| 2020-03-10 12:53:33 | SECOND BUILDING REVIEW CHECKLIST. |
| | CODE: FBC 6TH EDITION (2017) AND CITY AMENDMENTS. |
| | |
| | NOTE: |
| | BUILDING REVIEW MAY BE APPROVED WITH PROVISO. PROVISO |
| | MEANS CONTRACTOR WILL SUBMIT REQUIRED INFORMATION AFTER |
| | THE PERMIT IS ISSUED BUT BEFORE INSPECTIONS TO AVOID |
| | CONFLICTS/DELAYS. REVISION FEES MAY APPLY. CONTRACTOR |
| | TO ADVICE IF PROVISO OPTION IS PREFERRED AT THIS TIME |
| | OR IF RE-SUBMITTING REQUIRED INFORMATION BEFORE PERMIT |
| | ISSUANCE. |
| | |
| | |
| | |
| | 1- OK |
| | 2- OK |
| | 3- SEPARATE SPRINKLER PERMIT WILL BE REQUIRED FOR ANY |
| | MODIFICATIONS. |
| | |
| | ORIGINAL COMMENT. |
| | 4-FLOORING SOUND INSULATION MATERIAL FOR NEW TILE: |
| | A) PROVIDE 2 COPIES OF THE FLAME SPREAD INDEX AND SMOKE |
| | DEVELOPED INDEX TEST DONE IN ACCORDANCE WITH ASTM E 84 |
| | OR UL 723 AS REQUIRED BY SEC. 720.1 OF FBC 6TH EDITION |
| | (2017). |
| | |
| | RESPONSE: |
| | REPEAT COMMENT. NOT ADDRESSED. |
| | |
| | B) PROVIDE 2 COPIES OF THE SOUND TRANSMISSION CLASS |
| | (STC) TEST DONE IN ACCORDANCE WITH ASTM E 90 AS |
| | REQUIRED BY SEC. 1207.2 OF FBC 6TH EDITION (2017). |
| | |
| | RESPONSE: |
| | REPEAT COMMENT. NOT ADDRESSED. |
| | |
| | C) PROVIDE 2 COPIES OF THE IMPACT INSULATION CLASS |
| | (IIC) TEST DONE IN ACCORDANCE WITH ASTM E 492 AS |
| | REQUIRED BY SEC. 1207.3 OF FBC 6TH EDITION (2017). |
| | |
| | RESPONSE: |
| | REPEAT COMMENT. NOT ADDRESSED. |
| | |
| | NOTE: TEST SAMPLES TO MATCH BUILDING FLOOR/CEILING |
| | CONSTRUCTION AND PROPOSED FLOOR FINISH. ALSO, THERE ARE |
| | TESTS FOR 6" OR 8" CONCRETE SLABS WITH OR WITHOUT |
| | ACOUSTICAL CEILING. TYPICALLY THERE ARE NOT SUSPENDED |
| | ACOUSTICAL CEILINGS IN THESE BUILDINGS. |
| | |
| | 5- OK |
| | |
| | |
| | PLEASE FEEL FREE TO CONTACT ME IF YOU HAVE ANY |
| | QUESTIONS REGARDING THESE COMMENTS, |
| | JULIO GOMEZ |
| | COMMERCIAL COMBINATION PLANS EXAMINER |
| | DEVELOPMENT SERVICES DEPARTMENT |
| | BUILDING DIVISION |
| | (561)805-6712 |
| | [email protected] |