Plan Review Notes
Plan Review Notes For Permit 19090038
Permit Number 19090038
Review Stop G
Sequence Number 1
Notes
Date Text
2019-09-09 16:42:4009/09/2019 1ST GAS/LP/TANK REVIEW **DENIED** WITH
 COMMENTS
  
 NOTE - A COMPREHENSIVE REVIEW COULD NOT BE DONE AT THIS
 TIME AND ADDITIONAL PLAN REVIEW COMMENTS MAY BE
 GENERATED UPON THE RE-REVIEW OF SUBMITTED CORRECTIONS.
  
 1. SUBMIT AN ISOMETRIC DRAWING THAT CLEARLY SHOWS THE
 LENGTH OF ALL CUT SECTIONS OF PIPE PER 2017 FBC RES.
 SECS. G2413.4.1, G2413.4.2.
 2. TYPE OF GAS (LP OR NATURAL). WPB AMENDMENTS TO THE
 FBC SEC. 107.2.1 INFORMATION ON CONSTRUCTION DOCUMENTS.
 3. INDICATE THE DELIVERY PRESSURE (PSI) OF THE SYSTEM
 ON THE PLAN PER 2017 FBC RES. SEC. G2413.2.
 4. SHOW THE LOCATION OF LP TANK. A LISTED SHUTOFF
 VALVE, UNIONS AND REGULATOR PER THE 2017 FBC RES. SEC.
 G2420.4.
 5. SHOW THE DISTANCE FROM THE POINT OF DELIVERY, (GAS
 METER / MP REGULATOR / LP TANK) TO THE MOST REMOTE
 OUTLET IN THE BUILDING AND/OR SYSTEM PER THE 2017 FBC
 RES. SEC. G2413.4.1.
 6. SUBMIT TWO COPIES OF THE SIZING TABLE USED IN THE
 DESIGN FOR THE GAS SYSTEM OR PLACE A NOTE ON BOTH SETS
 OF PLANS LISTING THE SIZING TABLES FROM GAS CODES OR
 ANOTHER STANDARD THAT WERE USED IN THE DESIGN OF THIS
 SYSTEM PER THE 2017 FBC RES. SEC. G2413.3
 7. THE CITY RECORDS INDICATE AN EXISTING LP TANK AND
 GENERATOR INSTALLED IN 2005. THE BTU LOAD OF THE
 EXISTING SYSTEM MUST BE ADDED INTO THE TOTAL BTU LOAD
 ON THE SYSTEM TO ENSURE THE EXISTING SYSTEM IS PROPERLY
 SIZED. IF UNDERSIZED, THE EXISTING SYSTEM MUST BE
 REDONE TO ENSURE A SAFE OPERATING SYSTEM PER THE 2017
 FBC RES. SECS. G2412.4, G2412.8, G2413.1, G2413.2,
 G2413.3.
 8. IF APPLICABLE SUBMIT MANUFACTURER?S SPECIFICATIONS
 FOR THE PRESSURE REGULATORS. REGULATORS INSTALLED ON
 THE EXTERIOR OF THE BUILDING SHALL BE APPROVED FOR
 OUTDOOR INSTALLATION PER THE 2017 FBC RES. SEC.
 G2421.1.
 9. PLEASE SHOW ALL UNIONS IN FRONT OF REGULATOR 1? OF
 EITHER SIDE PER THE 2017 FBC FG SEC 410.2.
 10. THE ADDRESS OF THE PROJECT OR RESIDENCE MUST BE ON
 PLAN. WPB AMENDMENTS TO THE FBC SEC.107.2.1 INFORMATION
 ON CONSTRUCTION DOCUMENTS.
 11. THE MANUFACTURER'S SPECIFICATIONS FOR THE GENERATOR
 SHALL BE ONSITE FOR FINAL GAS INSPECTION. THE GENERATOR
 SHALL BE LISTED AND APPROVED. NFPA 58 SEC. 5.20.1. THE
 GENERATOR SHALL MEET THE REQUIREMENTS OF UL 2200.
  
  
 WHEN RESUBMITTING PLANS PLEASE INDICATE THE REVISION &
 REMOVE ANY VOIDED SHEETS & REPLACE ANY PAGES AS
 NECESSARY. A TRANSMITTAL LETTER LISTING THE ORIGINAL
 REVIEW COMMENT NUMBER, WITH A DESCRIPTION OF THE
 REVISION, MADE, IDENTIFYING THE SHEET OR SPECIFICATION
 PAGE WHERE THE CHANGES CAN BE FOUND WILL HELP TO
 EXPEDITE YOUR PERMIT. THANK YOU FOR YOUR ANTICIPATED
 COOPERATION.
  
  
 LUIS A. CRESPO
 PLUMBING INSPECTOR /
 PLUMBING PLAN REVIEW
 AVAILABLE FROM 1:00 PM TO 4:00 PM
 [email protected]
 561-805-6720
  