXPLAIN. |
| | |
| | B. IT APPEARS THAT THE GUEST SPACES ARE ONLY GETTING EV |
| | LEVEL 1, INSTEAD OF THE LEVEL 2 THAT ARE REQUIRED. NOTE |
| | ONLY TWO SPACES ARE REQUIRED TO HAVE EV LEVEL 2. |
| | |
| | 4) REPEAT COMMENT: THE SURVEY PROVIDED WITH THE PERMIT |
| | IS NOT THE LATEST SURVEY. PROVIDE THE CORRECT SURVEY. |
| | |
| | 5) REPEAT COMMENT: THE SITE PLAN NEEDS TO INCLUDE ALL |
| | THE SETBACK DIMENSIONS TO THE ELEMENTS OF THE SITE THAT |
| | ARE PART OF THE FOUNDATION. |
| | |
| | 8) THE ABOVE GRADE IMPROVEMENTS REQUIRE REVIEW AS |
| | SEPARATE PERMITS WITH PLANS: |
| | |
| | A. THE WALLS, FENCES, GATES AND COLUMNS REQUIRE A |
| | SEPARATE PERMIT WITH PLANS. |
| | B. HARDSCAPE, INCLUDING PAVERS, ARTIFICIAL TURF, DOG |
| | PARK ITEMS, BENCHES/PLAZA AREA, ETC. |
| | C. LANDSCAPE |
| | D. IRRIGATION |
| | E. GENERATOR - PLEASE NOTE THAT THE FULL HEIGHT OF THE |
| | GENERATOR DOES NOT APPEAR TO BE SCREENED AS REQUIRED BY |
| | RESOLUTION NO. 13-19. |
| | F. WATER FEATURES |
| | G. PARKING STRIPING |
| | H. SITE LIGHTING, INCLUDING BOLLARDS, NOTE: SINCE |
| | ACACIA ROAD IS A SEPARATE PARCEL, IT REQUIRES ITS OWN |
| | PERMIT FOR THE LIGHTING, BUT MAY BE INCLUDED ON ONE SET |
| | OF PLANS FOR BOTH PERMIT NUMBERS. PHOTOMETRIC PLANS ARE |
| | REQUIRED WITH THE PERMITS. |
| | I. BICYCLE RACKS, INCLUDES THE BICYCLE STORAGE ROOM. |
| | |
| | 9) ACACIA ROAD IS A SEPARATE PARCEL. ALL PLANS SHOWING |
| | THE ACACIA ROAD WORK ARE TO BE REVIEWED AND APPROVED |
| | UNDER A SEPARATE PERMIT. |
| | |
| | CONTACT ERIC SCHNEIDER @ (561) 822-1446 |
| | [email protected] |
| | |