| 2020-03-11 11:08:05 | THIS PLAN WAS REVIEWED AND FAILED BY PETER LEDUC, FIRE |
| | MARSHAL, WITH THE FOLLOWING COMMENTS: |
| | |
| | |
| | 1A) DOES THE SUBMITTING AND INSTALLING CONTRACTOR HAVE |
| | A FCC LICENSE? |
| | |
| | PLEASE PROVIDE. |
| | |
| | |
| | |
| | 1B) THERE IS NO HEAT MAP / COLOR SPECTRUM REPORT OF |
| | EACH FLOOR PLAN SHOWING THE AREAS THAT WOULD REQUIRE |
| | ENHANCEMENT. |
| | |
| | 24.5.2.2 RADIO COVERAGE. RADIO COVERAGE SHALL BE |
| | PROVIDED |
| | THROUGHOUT THE BUILDING AS A PERCENTAGE OF FLOOR AREA |
| | AS SPECIFIED |
| | IN 24.5.2.2.1 THROUGH 24.5.2.2.3. |
| | 24.5.2.2.1 CRITICAL AREAS. CRITICAL AREAS, SUCH AS THE |
| | FIRE COMMAND |
| | CENTER(S), THE FIRE PUMP ROOM(S), EXIT STAIRS, EXIT |
| | PASSAGEWAYS, |
| | ELEVATOR LOBBIES, STANDPIPE CABINETS, SPRINKLER |
| | SECTIONAL |
| | VALVE LOCATIONS, AND OTHER AREAS DEEMED CRITICAL BY THE |
| | AUTHORITY HAVING JURISDICTION, SHALL BE PROVIDED WITH |
| | 99 PERCENT |
| | FLOOR AREA RADIO COVERAGE. |
| | 24.5.2.2.2 GENERAL BUILDING AREAS. GENERAL BUILDING |
| | AREAS |
| | SHALL BE PROVIDED WITH 90 PERCENT FLOOR AREA RADIO |
| | COVERAGE. |
| | |
| | PLEASE PROVIDE A REPORT SHOWING ALL AREAS, THUS |
| | DEFENDING THE POSITION OF THE EQUIPMENT |
| | |
| | |
| | 2) THERE IS AN INDICATION OF RUNNING CABLE UP THROUGH |
| | EXISTING PENETRATIONS. |
| | |
| | PLEASE BE SPECIFIC AND IDENTIFY THOSE PENETRATIONS. |
| | |
| | |
| | 3) THERE ARE NO PRODUCT SHEETS INDUCING LISTINGS AND |
| | COMBATABILITY. |
| | |
| | 24.5.2.5.2 COMPONENT ENCLOSURES. ALL REPEATER, |
| | TRANSMITTER, RECEIVER, |
| | SIGNAL BOOSTER COMPONENTS, AND BATTERY SYSTEM |
| | COMPONENTS |
| | SHALL BE CONTAINED IN A NEMA4- OR 4X-TYPE ENCLOSURE(S). |
| | |
| | PLEASE PROVIDE. |
| | |
| | |
| | 4) THERE ARE INDICATIONS OF SPLITTERS AND COAX CABLE AS |
| | PLENUM RATED, BUT ARE THEY FIRE RATED? |
| | |
| | 27.7.1.6 WIRING INSIDE BUILDINGS. |
| | 27.7.1.6.1 AT THE COMMUNICATIONS CENTER, ALL |
| | CONDUCTORS, |
| | CABLES, AND FIBER-OPTIC CABLES SHALL EXTEND AS DIRECTLY |
| | AS POSSIBLE |
| | TO THE OPERATIONS CENTER IN CONDUITS, DUCTS, SHAFTS, |
| | RACEWAYS, |
| | OR OVERHEAD RACKS AND TROUGHS LISTED OR IDENTIFIED AS |
| | SUITABLE |
| | TO PROVIDE PROTECTION AGAINST PHYSICAL DAMAGE. |
| | 27.7.1.6.2* WHERE INSTALLED IN BUILDINGS, CONDUCTORS |
| | AND |
| | FIBER-OPTIC CABLES SHALL BE INSTALLED IN ANY OF THE |
| | FOLLOWING WIRING |
| | METHODS: |
| | (1) ELECTRICAL METALLIC TUBING |
| | (2) INTERMEDIATE METAL CONDUIT |
| | (3) RIGID METAL CONDUIT |
| | EXCEPTION: RIGID NONMETALLIC CONDUIT SHALL BE PERMITTED |
| | WHERE APPROVED |
| | BY THE AUTHORITY HAVING JURISDICTION. |
| | |
| | HOW WILL SPLITTERS BE PROTECTED? |
| | |
| | |
| | 5) WHEN RESUBMITTING, PLEASE PROVIDE PLAN SHEET |
| | REVISION CLOUDS OR NUMBERED NARRATIVE RESPONSES TO THE |
| | ABOVE. |
| | |
| | |
| | |
| | 6) ADDITIONAL COMMENTS MAY BE PROVIDED ON THE |
| | RE-SUBMITTAL OF THE ABOVE. |
| | |
| | |
| | PETER LEDUC |
| | FIRE MARSHAL |
| | 561-804-4709 |
| | [email protected] |
| | |