| 2019-07-22 07:22:07 | 7/22/2019 1ST GAS REVIEW**DENIED** WITH COMMENTS NOTE - |
| | A COMPREHENSIVE REVIEW COULD NOT BE DONE AT THIS TIME |
| | AND ADDITIONAL PLAN REVIEW COMMENTS MAY BE GENERATED |
| | UPON THE RE-REVIEW OF SUBMITTED CORRECTIONS. |
| | |
| | 1) INDICATE THE DELIVERY PRESSURE (PSI) OF THE SYSTEM |
| | ON THE PLAN PER 2017 FBC FUEL GAS SEC. 402.2 |
| | |
| | 2) SUBMIT TWO COPIES OF THE SIZING TABLE USED IN THE |
| | DESIGN FOR THE GAS SYSTEM OR PLACE A NOTE ON BOTH SETS |
| | OF PLANS LISTING THE SIZING TABLES FROM GAS CODES OR |
| | ANOTHER STANDARD THAT WERE USED IN THE DESIGN OF THIS |
| | SYSTEM 2017 FBC FUEL GAS SEC. 402.3 |
| | |
| | 3) SUBMIT MANUFACTURER?S SPECIFICATIONS FOR THE |
| | PRESSURE REGULATORS. REGULATORS INSTALLED ON THE |
| | EXTERIOR OF THE BUILDING SHALL BE APPROVED FOR OUTDOOR |
| | INSTALLATION. 2017 FBC FUEL GAS SEC.410.1 |
| | |
| | 4) THE CLAIMED VALUE INDICATED ON THE PERMIT |
| | APPLICATION DOES NOT MATCH THE PROVIDED BONA FIDE |
| | SIGNED CONTRACT. WPB AMENDMENTS TO THE FBC 109.3. |
| | BUILDING PERMITS VALUATIONS. |
| | |
| | 5) THE GENERATOR SHALL BE ONE FOOT SIX INCHES (1?-6?) |
| | FROM THE HOUSE, FIVE (5?-0?) FROM THE PROPERTY LINE, |
| | EXHAUST SHALL BE TEN (10?-0?) FROM ANY OPENING UNLESS |
| | OTHERWISE STATED IN THE MANUFACTURES SPECIFICATION |
| | INSTRUCTIONS. |
| | |
| | 6) SUBMIT TWO COPIES OF THE SURVEY INDICATING THE |
| | PROPOSED LOCATION OF THE NEW TANKLESS HEATER AND THE |
| | NEW GENERATOR. WPB AMENDMENTS TO THE FBC SEC. 107.2.1 |
| | |
| | |
| | ATELYO BELISLE |
| | PLUMBING INSPECTOR / |
| | PLUMBING PLANS EXAMINER |
| | AVAILABLE FROM 1:00 PM TO 4:00 PM |
| | [email protected] |
| | 561-805-6695 |
| | |