| 2020-07-13 10:33:38 | ** FAILED ** |
| | |
| | PLEASE ADDRESS THE FOLLOWING COMMENTS. RESPOND TO THE |
| | COMMENTS IN WRITING AND/OR ON THE PLANS WHERE |
| | APPLICABLE: |
| | |
| | 1.) PROVIDE A SITE PLAN DRAWN TO SCALE SUFFICIENT TO |
| | REPRESENT ALL ELEMENTS OF THE PROPOSED DOCK AND OF THE |
| | RIPARIAN PROPERTY FROM WHICH THE DOCK WILL PROJECT AND |
| | OF THE ADJACENT PROPERTIES ON BOTH SIDES THEREOF. [ZLDR |
| | S.94-313(A)(2)C.] [1/10/2020, 4/2/2020 AND 6/8/20 |
| | REPEAT COMMENT] |
| | |
| | 2.) VALID WRITTEN APPROVAL OF THE PROPOSED DOCK BY THE |
| | FLORIDA DEPARTMENT OF ENVIRONMENTAL PROTECTION (DEP), |
| | THE U.S. ARMY CORPS OF ENGINEERS (THE CORPS) AND/OR THE |
| | SOUTH FLORIDA WATER MANAGEMENT DISTRICT (SFWMD) IS |
| | REQUIRED. SUCH WRITTEN APPROVAL SHALL CONTAIN THE DATE |
| | ON WHICH THE PROPOSED DOCK WAS APPROVED. [ZLDR |
| | S.94-313(A)(2)E.] [1/10/2020, 4/2/2020 AND 6/8/20 |
| | REPEAT COMMENT] |
| | |
| | 3.) THE PROPOSED DOCK, TEES, DOLPHINS, PILINGS, |
| | BOATLIFTS, AND OTHER MOORING-RELATED FACILITIES SHALL |
| | BE CONSTRUCTED WITHIN THE MIDDLE-ONE THIRD OF THE LOT |
| | ON WHICH A DOCK IS CONSTRUCTED, AS EXTENDED INTO THE |
| | WATERWAY. PLEASE PROVIDE DIMENSIONS WITHIN THE SURVEY |
| | AND SITE PLAN THAT SHOW THE PROPOSED DOCK AND ALL |
| | RELATED ELEMENTS WILL BE LOCATED WITHIN THE MIDDLE |
| | ONE-THIRD OF THE LOT. [ZLDR S.94-313(A)(3)H.] |
| | [1/10/2020, 4/2/2020 AND 6/8/2020 REPEAT COMMENT - |
| | LINES SHOWING THE MIDDLE ONE THIRD MUST BE EXTENDED |
| | FROM PROPERTY INTO THE WATER WAY] |
| | |
| | |
| | |
| | NOTES: |
| | |
| | * ALL MOORING SLIPS SHALL BE PROVIDED WITH APPROPRIATE |
| | CONNECTIONS FOR POTABLE WATER AND ELECTRICAL SERVICE. |
| | [ZLDR S.94-313(A)(3)G.] |
| | |
| | * ANY REVISIONS TO THE PLANS MAY RESULT IN ADDITIONAL |
| | COMMENTS. |
| | |
| | * CONTACT LINDA LOUIE @ (561) 822-1458 IF THERE ARE |
| | QUESTIONS. |
| | |
| | * ZONE: SF7 |
| | |
| | * MASTER PERMIT: #19020388 (NEW SFR) |
| | |