| Date |
Text |
| 2020-01-23 15:46:47 | BUILDING REVIEW COMMENTS: |
| | |
| | W.P.B. PERMIT: 19051045 |
| | REVIEWED: JANUARY 23, 2020 |
| | |
| | DYLAN BATTLES |
| | BUILDING PLANS EXAMINER PX4191 |
| | [email protected] |
| | 561-805-6718 |
| | |
| | FLORIDA BUILDING CODE,6TH EDITION (2017) |
| | FBC[AMENDED] = 2017 CHAPTER 1 WPB AMENDMENTS (SEE LINK |
| | BELOW) |
| | HTTPS://WPB.ORG/DEPARTMENTS/DEVELOPMENT-SERVICES/FORMS/ |
| | BUILDING-PERMIT-FORMS |
| | FBC[B] = FBC BUILDING |
| | FBC[EXISTING] = FBC EXISTING BUILDING |
| | FBC[A] = FBC ACCESSIBILITY |
| | FBC[E] = FBC ENERGY CONSERVATION |
| | |
| | PLEASE PROVIDE SEPARATE PERMIT APPLICATION FOR THE |
| | ANCHOR SPACES IN THE SOUTH BUILDING. THAT STRUCTURE AND |
| | THE PARKING GARAGE ARE SEPARATE BUILDINGS AND LOCATED |
| | ON PARCELS WITH DIFFERENT PCN. |
| | ALSO, THESE PROJECTS HAVE DIFFERENT INSPECTION |
| | REQUIREMENTS AND CERTIFICATE OF OCCUPANCY WILL BE |
| | ISSUED ONLY FOR PARKING GARAGE. |
| | PERMIT 19051045 WILL BE FOR THE PARKING GARAGE SINCE |
| | THE ADDRESS WILL REMAIN AS STATED ON PERMIT |
| | THE NEW PERMIT WILL BE FOR ANCHOR SPACES AND ADDRESSES |
| | WILL NEED TO BE ASSIGNED TO EACH SPACE. |
| | THE SAME DRAWINGS WILL BE USED FOR THIS ADDITIONAL |
| | PERMIT SO NO ADDITIONAL DRAWINGS NEED TO BE SUPPLIED. |
| | |
| | I WILL SEPARATE COMMENTS ON THIS REVIEW |
| | THE PARKING GARAGE COMMENTS ARE BELOW. |
| | COMMENTS FOR THE ANCHOR SPACES TO FOLLOW, AND THEY WILL |
| | BE ADDED TO THE NEW PERMIT PLAN REVIEW. |
| | |
| | DB SPOKE TO EC AND THEY HAVE ALREADY WORKED OUT THEIR |
| | AIPP. |
| | VERIFICATION WILL BE ADDED TO PROVISOS. |
| | ART IN PUBLIC PLACES. THE CITY OF WEST PALM BEACH ART |
| | IN PUBLIC PLACES ORDINANCE REQUIREMENT THAT APPLIES TO |
| | ANY REMODEL OR NEW CONSTRUCTION PROJECT FOR WHICH THE |
| | PERMIT APPLICATION WAS SUBMITTED AFTER 6/29/14, AND THE |
| | TOTAL PROJECT CONSTRUCTION COSTS ARE EQUAL TO OR |
| | GREATER THAN $750,000 WILL NEED TO COMPLY WITH THIS |
| | ORDINANCE. PER CITY OF WEST PALM BEACH ORDINANCE NO. |
| | 4504-14, AND CITY OF WEST PALM BEACH CODE OF |
| | ORDINANCES, ARTICLE V, ART IN PUBLIC PLACES, SECTION |
| | 78-123(A) AND SECTION 78-126(A), THE ART ASSESSMENT IS |
| | 1% OF THE TOTAL PROJECT CONSTRUCTION COST. PER CITY OF |
| | WEST PALM BEACH CODE OF ORDINANCES, ARTICLE V, ART IN |
| | PUBLIC PLACES, SECTION 78-122, RENOVATION AND NEW |
| | CONSTRUCTION PROJECTS ARE ASSESSED CUMULATIVELY, SO THE |
| | ART ASSESSMENT WILL BE APPLICABLE TO ALL FUTURE |
| | PROJECTS. SEC. 78-129. - PUBLIC ART ASSESSMENT FOR |
| | PRIVATE DEVELOPMENT. (A) APPLICABILITY. THE PROVISIONS |
| | OF THIS ARTICLE AND THE PUBLIC ART ASSESSMENT SECTION |
| | SHALL APPLY TO ALL PRIVATE DEVELOPMENT PROJECTS, |
| | INCLUDING NEW CONSTRUCTION, OR THE RENOVATION OR |
| | IMPROVEMENT OF AN EXISTING BUILDING, WHERE TOTAL |
| | CONSTRUCTION COSTS ARE EQUAL TO OR GREATER THAN |
| | $750,000.00. ALL BUILDINGS WITHIN NEW PLANNED |
| | DEVELOPMENTS SHALL BE ASSESSED CUMULATIVELY TOWARDS |
| | THIS ART IN PUBLIC PLACES REQUIREMENT, EVEN IF THE |
| | BUILDINGS ARE PERMITTED SEPARATELY OR DEVELOPED IN |
| | PHASES. THE PROVISIONS OF THIS SECTION APPLY TO NEW |
| | DEVELOPMENT OR NEW CONSTRUCTION WITHIN EXISTING PLANNED |
| | DEVELOPMENTS. |
| | - THIS PROJECT MEETS THE CRITERIA TO PROVIDE AIPP. |
| | PLEASE CONTACT: MS. SYBILLE WELTER ART IN PUBLIC PLACES |
| | COORDINATOR 822-1515 E-MAIL: [email protected] |
| | |
| | THE PARKING GARAGE CAN BE APPROVED WITH PROVISOS. |
| | |
| | PROVISOS: |
| | A) THE PARKING LOT ON GROUND LEVEL WILL NEED TO BE |
| | PERMITTED SEPARATELY. |
| | B) ENGINEERED DRAWINGS FOR THE TILT UP CONSTRUCTION AND |
| | BRACING WILL NEED TO BE REVIEWED PRIOR TO ERECTING THE |
| | PARKING STRUCTURE. |
| | C) RESIDENT INSPECTOR AGREEMENT FOR THE ENGINEER TAH |
| | WILL INSPECT ANY WELDS/BOLTS ASSOCIATED WITH THE |
| | PARKING GARAGE. |
| | D) PROVIDE OPENING CALCULATIONS FOR EACH TIER TO SHOW |
| | THAT THE STRUCTURE MEETS REQUIREMENTS FOR OPEN GARAGE. |
| | CURRENTLY THERE ARE NO ELEVATIONS OR CALCULATIONS TO |
| | REVIEW FOR THE PARKING GARAGE. |
| | E) ENGINEERING FOR HANDRAILS AND GUARDRAILS. |
| | F) SUBMITTAL TO INCLUDE ANY PRODUCT APPROVALS INCLUDING |
| | WINDOWS, STOREFRONT AND DOORS. |
| | G) ROOFING PRODUCT APPROVALS TO BE SUBMITTED WITH SUB |
| | PERMIT APPLICATION. |
| | H) SIGNAGE TO BE SUBMITTED UNDER SEPARATE PERMIT. |
| | SHEETS THAT SHOW SIGNAGE HAVE AN X PLACED ON THEM SINCE |
| | THEY ARE NOT APPROVED. |
| | H) FIRE SPRINKLERS AND FIRE ALARMS TO BE SUBMITTED AS |
| | SEPARATE PERMITS. |
| | I) AIPP COMPLIANCE REQUIRED; VERIFICATION REQUIRED |
| | PRIOR TO C.O. |
| | CONTACT WITHIN 90 DAYS OF PERMIT ISSUANCE. |
| | J) 5) CONSTRUCTION HOURS - 7AM TO 7PM MON-FRI, 8AM TO |
| | 8PM SAT-SUN |
| | |
| | PLEASE PROVIDE COMMENT RESPONSE SHEET TO EXPLAIN HOW |
| | EACH COMMENT IS BEING ADDRESSED. |
| | |
| | PLEASE FEEL FREE TO CONTACT ME AT 561-805-6718 (M-F |
| | 8-5) TO DISCUSS COMMENTS, OR E-MAIL ANYTIME |
| | [email protected] |
| | |
| | |
| | |