| 2019-11-07 07:32:55 | GAS 1ST REVIEW**DENIED**19091166 |
| | 1. YOU ONLY SUPPLIED A FLAT DRAWING. PER FBC 107.3.5 A |
| | GAS ISOMETRIC RISER IS REQUIRED. SUBMIT AN ISOMETRIC |
| | DRAWING THAT CLEARLY SHOWS THE LENGTH OF ALL CUT |
| | SECTIONS OF PIPE PER 2017 FBC-FUEL GAS, SECS. 402.4.1, |
| | 402.4.2. |
| | |
| | 2. SHOW THE TYPE OF PIPE MATERIAL BEING INSTALLED, ALL |
| | PIPE SIZES, AND THE CORRESPONDING EHD NUMBER OF THE |
| | CORRUGATED STAINLESS STEEL TUBING (IF APPLICABLE) FOR |
| | EACH PIPE SIZE. WPB AMENDMENTS TO FBC SEC.107.2.1. |
| | |
| | 3. SHOW THE DISTANCE FROM THE POINT OF DELIVERY, (GAS |
| | METER / MP REGULATOR / LP TANK) TO THE MOST REMOTE |
| | OUTLET IN THE BUILDING AND / OR SYSTEM PER THE 2017 |
| | FBC-FUEL GAS SEC.402.4.1, 402.4.2. |
| | |
| | 4. INDICATE THE DELIVERY PRESSURE (PSI) OF THE SYSTEM |
| | ON THE PLAN PER 2017 FBC-FUEL GAS SEC.402.1, 402.4.3 |
| | THRU 402.6 |
| | |
| | 5. SUBMIT MANUFACTURER?S SPECIFICATION SHEETS / |
| | INSTALLATION MANUAL FOR ALL GAS EQUIPMENT TO VERIFY |
| | COMPLIANCE WITH STANDARDS NFPA 54, NFPA 58, AND |
| | FBC-2017 FUEL GAS CODE SEC. 402.2, AND 301.3 OR 2017 |
| | FBC-RES. SEC. G2404.3. GAS APPLIANCES SHALL BE LISTED |
| | AND LABELED. THE INSTALLATION MANUALS FOR ALL GAS |
| | APPLIANCES / EQUIPMENT SHALL BE ONSITE AT THE TIME OF |
| | INSPECTION. FGC SEC.305.1, |
| | |
| | 6. SUBMIT COMBUSTION AIR CALCULATIONS FOR THE ADDED GAS |
| | APPLIANCES. WHERE COMBUSTION AIR IS PROVIDED BY THE |
| | BUILDING?S MECHANICAL VENTILATION SYSTEM, THE SYSTEM |
| | SHALL PROVIDE THE SPECIFIED COMBUSTION AIR RATE IN |
| | ADDITION TO THE REQUIRED VENTILATION AIR. 2017 FBC-FUEL |
| | GAS SEC.304.9.3 |
| | |
| | 7. SUBMIT TWO COPIES OF THE APPLICABLE SIZING TABLES |
| | USED TO SIZE THE GAS SYSTEM OR PLACE A NOTE ON THE |
| | PLANS/DRAWINGS SPECIFYING WHICH SIZING TABLE(S) FROM |
| | THE GAS CODE OR OTHER STANDARD THAT WERE USED IN THE |
| | DESIGN OF THIS GAS SYSTEM. REFER TO THE 2017 FBC-FUEL |
| | GAS SECS. 401.4, 401.8, 402.3, AND TABLES 402.4 (1) |
| | THRU 402.4 (37) |
| | |
| | 8. SUBMIT MANUFACTURER?S SPECIFICATIONS FOR THE |
| | PRESSURE REGULATORS. REGULATORS INSTALLED ON THE |
| | EXTERIOR OF THE BUILDING SHALL BE APPROVED FOR OUTDOOR |
| | INSTALLATION. 2017 FGC SEC.410.1, |
| | |
| | 9. SHT. P301 SHOWS 1.5? GAS PIPING BUT THIS CONFLICTS |
| | WITH HWH DETAIL AS IT SHOWS 2.5? PIPING. PLEASE |
| | CLARIFY. FBC 107.2.1 |
| | |
| | 10. SHT. P103 ADD TANKLESS WATER HEATERS TO GAS |
| | SCHEDULE. FBC 107.2.1 |
| | |
| | 11. SUBMIT A DETAIL SHOWING THE TYPE, LOCATION, SIZE, |
| | TERMINATION POINT, HEIGHT ABOVE THE ROOF AND ANCHORING |
| | DETAILS OF THE GAS VENT(S) PER 2017 FBC-FUEL GAS SECS. |
| | 502 THRU 505. PLEASE SIZE EACH SECTION OF VENT PIPING |
| | AND CALL OUT MATERIAL TO BE USED AND INSTALLATION |
| | MANUAL FOR THAT MATERIAL. |
| | NOTE - A COMPREHENSIVE REVIEW COULD NOT BE DONE AT THIS |
| | TIME AND ADDITIONAL PLAN REVIEW COMMENTS MAY BE |
| | GENERATED UPON THE RE-REVIEW OF SUBMITTED CORRECTIONS. |
| | |
| | TIM HUNT |
| | PLUMBING PLANS EXAMINER |
| | CITY OF WEST PALM BEACH ( CGA SOLUTIONS) |
| | [email protected] |
| | 561-248-2703 |
| | |