| 2019-11-15 10:48:03 | PLAN REVIEW - BUILDING DEMO |
| | |
| | CODES IN EFFECT: |
| | 2017 FLORIDA BUILDING CODE, 6TH EDITION W/2017 WEST |
| | PALM BEACH AMENDMENTS TO THE FLORIDA BUILDING CODE, |
| | CHAPTER 1 ADMINISTRATION |
| | FBC RE = FLORIDA RESIDENTIAL CODE 2017 6TH EDITION |
| | FBC CE = FLORIDA BUILDING CODE ENERGY CONSERVATION 2017 |
| | 6TH EDITION |
| | |
| | CHRISTOPHER S. THROOP, C.B.O. |
| | BUILDING PLANS EXAMINER, PX3169 |
| | 1&2 FAMILY PLANS EXAMINER, SFP306 |
| | CONSTRUCTION SERVICES DIVISION |
| | TEL: 561-805-6726 |
| | FAX: 561-805-6676 |
| | E-MAIL: [email protected] |
| | |
| | 1ST REVIEW |
| | |
| | RESULTS: DENIED |
| | |
| | YOUR SUBMITTAL IS DEFICIENT FOR THE REASONS LISTED |
| | BELOW. |
| | ADDRESS THE ATTACHED COMMENTS AND RE-SUBMIT |
| | |
| | PLEASE SEE ATTACHED DEMO CHECKLIST. I HAVE INDICATED |
| | ITEMS COMPLETE. PLEASE ADDRESS ANY OPEN ITEMS |
| | |
| | PROVIDE EACH OF THE FOLLOWING ITEMS VIA EMAIL AS THEY |
| | ARE AVAILABLE; SEND TO [email protected], INCLUDE THE |
| | PERMIT NUMBER IN THE SUBJECT LINE. |
| | |
| | |
| | THE FOLLOWING ITEMS ARE REQUIRED PRIOR TO ISSUANCE OF A |
| | DEMO PERMIT PER FLORIDA BUILDING CODE, BUILDING 3303: |
| | |
| | 1. UTILITY RELEASE - FLORIDA POWER & LIGHT (ELECTRIC) |
| | RELEASE OF SERVICE CONFIRMATION - COMPLETE |
| | |
| | 2. UTILITY RELEASE - FLORIDA PUBLIC UTILITIES (GAS) |
| | RELEASE OF SERVICE CONFIRMATION - COMPLETE |
| | |
| | 3. UTILITY RELEASE - CITY OF WEST PALM BEACH WATER |
| | DEPARTMENT, REQUEST FOR METER PULL, ON THEIR FORM |
| | "DEMOLITION APPLICATION" - COMPLETE |
| | |
| | HTTP://WPB.ORG/DEPARTMENTS/DEVELOPMENT-SERVICES/FORMS/B |
| | UILDING-PERMIT-FORMS |
| | |
| | IF A HYDRANT METER OR BACKFLOW PREVENTER IS DESIRED, |
| | THEN A PARTIAL RELEASE WILL BE NOTED ON THEIR FORM. |
| | |
| | FAX THE COMPLETED "DEMOLITION APPLICATION" FORM TO |
| | 561-822-2183. AFTER THEY FAX THE RELEASE TO YOU, SEND A |
| | COPY VIA EMAIL TO [email protected] WITH THE PERMIT |
| | NUMBER IN THE SUBJECT LINE. |
| | |
| | 4. SEWER LATERAL CAPPING PERMIT IS REQUIRED; SCHEDULE A |
| | FINAL PLUMBING #703. PLEASE NOTIFY US VIA EMAIL AFTER |
| | FINAL INSPECTION HAS PASSED). - OPEN |
| | OBTAIN A PLUMBING PERMIT. PROVIDE RESULTS OF A FINAL |
| | INSPECTION. |
| | |
| | 5. EXTERMINATION LETTER - LETTER FROM A LICENSED PEST |
| | CONTROL COMPANY STATING THAT DEMOLITION ADDRESS HAS |
| | BEEN INSPECTED AND/OR TREATED FOR RODENTS. - COMPLETE |
| | |
| | 6. COMPLETE THE DEMO DEBRIS FORM AND PAY THE FEES, |
| | "DEMOLITION DEBRIS DISPOSAL FEE": - OPEN |
| | |
| | HTTP://WPB.ORG/DEPARTMENTS/DEVELOPMENT-SERVICES/FORMS/B |
| | UILDING-PERMIT-FORMS |
| | |
| | AFTER THE FORM IS SENT TO [email protected], THE FEES |
| | WILL BE ADDED TO YOUR PERMIT. YOU CAN THEN PAY THE FEES |
| | ONLINE PRIOR TO PERMIT ISSUANCE. |
| | |
| | 7. ASBESTOS - SEE ASBESTOS REVIEW |
| | |
| | |
| | |
| | |