| 2019-05-02 08:06:21 | PLUMBING 1ST REVIEW**DENIED** |
| | |
| | ********BACKFLOWS REQUIRED TO HAVE A SEPERATE |
| | PERMIT.********WPB CROSS CONNECTION MANUAL & 107.1 |
| | |
| | 1) VALUE TOO LOW. COST MUST INCLUDE MATERIAL, WHAT |
| | LABOR WOULD COST IF CONTRACTED, PERMIT AND DESIGN FEE. |
| | 109.3 BUILDING PERMIT VALUATIONS. IF, IN THE OPINION OF |
| | THE BUILDING OFFICIAL, THE CLAIMED VALUATION OF |
| | BUILDING, ALTERATION, STRUCTURE, ELECTRICAL, GAS, |
| | MECHANICAL OR PLUMBING SYSTEMS APPEARS TO BE |
| | UNDERESTIMATED ON THE APPLICATION, THE PERMIT SHALL BE |
| | DENIED, UNLESS THE APPLICANT CAN SHOW DETAILED, |
| | QUANTITY ESTIMATES, AND/OR BONA FIDE SIGNED CONTRACTS |
| | (EXCLUDING LAND VALUE) TO MEET THE APPROVAL OF THE |
| | BUILDING OFFICIAL. FOR PERMITTING PURPOSES, VALUATION |
| | OF BUILDINGS AND SYSTEMS SHALL BE TOTAL REPLACEMENT |
| | VALUE TO INCLUDE STRUCTURAL, ELECTRIC, PLUMBING, |
| | MECHANICAL, INTERIOR FINISH, RELATIVE SITE WORK, |
| | ARCHITECTURAL AND DESIGN FEES, MARKETING COSTS, |
| | OVERHEAD AND PROFIT; EXCLUDING ONLY LAND VALUE. |
| | VALUATION REFERENCES MAY INCLUDE THE LATEST PUBLISHED |
| | DATA OF NATIONAL CONSTRUCTION COST ANALYSIS SERVICES |
| | (MARSHALL-SWIFT, MEANS, ETC.), AS PUBLISHED BY |
| | INTERNATIONAL CODE CONGRESS. FINAL BUILDING PERMIT |
| | VALUATION SHALL BE SET BY THE BUILDING OFFICIAL. |
| | |
| | 2) PLAN SUBMITTED SHALL NOT BE IN PENCIL. 2ND PLAN |
| | WHICH IS A COPY IS VERY LIGHT IN SOME AREA. PROVIDE 2 |
| | COPIES OF A PLAN ON APPROVED MATERIAL. FBC 107.2.1 |
| | |
| | 3) PROVIDE PIPE SIZES, RAIN SENSOR, AND REMOVE |
| | LANDSCAPE FROM PLAN. FBC 107.3.5 |
| | |
| | |
| | |
| | TIM HUNT |
| | PLUMBING PLANS EXAMINER/ PLUMBING INSPECTOR |
| | BUILDING DIVISION |
| | CITY OF WEST PALM BEACH |
| | 401 CLEMATIS STREET, 1ST FLOOR |
| | WEST PALM BEACH, FL 33401 |
| | 561-248-2703 |
| | [email protected] |
| | [email protected] |
| | |
| | |
| | |
| | |
| | |