2020-04-30 11:56:21 
 2ND REVIEW FBC-2017 PLUMBING/GAS
 PERMIT #19120807
 4/30/2020
  
 CODES IN EFFECT:
  
 FBC B- FLORIDA BUILDING CODE SIXTH EDITION 2017
 FBC M- FLORIDA MECHANICAL CODE SIXTH EDITION 2017
 FBC EC- FLORIDA ENERGY CONSERVATION CODE SIXTH EDITION
 2017
 FBC FG- FLORIDA FUEL GAS CODE SIXTH EDITION 2017
 FBC EX- FLORIDA EXISTING BUILDING CODE SIXTH EDITION
 2017
 FBC P- FLORIDA PLUMBING CODE SIXTH EDITION 2017
 FS- FLORIDA STATUTES
 FAC- FLORIDA ADMINISTRATIVE CODE
 WPB- WEST PALM BEACH AMENDMENTS TO THE FBC SIXTH
 EDITION 2017
  
 PLAN REVIEW RESULTS: DENIED.
  
 1) SHEET 4, UNDERGROUND GAS PIPING: SHOW THE WHERE
 GENERATOR BRANCH LINE CONNECTS TO THE MAIN LINE-
 SECTION 107.2.1 WPB.
  
 2) P1.1: MODIFY THE ISOMETRIC DRAWING TO INDICATE THE
 LENGTH OF THE UNDERGROUND PIPING RUN FROM THE POINT OF
 CONNECTION AT THE MAIN UNDERGROUND LINE TO THE NEW GAS
 METER AT THE ENCLOSURE. IDENTIFY THE TYPE AND SIZE OF
 UNDERGROUND GAS PIPING, BURIAL DEPTH AND HOW THE PIPE
 WILL BE PROTECTED FROM DAMAGE- SECTIONS 402.4 AND 404.1
 FBC FG.
  
 3) P1.1: I HAVE REVIEWED THE SUBMITTED SHOP DRAWINGS
 AND PRODUCT APPROVAL FOR THE GENERATOR ENCLOSURE, AND
 THE CLARKE GENERATOR SPECIFICATIONS SUBMITTAL WHICH
 INCLUDES THE OPTIBLEND DUEL FUEL SYSTEM SPECS. I DO NOT
 SEE IN ANY OF THESE DOCUMENTS AN INTERNAL GAS PIPING
 ISOMETRIC OR LAYOUT DRAWING FOR CONNECTING THE
 GENERATORS TO THE NEW EXTERIOR GAS LINE AND SERVICE.
 PAGE 29 OF THE GENERATOR SPECS INDICATES THE OPTIBLEND
 KITS ARE SHIPPED WITH EACH ASSEMBLY PACKAGE TOGETHER,
 BUT NO CONNECTION DETAILS PROVIDED TO THE GAS SUPPLY
 SYSTEM. PLEASE MODIFY THE EXISTING ISOMETRIC DRAWING
 ACCORDINGLY AND ALSO PROVIDE A GAS PIPING LAYOUT FOR
 INSIDE THE ENCLOSURE. SHOW LOCATIONS OF REGULATORS,
 SHUT OFF VALVES, UNIONS AND INLET PRESSURE REQUIRED AT
 THE OPTIBLEND KIT AND GENERATOR. PLEASE SEE GAS
 PRESSURE INFO ON PAGE 23 AND 29 OF THE SPEC- SECTIONS
 107.2.1 WPB. A) PLEASE CLARIFY HOW THE 18,000 SCFH
 TOTAL GAS LOAD WAS DETERMINED. WHICH CONVERSION OR
 CALULATION METHOD WAS USED?- SECTION 107.2.1 WPB.
  
 WHEN RESUBMITTING, IT IS HELPFUL TO PROVIDE A RESPONSE
 LETTER ADDRESSING EACH ITEM ALONG WITH THE CITY
 RE-SUBMITTAL FORM.
  
 CHRISTOPHER L. COLE
 MECHANICAL/PLUMBING PLANS EXAMINER
 401 CLEMATIS STREET
 WEST PALM BEACH FL 33401
 561-805-6719
 [email protected]
  
  


Account Summary | Usage Policy | Privacy Policy
Copyright © 2005 – 2014, SunGard Pentamation, Inc & City of West Palm Beach, FL – All Rights Reserved