| Plan Review Notes For Permit 19090823 |
| Permit Number |
19090823 |
|
| Review Stop |
P |
| Sequence Number |
2 |
|
| Notes |
| Date |
Text |
| 2019-10-10 06:27:29 | 1) INDICATE IF ANY WORK WILL BE DONE TO THE MAIN DRAIN | | | OR GUTTER SYSTEM, WHICHEVER IS APPLICABLE.WPB AMEND. TO | | | FBC SEC. 107.2.1. 2ND REQUEST. | | | 2) SUBMIT 2 SETS OF PLANS FOR REVIEW OR TWO COPIES OF | | | THE WORK ORDER THAT CLEARLY REFLECTS THE TOTAL SCOPE OF | | | WORK TO BE DONE. WPB AMEND. TO FBC SEC. 107.2.1. | | | | | | TIM LARGE | | | CHIEF PLUMBING INSPECTOR | | | PLUMBING PLAN REVIEW | | | 561-805-6692 | | | [email protected] | | | | | | |
|