| 2019-08-02 16:42:20 | 08/02/2019 1ST PLUMBING/BACKFLOW REVIEW **DENIED** WITH |
| | COMMENTS |
| | |
| | NOTE - A COMPREHENSIVE REVIEW COULD NOT BE DONE AT THIS |
| | TIME AND ADDITIONAL PLAN REVIEW COMMENTS MAY BE |
| | GENERATED UPON THE RE-REVIEW OF SUBMITTED CORRECTIONS. |
| | |
| | 1. ON THE ISOMETRIC DRAWING PLEASE SHOWS THE VALVE, |
| | SEDIMENT TRAP AND REGULATOR PER, 2017 FBC FUEL GAS RES |
| | SECS. G2413.4.1, G2413.4.2. |
| | 2. THIS UNIT REQUIRES A REGULATOR AS IT HAS 10.5? WC |
| | MINIMUM AND THE METER IS 12? WC. PLEASE SUBMIT |
| | MANUFACTURES SPECIFICATION FOR REGULATOR, REGULATORS |
| | INSTALLED OUTDOORS SHALL BE DESIGNED, INSTALLED OR |
| | PROTECTED SO THEIR OPERATION WILL NOT BE AFFECTED BY |
| | THE ELEMENTS. PROVIDE DOCUMENTATION FROM THE |
| | MANUFACTURER THAT THE REGULATORS ARE APPROVED FOR |
| | EXTERIOR USE. NFPA 58-11 SEC. 6.8.1.5. |
| | 3. THIS UNIT REQUIRES A 120 VOLT OUTLET FOR SOURCE OF |
| | IGNITION AND A SUB ELECTRICAL PERMIT IS REQUIRED FOR |
| | THE SOURCE OF IGNITION IF ONE NOT WITHIN RANGE, WPB |
| | AMENDMENTS TO THE FBC SEC. 105.1. |
| | 4. THE VALUE LISTED ON THE PLUMBING APPLICATION AND THE |
| | OVERALL VALUE IS LOW. PROVIDE BONA FIDE SIGNED CONTRACT |
| | PER WPB AMENDMENTS TO THE FBC 109.3 BUILDING PERMITS |
| | VALUATIONS. IF IN THE OPINION OF THE BUILDING OFFICIAL, |
| | THE CLAIMED VALUATION OF BUILDING, ALTERATION, |
| | STRUCTURE, ELECTRICAL, GAS, MECHANICAL OR PLUMBING |
| | SYSTEMS APPEARS TO BE UNDERESTIMATED ON THE |
| | APPLICATION, THE PERMIT SHALL BE DENIED UNLESS THE |
| | APPLICANT CAN SHOW DETAILED, QUANTITY ESTIMATES, AND/OR |
| | BONA FIDE SIGNED CONTRACTS (EXCLUDING LAND VALUE) TO |
| | MEET THE APPROVAL OF THE BUILDING OFFICIAL. FOR |
| | PERMITTING PURPOSES, VALUATION OF BUILDINGS AND SYSTEMS |
| | SHALL BE TOTAL REPLACEMENT VALUE TO INCLUDE STRUCTURAL, |
| | ELECTRIC, PLUMBING, MECHANICAL, INTERIOR FINISH, |
| | RELATIVE SITE WORK, ARCHITECTURAL AND DESIGN FEES, |
| | MARKETING COSTS, OVERHEAD AND PROFIT; EXCLUDING ONLY |
| | LAND VALUE. VALUATION REFERENCES MAY INCLUDE THE LATEST |
| | PUBLISHED DATA OF NATIONAL CONSTRUCTION COST ANALYSIS |
| | SERVICES (MARSHALL-SWIFT, MEANS, ETC.), AS PUBLISHED BY |
| | INTERNATIONAL CODE CONGRESS. FINAL BUILDING PERMIT |
| | VALUATION SHALL BE SET BY THE BUILDING OFFICIAL. |
| | |
| | WHEN RESUBMITTING PLANS PLEASE INDICATE THE REVISION & |
| | REMOVE ANY VOIDED SHEETS & REPLACE ANY PAGES AS |
| | NECESSARY. A TRANSMITTAL LETTER LISTING THE ORIGINAL |
| | REVIEW COMMENT NUMBER, WITH A DESCRIPTION OF THE |
| | REVISION, MADE, IDENTIFYING THE SHEET OR SPECIFICATION |
| | PAGE WHERE THE CHANGES CAN BE FOUND WILL HELP TO |
| | EXPEDITE YOUR PERMIT. THANK YOU FOR YOUR ANTICIPATED |
| | COOPERATION. |
| | |
| | LUIS A. CRESPO |
| | PLUMBING INSPECTOR / |
| | PLUMBING PLAN REVIEW |
| | AVAILABLE FROM 1:00 PM TO 4:00 PM |
| | [email protected] |
| | 561-805-6720 |
| | |