| 2021-07-14 11:10:28 | REMODEL |
| | REVIEWED BY ROGER MCPHERSON |
| | 561-805-6716 |
| | [email protected] |
| | |
| | CORRECTIONS NEEDED - |
| | 1) BUILDING CODE VERSION SHOWN ON COVER PAGE (001 |
| | CS-000) IS INCORRECT - SHOULD BE 2017 FBC |
| | 2) PLEASE PROVIDE COMPLETE (FRONT PAGES AND THE |
| | INSTALLATION INSTRUCTIONS) PRODUCT APPROVALS FOR THE |
| | NEW EXTERIOR DOORS. FBC WPB AMENDMENTS 107.3.4.1 (ALL |
| | PRODUCT APPROVALS NEED TO BE REVIEWED AND MARKED |
| | APPROVED BY THE DESIGNER OF RECORD IF THE PRODUCT |
| | APPROVAL NUMBERS ARE NOT LISTED ON THE DRAWINGS) |
| | 3) DOOR PRODUCT APPROVALS MAY BE DEFERRED SUBMITTALS BY |
| | LISTING ITEMS TO BE DEFERRED ON THE CONSTRUCTION |
| | DOCUMENTS - 107.3.4.1 DEFERRED SUBMITTALS. FOR THE |
| | PURPOSES OF THIS SECTION, DEFERRED SUBMITTALS ARE |
| | DEFINED AS THOSE PORTIONS OF THE DESIGN THAT ARE NOT |
| | SUBMITTED AT THE TIME OF THE APPLICATION AND THAT ARE |
| | TO BE SUBMITTED TO THE BUILDING OFFICIAL WITHIN A |
| | SPECIFIED PERIOD. DEFERRAL OF ANY SUBMITTAL ITEMS SHALL |
| | HAVE THE PRIOR APPROVAL OF THE BUILDING OFFICIAL. THE |
| | REGISTERED DESIGN PROFESSIONAL IN RESPONSIBLE CHARGE |
| | SHALL LIST THE DEFERRED SUBMITTALS ON THE CONSTRUCTION |
| | DOCUMENTS FOR REVIEW BY THE BUILDING OFFICIAL. |
| | DOCUMENTS FOR DEFERRED SUBMITTAL ITEMS SHALL BE |
| | SUBMITTED TO THE REGISTERED DESIGN PROFESSIONAL IN |
| | RESPONSIBLE CHARGE WHO SHALL REVIEW THEM AND FORWARD |
| | THEM TO THE BUILDING OFFICIAL WITH A NOTATION |
| | INDICATING THAT THE DEFERRED SUBMITTAL DOCUMENTS HAVE |
| | BEEN REVIEWED AND FOUND TO BE IN GENERAL CONFORMANCE TO |
| | THE DESIGN OF THE BUILDING. THE DEFERRED SUBMITTAL |
| | ITEMS SHALL NOT BE INSTALLED UNTIL THE DEFERRED |
| | SUBMITTAL DOCUMENTS HAVE BEEN APPROVED BY THE BUILDING |
| | OFFICIAL. |
| | |
| | |
| | |