| 2019-10-07 09:50:36 | ***CORRECTIONS*** |
| | PETER E VALENTI |
| | BUILDING PLANS EXAMINER |
| | [email protected] |
| | 561-805-6673 |
| | |
| | FBC = FLORIDA BUILDING CODE, 6TH EDITION (2017) |
| | FBC B = FBC BUILDING |
| | FBC EB = FBC EXISTING BUILDING |
| | FBC A = FBC ACCESSIBILITY |
| | FBC EC = FBC ENERGY CONSERVATION |
| | FBC R = FBC RESIDENTIAL |
| | FBC M = FBC MECHANICAL |
| | |
| | 3RD BUILDING REVIEW: |
| | |
| | 1. FAIL, THE SEPERATE PERMIT APPLICATIONS NEED TO BE |
| | SUBMITTED SEPERATELY. |
| | 2. APPROVED WITH PROVISO, THE ART IN PUBLIC PLACES IS |
| | TO BE COMPLETED PRIOR TO C.O. AND AS PER DIRECTION BY |
| | SYBILLE WELTER. |
| | 3. FAIL, THE SUBMITTED SURVEY IS NOT LEGIBLE, PLEASE |
| | PROVIDE A LEGIBLE SURVEY THAT INCLUDES SETBACKS. |
| | 4. APPROVED. |
| | 5. APPROVED. |
| | 6. APPROVED WITH PROVISO, THE PERMIT APPLICATION IS IN |
| | PROGRESS. |
| | 7. APPROVED WITH PROVISO, A REVISION WILL BE REQUIRED |
| | FOR FIRE RATING THE RADIO PROPOGATION CONDUITS |
| | ENCLOSURE IF DETERMINED TO BE REQUIRED AFTER TESTING |
| | HAS BEEN COMPLETED. |
| | 8. APPROVED. |
| | 9. THE CIVIL/SPRINKLER PLANS (SHEETS 230-243) STILL |
| | SHOW THE FIRE WATER SUPPLY RISER IN THE LANDING IN |
| | FRONT OF DOOR OPENING, WHILE THE EXISTING NOTE ON SHEET |
| | 005 INDICATES THET THE RISER IS TO BE REMOVED AND |
| | RELOCATED. |
| | 10. APPROVED. |
| | 11. APPROVED. |
| | 12. APPROVED AS PROVISO: VERIFY IN FIELD |
| | WITHMANUFACTURER'S SPECIFICATIONS. |
| | 13. APPROVED. |
| | 14. APPROVED. |
| | 15. APPROVED. |
| | 16. APPROVED. |
| | 17. APPROVED AS PROVISO: THE E.O.R NEEDS TO |
| | REVIEW/APPROVE ALL DELEGATED ITEMS INCLUDING ROOFING |
| | MATERIALS/SYSTEMS. |
| | 18. APPROVED. |
| | 19. FAIL, STILL PENDING THE SUBMITTAL OF PRODUCT |
| | APPROVALS FOR: ROOF HATCHES, EFIS SYSTEM, ROOF TOP |
| | VENTILATORS, SHUTTERS, AND SKY LIGHTS. |
| | 20. APPROVED WITH PROVISO, THE PRODUCT APPROVALS HAVE |
| | TO BE REVIEWED (REVIEW STAMPED AND SIGNED) BY DESIGNER |
| | OF RECORD PRIOR TO JURISDICTIONAL APPROVAL. |
| | 21. FAIL, THE DEFERRED SUBMITTALS NEED TO BE LISTED ON |
| | THE CONTRACT DRAWINGS. |
| | 22. APPROVED. |
| | 23. APPROVED. |
| | 24. & 25. NOT REQUIRED. |
| | 26. FAIL, PROVIDE (3) ORIGINAL COMPLETED |
| | THRESHOLD/SPECIAL INSPECTOR AGREEMENT OF UNDERSTANDING |
| | FORMS INCLUDING THE SIGNED OWNER AND CONTRACTOR |
| | AGREEMENT SECTIONS. |
| | 27. NOT REQUIRED ON BUILDING STOP. SEE IMPACT FEE STOP. |
| | 28. FAIL. PROVIDE A TRANSMITTAL /RESPONSE LETTER |
| | LISTING THE ORIGINAL REVIEW COMMENT NUMBER WITH A |
| | DESCRIPTION OF THE REVISION MADE, IDENTIFYING THE SHEET |
| | OR SPECIFICATION PAGE WHERE THE CHANGES CAN BE FOUND. |
| | THIS WILL HELP TO EXPEDITE YOUR PERMIT. THANK YOU FOR |
| | YOUR ANTICIPATED COOPERATION. |
| | |