| 2020-06-19 15:25:46 | ADDITIONAL BUILDING REVIEW COMMENTS. |
| | |
| | ****CORRECTIONS**** |
| | |
| | ROBERT MCDOUGAL |
| | BUILDING PLANS EXAMINER |
| | [email protected] |
| | 561-805-6714 |
| | |
| | FBC = FLORIDA BUILDING CODE, 6TH EDITION (2017) |
| | FBC B = FBC BUILDING |
| | FBC R = FBC RESIDENTIAL |
| | FBC EB = FBC EXISTING BUILDING |
| | FBC A = FBC ACCESSIBILITY |
| | FBC EC = FBC ENERGY CONSERVATION |
| | |
| | THE FOUNDATION PERMIT HAS BEEN DENIED FOR THE FOLLOWING |
| | REASONS. |
| | |
| | 1) THE PERMIT TO CONSTRUCT THE BUILDING HAS NOT BEEN |
| | APPLIED FOR AT THIS TIME. TYPICALLY THE PERMIT TO |
| | CONSTRUCT THE BUILDING HAS BEEN APPLIED FOR AND THE |
| | PLANS FOR CONSTRUCTION HAVE REVIEWED BEFORE A PERMIT |
| | FOR A FOUNDATION ONLY PERMIT IS APPLIED FOR. UNLESS THE |
| | PLANS FOR THE BUILDING HAVE BEEN REVIEWED AND APPROVED, |
| | THE FOUNDATION ONLY PERMIT WILL BE ISSUED AS A PROCEED |
| | AT YOUR ON RISK PERMIT. FBC 107.3.3 PHASED APPROVAL. |
| | (SEE ALSO SECTION 105.13.) THE BUILDING OFFICIAL IS |
| | AUTHORIZED TO ISSUE A PERMIT FOR THE CONSTRUCTION OF |
| | FOUNDATIONS OR ANY OTHER PART OF A BUILDING OR |
| | STRUCTURE BEFORE THE CONSTRUCTION DOCUMENTS FOR THE |
| | WHOLE BUILDING OR STRUCTURE HAVE BEEN SUBMITTED, |
| | PROVIDED THAT ADEQUATE INFORMATION AND DETAILED |
| | STATEMENTS HAVE BEEN FILED COMPLYING WITH PERTINENT |
| | REQUIREMENTS OF THIS CODE. THE HOLDER OF SUCH PERMIT |
| | FOR THE FOUNDATION OR OTHER PARTS OF A BUILDING OR |
| | STRUCTURE SHALL PROCEED AT THE HOLDER'S OWN RISK |
| | WITH THE BUILDING OPERATION AND WITHOUT ASSURANCE THAT |
| | A PERMIT FOR THE ENTIRE STRUCTURE WILL BE GRANTED. THIS |
| | PROVISION ONLY APPLIES TO THE FLORIDA BUILDING CODE; |
| | ALL OTHER AGENCY |
| | APPROVALS NECESSARY FOR CONSTRUCTION MUST BE SECURED |
| | PRIOR TO THIS PROVISION BEING APPLIED. |
| | |
| | 2)A PORTION OF THE PROPERTY IS LOCATED IN AN AE FLOOD |
| | ZONE WHICH IS A SPECIAL FLOOD HAZARD AREA. IT APPEARS |
| | THAT THE BUILDING AND THE EQUIPMENT SERVICING IT ARE |
| | NOT LOCATED IN THE AE FLOOD ZONE. IT APPEARS THAT SHEET |
| | C5.00 HAS THE X AND X500 FLOOD ZONES REVERSED. FROM |
| | EAST TO WEST THE FLOOD ZONES ARE AE, X500 AND X. PLEASE |
| | CORRECT. |
| | |
| | 3) ON SHEET 00.200 UNDER BUILDING TYPE THAT REFERENCES |
| | THE 2010 FBC AND THIS PROJECT FALLS UNDER THE 2017 FBC. |
| | |
| | 4) THIS PROJECT EXPANDS OVER MULTIPLE LOTS OR PARCELS |
| | OF LAND. THIS WILL HAVE TO BE ADDRESSED PRIOR TO PERMIT |
| | ISSUANCE. FBC 107.2.1 |
| | |
| | 5) AN MOT PLAN IS REQUIRED TO BE APPROVED BEFORE PERMIT |
| | ISSUANCE. IN ADDITION TO TRAFFIC CONTROL, THE PLAN |
| | SHOULD INCLUDE LOCATION OF STAGING AREAS, CONSTRUCTION |
| | TRAILER LOCATIONS, EMPLOYEE PARKING DURING |
| | CONSTRUCTION, EMERGENCY FIRE DEPARTMENT ACCESS, SITE |
| | FENCING (SAFEGUARDS DURING CONSTRUCTION), HOURS OF |
| | WORK, ETC. FBC 107 |
| | |
| | 6) THIS IS A THRESHOLD BUILDING. SUBMIT THE REQUIRED |
| | THRESHOLD DOCUMENTS WITH ORIGINAL SIGNATURES AND COMPLY |
| | WITH THE OTHER THRESHOLD REQUIREMENTS. THRESHOLD |
| | BUILDING / FL S. S. 553.71(7) "THRESHOLD BUILDING" |
| | MEANING ANY BUILDING WHICH IS GREATER THAN (3) STORIES |
| | OR 50 FT. IN HEIGHT, OR WHICH HAS AN ASSEMBLY OCCUPANCY |
| | CLASSIFICATION AS DEFINED IN THE FLORIDA BUILDING CODE |
| | WHICH EXCEEDS 5,000 SQ. FT. IN AREA AND AN OCCUPANT |
| | CONTENT OF GREATER THAN 500 PERSONS. |
| | |
| | A)FBC (CITY AMENDMENTS)110.8.1 THRESHOLD INSPECTION |
| | PLAN. THE ENFORCING AGENCY SHALL REQUIRE A SPECIAL |
| | INSPECTOR TO PERFORM STRUCTURAL INSPECTIONS ON A |
| | THRESHOLD BUILDING PURSUANT TO A STRUCTURAL INSPECTION |
| | PLAN PREPARED BY THE ENGINEER OF RECORD. THE STRUCTURAL |
| | INSPECTION PLAN MUST BE SUBMITTED TO THE ENFORCING |
| | AGENCY PRIOR TO THE ISSUANCE OF A BUILDING PERMIT FOR |
| | THE CONSTRUCTION OF A THRESHOLD BUILDING. THE PURPOSE |
| | OF THE STRUCTURAL INSPECTION PLAN IS TO PROVIDE |
| | SPECIFIC INSPECTION PROCEDURES AND SCHEDULES SO THAT |
| | THE BUILDING CAN BE ADEQUATELY INSPECTED FOR COMPLIANCE |
| | WITH THE PERMITTED DOCUMENTS. (I SAW THAT A THRESHOLD |
| | INSPECTION PLAN IS PROVIDED ON SHEET S0-003.) |
| | |
| | B) THRESHOLD INSPECTOR: WPB AMENDMENT 110.8.1 W.P.B. |
| | CONSTRUCTION SERVICES DEPARTMENT REQUEST FOR THRESHOLD |
| | BUILDINGS A SPECIAL INSPECTOR AS REQUIRED BY 553.79(5) |
| | FLORIDA STATUTES TO THE MINIMUM INSPECTIONS REQUIRED BY |
| | THIS CODE. THE THRESHOLD INSPECTION FORMS ARE REQUIRED |
| | TO BE FILED OUT BY ALL PARTIES WITH INTEREST, NOTARIZED |
| | AND RETURNED TO THIS OFFICE, AND REVIEWED AND APPROVED |
| | BEFORE PERMIT ISSUANCE WILL TAKE PLACE. |
| | |
| | C) THRESHOLD BLDG. REQUIRED STATEMENT: W.P.B. AMENDMENT |
| | 110.8.4.4 ALL PLANS FOR THE BUILDING WHICH ARE REQUIRED |
| | TO BE SIGNED AND SEALED BY THE ARCHITECT OR ENGINEER OF |
| | RECORD CONTAIN A STATEMENT THAT, TO THE BEST OF THE |
| | ARCHITECT'S OR ENGINEER'S KNOWLEDGE, THE PLANS AND |
| | SPECIFICATIONS COMPLY WITH THE APPLICABLE MINIMUM |
| | BUILDING CODES AND THE APPLICABLE FIRE-SAFETY STANDARDS |
| | AS DETERMINED BY THE LOCAL AUTHORITY IN ACCORDANCE WITH |
| | THIS SECTION AND CHAPTER 633 FLORIDA STATUTES. |
| | |
| | D) FOR THE SPECIAL INSPECTOR PLEASE PROVIDE A RESUME OF |
| | INSPECTION EXPERIENCE ON PREVIOUS PROJECT. THE RESUME |
| | MUST BE ACCOMPANIED BY ALL CERTIFICATES AS SPECIFIED |
| | HEREIN. THE BUILDING OFFICIAL OR HIS DESIGNEE WILL |
| | REVIEW THE RESUME. AFTER THE RESUME IS REVIEWED, AN |
| | INTERVIEW WILL BE SCHEDULED. UNDER NO CIRCUMSTANCES |
| | WILL AN INSPECTOR BE INTERVIEWED FOR WORK WITHOUT FIRST |
| | MEETING THE ABOVE CRITERIA. |
| | |
| | E) THE CONTRACTOR WILL PRODUCE A JOB SUMMARY OR HISTORY |
| | FOR THIS TYPE OF CONSTRUCTION. |
| | |
| | F) NOTE: FOR DIGITAL PLANS, AFTER PERMIT ISSUANCE, |
| | PLEASE E-MAIL THE PERMIT LIBRARIAN OF THE PERMIT BEING |
| | ISSUED, THE PERMIT LIBRARIAN WILL THEN E-MAIL YOU THE |
| | APPROVED AND BATCH STAMPED PLANS SO YOU MAY PRINT YOUR |
| | PLANS, TWO SETS OF PLANS WILL NEED TO BE PRINTED IN |
| | COLOR, (1) FOR THE THRESHOLD INSPECTOR, THE OTHER FOR |
| | THE MEP INSPECTORS OTHER PLANS YOU WISH TO PRINT MAYBE |
| | IN BLACK & WHITE. |
| | |
| | G) 110.8.4.3 ALL SHORING AND RESHORING PROCEDURES, |
| | PLANS AND DETAILS SHALL BE SUBMITTED TO THE ENFORCEMENT |
| | AGENCY FOR RECORDKEEPING. EACH SHORING AND RESHORING |
| | INSTALLATION SHALL BE SUPERVISED, INSPECTED AND |
| | CERTIFIED TO BE IN COMPLIANCE WITH THE SHORING |
| | DOCUMENTS BY THE CONTRACTOR. |
| | |
| | H) PLEASE CALL THE CITY OF WEST PALM BEACH'S AUTOMATED |
| | TELEPHONE INSPECTIONS LINE (561) 805-6700 FOR ALL |
| | BUILDING INSPECTIONS FOR AUDITING OF JOBSITE |
| | INSPECTIONS WITHOUT THIS THE PERMIT EXPIRES IN 6 |
| | MONTHS, ABANDONMENT OF JOB, NO INSPECTION ACTIVITY. |
| | |
| | I) 110.8 THRESHOLD BUILDINGS, OPERATING GUIDELINES FOR |
| | THRESHOLD INSPECTORS #25. ASSURE THAT THE DESIGNER HAS |
| | REQUIRED ON THE PLANS OR SPECIFICATIONS ONE MATERIAL, |
| | APPROVED FOR FIRE STOPPING PENETRATIONS, FOR WALLS AND |
| | CEILINGS. |
| | |
| | J) PLEASE CONTACT ME WITH AN EMAIL ADDRESS AND I WILL |
| | BE HAPPY TO SEND YOU A COPY OF THE CURRENT (OCTOBER |
| | 2018) GUIDELINES AND POLICIES FOR PROJECTS CONCERNING |
| | THRESHOLD/SPECIAL INSPECTORS AND RESIDENT INSPECTORS. |
| | |
| | 7) THE PILE INSTALLATION PLANS ARE REQUIRED TO BE |
| | SUBMITTED AND APPROVED BY THE ENGINEER OF RECORD FOR |
| | THE PROJECT PRIOR TO COMMENCEMENT OF OPERATIONS. FBC |
| | 107 |
| | |
| | 8) ON SHEET S0-001, THE MEAN ROOF HEIGHT WAS LEFT BLANK |
| | UNDER THE WIND CRITERIA DESIGN DATA. FBC 107 |
| | |
| | 9) SOME OF THE PLANS, SUCH AS THE DELIVERY MANAGEMENT |
| | PLANS, ARE MARKED NOT FOR CONSTRUCTION. PLANS THAT ARE |
| | SUBMITTED FOR THE PURPOSE OF OBTAINING A PERMIT CAN NOT |
| | HAVE THIS STATEMENT ON THEM. FBC 107 |
| | |
| | 10) NOTE #8 ON SHEET A1.1B1 STATES THAT THE MINIMUM |
| | CLEARANCE ABOVE PARKING STALLS IS 7'-0" AFF. FBC |
| | ACCESSIBILITY SECTION 502.5 REQUIRES THE VERTICAL |
| | CLEARANCE FOR ACCESSIBILE VAN PARKING SPACES, ACCESS |
| | AISLES AND VECHICULAR ROUTES IS 98" OR 8'- 2". |
| | |
| | 11) SHOW THAT THERE IS AT LEAST ONE ELEVATOR THAT IS |
| | CAPBALE OF ACCOMODATING AN AMBULANCE STRETCHER IN THE |
| | HORIZONTAL OPEN POSITION AS REQUIRED BY FBC 3002.4 |
| | |
| | 12) FBC 3007.6 REQUIRES A FIRE SERVICE ACCESS ELEVATOR |
| | TO OPEN INTO A FIRE SERVICE ACCESS ELEVATOR LOBBY. FBC |
| | 3007.6.4 REQUIRES THE LOBBY SIZE TO BE A MINIMUM OF 150 |
| | SQUARE FEET WITH NO DIMENSION LESS THAN 8 FEET IN |
| | DIMENSION. THE FIRE SERVICE ACCESS ELEVATOR LOBBIES |
| | HAVE A DIMENSION OF 6 FEET. DOES THIS DESIGN USE FBC |
| | 3007.6 EXCEPTION #2 WHICH ALLOWS A 6 FT WIDE, 150 SQFT |
| | EXIT ACCESS CORRIDOR WITH THE PRESSURIZED FIRE ACCESS |
| | ELEVATORS AND FLOOR TO FLOOR SMOKE CONTROL? PLEASE |
| | CLARIFY. |
| | |
| | 13) IN ORDER TO PREVENT BEING OVER CHARGED FOR THE |
| | BUILDING PERMITS, PROVIDE A COST BREAKDOWN OF THE |
| | PROJECT. SEPARATE THE COSTS ASSOCIATED WITH THE |
| | FOUNDATION PERMIT FROM THE ITEMS THAT REQUIRE SEPARATE |
| | PERMITS. FBC 109 |
| | |
| | 14) IN ORDER TO DETERMINE PERCENTAGE OF ALLOWABLE |
| | OPENINGS, SUBMIT A SITE PLAN THAT SHOWS THE DISTANCE |
| | FROM THE EXTERIOR WALLS OF THE BUILDING TO PROPERTY |
| | LINES. FBC 705.8 |
| | |
| | 15) WHEN RESUBMITTING, IT IS HELPFUL TO PROVIDE A |
| | RESPONSE LETTER ADDRESSING EACH ITEM ALONG WITH THE |
| | CITY RE-SUBMITTAL FORM. ADDITIONAL COMMENTS MAY BE |
| | GENERATED BY THE RESPONSES. |
| | |
| | |
| | |
| 2020-06-08 09:20:53 | NEW RESIDENTIAL HI RISE "FOUNDATION ONLY" |
| | REVIEWED BY ROGER MCPHERSON |
| | 561-805-6716 |
| | [email protected] |
| | |
| | CORRECTIONS NEEDED - FBC WPB AMENDMENTS 107 |
| | 1) EXIT STAIRWAYS SHALL TERMINATE AT AN EXIT DISCHARGE |
| | OR A PUBLIC WAY. THE STAIRWAYS CANNOT CONTINUE TO THE |
| | BASEMENT NOR SHALL THEY CONTINUE UP FROM THE BASEMENT |
| | BEYOND THE EXIT DISCHARGE. FBC 1023.3 -AND- 1023.11.1 |
| | 2) DOORS SHOWN IN STAIRWAY "B" DRAWING (LS1.102) NEED |
| | TO COMPLY WITH FBC 1010.1.8 |
| | 3) PLEASE SHOW THE TERMITE PROTECTION REQUIREMENT PER |
| | FBC 1816 |
| | 4) PLEASE COMPLETE A "THRESHOLD/SPECIAL INSPECTOR |
| | AGREEMENT OF UNDERSTANDING" FORM. ( FORMS CAN BE |
| | OBTAINED BY E MAILING [email protected]) |
| | 5) FBC 1016.2 EGRESS THROUGH INTERVENING SPACES. |
| | EGRESS THROUGH INTERVENING SPACES SHALL COMPLY WITH |
| | THIS SECTION. |
| | 1.EXIT ACCESS THROUGH AN ENCLOSED ELEVATOR LOBBY IS |
| | PERMITTED. ACCESS TO NOT LESS THAN ONE OF THE REQUIRED |
| | EXITS SHALL BE PROVIDED WITHOUT TRAVEL THROUGH THE |
| | ENCLOSED ELEVATOR LOBBIES REQUIRED BY SECTION 3006. |