| 2020-02-03 15:33:15 | PLAN REVIEW - BUILDING |
| | |
| | CODES IN EFFECT: |
| | 2017 FLORIDA BUILDING CODE, 6TH EDITION W/2017 WEST |
| | PALM BEACH AMENDMENTS TO THE FLORIDA BUILDING CODE, |
| | CHAPTER 1 ADMINISTRATION |
| | FBC RE = FLORIDA RESIDENTIAL CODE 2017 6TH EDITION |
| | FBC CE = FLORIDA BUILDING CODE ENERGY CONSERVATION 2017 |
| | 6TH EDITION |
| | |
| | CHRISTOPHER S. THROOP, C.B.O. |
| | BUILDING PLANS EXAMINER, PX3169 |
| | 1&2 FAMILY PLANS EXAMINER, SFP306 |
| | CONSTRUCTION SERVICES DIVISION |
| | TEL: 561-805-6726 |
| | FAX: 561-805-6676 |
| | E-MAIL: [email protected] |
| | |
| | 1ST REVIEW |
| | |
| | RESULTS: DENIED |
| | |
| | YOUR SUBMITTAL IS DEFICIENT FOR THE REASONS LISTED |
| | BELOW. |
| | ADDRESS THE ATTACHED COMMENTS AND RE-SUBMIT |
| | |
| | 1. PROVIDE SURVEY. |
| | |
| | 2, PROVIDE SITE DRAINAGE PLAN. |
| | |
| | FBC R401.3 SITE DRAINAGE |
| | PROVIDE TWO SETS OF A SITE DRAINAGE PLAN SHOWING |
| | COMPLIANCE WITH FBC R401.3 DRAINAGE. |
| | SURFACE DRAINAGE SHALL BE DIVERTED TO A STORM SEWER |
| | CONVEYANCE OR OTHER APPROVED POINT OF COLLECTION THAT |
| | DOES NOT CREATE A HAZARD. |
| | |
| | |
| | 3. PROVIDE FINISHED FLOOR ELEVATION. NOTE ON PLAN PAGE |
| | 7.0 STATES FINISHED FLOOR NEEDS TO BE 18INCHES ABOVE |
| | CROWN OF ROAD, THIS IS A PALM BEACH COUNTY REQUIREMENT. |
| | SEE THE CITY OF WPB REQUIREMENTS BELOW. |
| | |
| | R403.1.7.3 FOUNDATION ELEVATION. |
| | ON GRADED SITES, THE TOP OF ANY EXTERIOR FOUNDATION |
| | SHALL EXTEND ABOVE THE ELEVATION OF THE STREET GUTTER |
| | AT POINT OF DISCHARGE OR THE INLET OF AN APPROVED |
| | DRAINAGE DEVICE A MINIMUM OF 12 INCHES (305 MM) PLUS 2 |
| | PERCENT. ALTERNATE ELEVATIONS ARE PERMITTED SUBJECT TO |
| | THE APPROVAL OF THE BUILDING OFFICIAL, PROVIDED IT CAN |
| | BE DEMONSTRATED THAT REQUIRED DRAINAGE TO THE POINT OF |
| | DISCHARGE AND AWAY FROM THE STRUCTURE IS PROVIDED AT |
| | ALL LOCATIONS ON THE SITE. |
| | |
| | 4. SAFETY GLAZING REQUIRED AT BOTTOM OF STAIRS. |
| | |
| | R308.4.7GLAZING ADJACENT TO THE BOTTOM STAIR LANDING. |
| | |
| | 5. ROOFING PERMIT REQUIRED. |
| | |
| | PERMITS |
| | 105.1 REQUIRED. |
| | |
| | 6. PROVIDE PRODUCT APPROVALS FOR PROPOSED ROOFING |
| | SYSTEM COMPONENTS. |
| | |
| | FBC 107.3.4 ? PROVIDE PRODUCT APPROVALS FOR THOSE |
| | PRODUCTS WHICH ARE REGULATED BY FAC RULE 9N-3 REVIEWED |
| | AND APPROVED IN WRITING BY THE DESIGNER OF RECORD. |
| | SPECIFICALLY, PROVIDE ROOFING SUBMITTALS. |
| | |
| | PLEASE NOTE THAT SUBMITTAL OF ADDITIONAL AND/OR REVISED |
| | MATERIALS MAY RESULT IN NEW PLAN REVIEW COMMENTS. |
| | |
| | |