| 2019-11-04 15:01:24 | 1ST REVIEW FBC-2017 MECHANICAL |
| | PERMIT #19090272 |
| | 11/4/19 |
| | |
| | CODES IN EFFECT: |
| | |
| | FBC B- FLORIDA BUILDING CODE SIXTH EDITION 2017 |
| | FBC M- FLORIDA MECHANICAL CODE SIXTH EDITION 2017 |
| | FBC EX- FLORIDA EXISTING BUILDING CODE SIXTH EDITION |
| | 2017 |
| | FS- FLORIDA STATUTES |
| | FAC- FLORIDA ADMINISTRATIVE CODEWPB- WEST PALM BEACH |
| | AMENDMENTS TO THE FBC SIXTH EDITION 2017 |
| | NFPA 110- 2018 |
| | NFPA 37- 2018 |
| | NFPA 30- 2018 |
| | |
| | PLAN REVIEW RESULTS: DENIED. |
| | |
| | 1) SHEETS SP1.0.3 & M1.2.1A: THE SITE PLAN INDICATES BY |
| | SCALE THAT THE THE EXHAUST PIPE DISCHARGE AND THE |
| | GENERATOR EXHAUST OUTLET ARE WITHIN THE REQUIRED 10' |
| | CLEARANCE TO THE PROPERTY LINE. PLEASE REFER TO THE |
| | MAIN BUILDING PLANS APPROVED UNDER PERMIT #17110075. |
| | THERE ARE NOTES ON THE GROUND FLOOR MECHANICAL PLANS |
| | INDICATING ALL OUTSIDE AIR INTAKES AND EXHAUST OUTLETS |
| | SHALL MEET THE REQUIRED CLEARANCE DISTANCES. IT APPEARS |
| | THAT MANY AIR INLETS AND EXHAUST OUTLETS WILL BE |
| | LOCATED TOO CLOSE TO THE PROPERTY LINE. |
| | |
| | 2) SUBMIT THE SPECS FOR THE FUEL TANK- SECTION 107.2.1 |
| | WPB & SECTION 21.4.2.1.1 NFPA 30. SECTION 8.1.1 NFPA |
| | 37. INDICATE THE DIAMETER OF THE EXHAUST PIPE ON SHEET |
| | M1.2.1A. |
| | |
| | 3) SUBMIT THE UL 2200 CERTIFICATE FOR THE GENERATOR- |
| | SECTION 915.1 FBC M. |
| | |
| | 4) SUBMIT THE SPECS FOR THE ENGINE EXHAUST PIPE- |
| | SECTION 8.1.1 NFPA 37. |
| | A) INDICATE THE DIAMETER OF THE EXHAUST PIPE AND THE |
| | TOTAL RUN LENGTH OF THE PIPE ON SHEET M1.2.1A. |
| | B) PROVIDE THE CLEARANCE DISTANCES FROM THE EXHAUST |
| | PIPE DISCHARGE TO GRADE AND TO THE PROPERTY LINE- |
| | SECTION 501.3.1(2) FBC M. |
| | C) PROVIDE BACKPRESSURE CALCULATIONS FOR THE EXHAUST |
| | PIPING AND SILENCER, AND VERIFY THE BACKPRESSURE DOES |
| | NOT EXCEED THE MAXIMUM 10 KPA ALLOWABLE BACKPRESSURE |
| | PER THE GENERATOR MAHNUFACTURER. |
| | |
| | 5) THE SUBMITTED EPA CERTIFICATE FOR THE GENERATOR |
| | EMISSIONS EXPIRED ON 12/31/18. PLEASE PROVIDE AN |
| | UPDATED CERTIFICATE- SECTION 107.2.1 WPB. |
| | |
| | 6) THE SPECS FOR THE SOUNDLINING INDICATE NOT |
| | RECOMMENDED FOR EQUIPMENT WITH OPERATING TEMPERATURES |
| | GREATER THAN 250 DEGREES F, HOWEVER THE GENERATOR SPECS |
| | SHOW THE EXHAUST TEMPERATURE AT 975 DEGREES F. |
| | |
| | 7) SHEET M.1.2.1A: THE RADIATOR EXHAUST AIR DISCHARGE |
| | SHALL BE DUCTED OUTDOORS OR TO AN EXTERIOR OPENING BY A |
| | 2-HOUR FIRE-RATED TRANSFER SYSTEM- SECTION 7.7.4.2 NFPA |
| | 110. |
| | |
| | 8) REFER TO SECTION 7.7.1 NFPA 110- 2016 AND VERIFY |
| | THAT THE VENTILATION AIRFLOW IN THE GENERATOR/TANK |
| | (EPS) ROOM IS DESIGNED TO LIMIT THE MAXIMUM AIR |
| | TEMPERATURE IN THE ROOM TO THE MAXIMUM AMBIENT AIR |
| | TEMPERATURE REQUIRED BY THE GENERATOR MANUFACTURER. |
| | CONSIDERATION SHALL BE GIVEN TO ALL THE HEAT EMITTED TO |
| | THE ROOM BY THE ENERGY CONVERTER, EXHAUST PIPES, AND |
| | ALL OTHER HEAT PRODUCING EQUIPMENT- SECTION 7.7.1.1. |
| | DESIGN OF THE HEATING, COOLING, AND VENTILATION SYSTEM |
| | SHALL AMONG OTHER THINGS, INCLUDE PROVISONS FOR FACTORS |
| | SUCH AS HEAT, COLD, HUMIDITY, LOUVERS, ETC.- SECTION |
| | 7.7.7. |
| | |
| | 9) M1.2.1A: GENERATOR/FUEL TANK ROOM EXHAUST SYSTEM: |
| | A) PROVIDE EXHAUST VENTILATION CALCULATIONS FOR THE |
| | GENERATOR/TANK (EPS) ROOM, AND PROVIDE AN EQUIPMENT |
| | SCHEDULE FOR EF-2- SECTION 502.4.2 FBC M. |
| | B) THE EF-2 EXHAUST DUCT SHALL RUN INDEPENDENTLY, AND |
| | SHALL BE ENCLOSED IN 2-HR FIRE-RATED CONSTUCTION FROM |
| | THE PENETRATION OF THE WALL TO THE EXHAUST OUTLET- |
| | SECTIONS 501.3, 510.2, 510.6.7 |
| | C) INDICATE THE TYPE AND GAGE OF THE EXHAUST DUCTWORK- |
| | SECTION 510.9 FBC M. |
| | D) PLEASE NOTE THAT EXHAUST SYSTEM SHALL RUN |
| | CONTINOUSLY- SECTIONS 4.1.2.1.3 & 6.3.6.5.1 NFPA 37, |
| | AND SECTION 502.4.2 FBC. |
| | |
| | 10) SHOW THE LOCATION OF THE REMOTE FILL PIPING |
| | STATION, AND SHOW THE FUEL PIPING RUN TO THE TANK- |
| | SECTION 1305.6 FBC M & SECTION 6.6.3.3 NFPA 37. A) |
| | INDCATE THE TYPE AND SIZE OF PIPING- SECTION 1302 FBC |
| | M. |
| | |
| | 11) SHOW THE FUEL TANK VENT PIPING RUN AND TERMINATION |
| | LOCATION- SECTION 1305.7 FBC M & SECTION 6.7.1.1 NFPA |
| | 37. |
| | |
| | |
| | WHEN RESUBMITTING, IT IS HELPFUL TO PROVIDE A RESPONSE |
| | LETTER ADDRESSING EACH ITEM ALONG WITH THE CITY |
| | RE-SUBMITTAL FORM. ADDITIONALLY, PLEASE INSERT |
| | CORRECTED PLAN SHEETS INTO THE SETS, REMOVE THE |
| | PREVIOUSLY REVIEWED SHEETS AND MARK VOID ON THEM, AND |
| | KEEP THEM WITH THE SUBMITTALS |
| | |
| | CHRISTOPHER L. COLE |
| | MECHANICAL PLANS EXAMINER |
| | 401 CLEMATIS STREET |
| | WEST PALM BEACH FL 33401 |
| | 561-805-6719 |