| 2019-11-12 06:49:16 | 11/12/2019 2ND GAS REVIEW**DENIED** WITH COMMENTS NOTE |
| | - A COMPREHENSIVE REVIEW COULD NOT BE DONE AT THIS TIME |
| | AND ADDITIONAL PLAN REVIEW COMMENTS MAY BE GENERATED |
| | UPON THE RE-REVIEW OF SUBMITTED CORRECTIONS. |
| | |
| | 1- THE BTU LOAD OF THE EXISTING GAS SYSTEM MUST BE |
| | ADDED INTO THE TOTAL BTU LOAD ON THE SYSTEM TO ENSURE |
| | THE EXISTING SYSTEM IS PROPERLY SIZED. IF UNDERSIZED, |
| | THE EXISTING SYSTEM MUST BE REDONE TO ENSURE A SAFE |
| | OPERATING SYSTEM. 2017 FBC FUEL GAS SEC. 401.4, 401.8, |
| | 402.1, 402.2, 402.3 OR 2017 FBC FUEL GAS SECS.G2412.4, |
| | G2412.8, G2413.1, G2413.2, G2413.3. |
| | |
| | 2-GAS PLAN REVIEW, A GAS PLAN HAS NOT BEEN INCLUDED IN |
| | THIS SUBMITTAL PACKAGE. A GAS PLAN REVIEW HAS NOT BEEN |
| | PERFORMED AT THIS TIME. A SEPARATE GAS PERMIT AND PLANS |
| | WILL BE REQUIRED FOR A CONTRACTOR TO PERFORM THE |
| | RELATED WORK. PROVIDE COMPLETE PLANS AND GAS RISER THAT |
| | REFLECTS THE ENTIRE SCOPE OF GAS WORK TO BE DONE. AT |
| | THIS TIME. WPB AMENDMENTS TO FBC SEC. 107.2.1. |
| | |
| | 3-WHEN RESUBMITTING PLANS PLEASE INDICATE THE REVISION |
| | & REMOVE ANY VOIDED SHEETS & REPLACE ANY PAGES AS |
| | NECESSARY. A TRANSMITTAL LETTER LISTING THE ORIGINAL |
| | REVIEW COMMENT NUMBER, WITH A DESCRIPTION OF THE |
| | REVISION, MADE, IDENTIFYING THE SHEET OR SPECIFICATION |
| | PAGE WHERE THE CHANGES CAN BE FOUND WILL HELP TO |
| | EXPEDITE YOUR PERMIT. THANK YOU FOR YOUR ANTICIPATED |
| | COOPERATION. |
| | |
| | 4- THE INFORMATION PROVIDED STATES THAT THE |
| | MANUFACTURE" OFFERS" A UL 2200. PROVIDE A COPY OF THE |
| | UL 2200 LISTING FOR THE GENERATOR |
| | |
| | ATELYO BELISLE |
| | PLUMBING INSPECTOR / |
| | PLUMBING PLANS EXAMINER |
| | AVAILABLE FROM 1:00 PM TO 4:00 PM |
| | [email protected] |
| | 561-805-6695 |
| | |