| Date |
Text |
| 2019-10-18 11:44:26 | PROVISO: |
| | |
| | |
| | |
| | |
| | 1) THIS PROPOSED BUILDING IS GOING TO BE BUILT IN A AE |
| | FLOOD ZONE WITH THE BASE FLOOD BFE: 12.7 FEET NAV88. |
| | DURING THE PERMITTING OF THIS STRUCTURE THERE WILL BE |
| | REQUIRED (3) DIFFERENT FLOOD ZONE CERTIFICATES: |
| | |
| | (1)CONSTRUCTION DRAWINGS ELEVATION CERTIFICATE WAS |
| | PROVIDED AND IS OK. |
| | |
| | THE OTHER TWO ELEVATIONS CERTIFICATES NEED TO BE |
| | PROVIDED DURING CONSTRUCTION AND THEY ARE: |
| | |
| | (2) ONCE THE FIRST FLOOR SLAB IS POURED THE 2ND |
| | ELEVATION CERTIFICATE IS REQUIRED. W. P. B. |
| | ADMINISTRATIVE CODE 110.3 REQUIRED INSPECTIONS 1.2 |
| | FLOOR/ SLAB INSPECTION. IN FLOOD HAZARD AREAS, UPON |
| | PLACEMENT OF THE LOWEST FLOOR, INCLUDING BASEMENT, AND |
| | PRIOR TO FURTHER VERTICAL CONSTRUCTION, THE ELEVATION |
| | CERTIFICATION, REQUIRED IN SECTION 1612.5, SHALL BE |
| | SUBMITTED TO THE BUILDING OFFICIAL. |
| | |
| | (3) BEFORE THE ISSUANCE OF A CERTIFICATE OF OCCUPANCY |
| | OR A CERTIFICATE OF COMPLETION THE 3RD FLOOD ZONE |
| | CERTIFICATE IS REQUIRED WITH THE HEIGHT OF ALL EXTERIOR |
| | ATTENDANTS A/C PADS OR OTHER SLABS FOR GENERATORS. |
| | W. P. B. ADMINISTRATIVE CODE 110.3 REQUIRED INSPECTIONS |
| | (6) FINAL INSPECTION. TO BE MADE AFTER THE BUILDING IS |
| | COMPLETED AND READY FOR OCCUPANCY. 6.1. LOWEST FLOOR |
| | ELEVATION. IN FLOOD HAZARD AREAS, AS PART OF THE FINAL |
| | INSPECTION, A FINAL CERTIFICATION OF THE LOWEST FLOOR |
| | ELEVATION SHALL BE SUBMITTED TO THE AUTHORITY HAVING |
| | JURISDICTION. |