| Date |
Text |
| 2019-08-19 14:52:20 | 2ND MECHANICAL REVIEW FAIL |
| | |
| | 1) M2.1 & M2.2: AUTOMATICALLY CONTROLLED SHUTOFF |
| | DAMPERS ARE REQUIRED FOR THE O/A DUCTS AT EACH AIR |
| | HANDLER LOCATION - SECTION C403.2.4.3 FBC EC. |
| | |
| | 2) M2.1 & M2.2: PLEASE SHOW THE FLEX DUCT SIZES- |
| | SECTION 603.2 FBC M. |
| | |
| | 3) PROVIDE CONDENSATE DISPOSAL PLANS FOR THE AC SYSTEMS |
| | INCLUDING TYPE AND SIZES OF CONDENSATE PIPING, PIPING |
| | RUNS, PIPING SUPPORTS INSIDE AND ABOVE THE ROOF, AND |
| | DISCHARGE LOCATIONS- SEE SECTION 307.2 FBC M. |
| | |
| | 4) PLEASE PROVIDE AN ENLARGED COMPRESSOR ROOM PLAN AND |
| | EQUIPMENT SCHEDULE. IT APPEARS THAT FUEL OIL TANKS WILL |
| | BE INSTALLED IN THE ROOM WHICH REQUIRES THE ROOM, THE |
| | TANK INSTALLATION, AND VENTILATION SYSTEM TO BE IN |
| | COMPLIANCE WITH NFPA 30. A) PLEASE SUBMIT |
| | MANUFACTURER?S SPECIFICATIONS FOR THE TANKS. B) PROVIDE |
| | THE CLASSIFICATION OF THE FUEL AND SUBMIT AN MSDS |
| | SHEET- SECTION 4.3.1. C) PROVIDE EXHAUST VENTILATION |
| | CALCULATIONS FOR EF-4 AND INDICATE THE SEQUENCE OF |
| | OPERATION- SECTION 24.10.1 NFPA 30, AND SECTION 510.2 |
| | FBC M. |
| | |
| | 5) REQUIRED SUBMITTALS LISTED BELOW SHALL BE PROVIDED |
| | WITH THE CORRECTED PLANS OR MAY BE DEFERRED BY REQUEST. |
| | ALL SUBMITTALS SHALL BEAR THE SHOP DRAWING APPROVAL |
| | STAMP BY THE ENGINEER OF RECORD. |
| | |
| | 1) SIGNED AND SEALED STRUCTURAL ENGINEERING FOR |
| | INSTALLATION OF ALL EXTERIOR MECHANICAL EQUIPMENT (AS |
| | NOTED ABOVE IN COMMENT #10). |
| | 2) C0, N02, CO2, FV SENSORS AND CONTROLLERS. |
| | 3) MOTORIZED DAMPERS. |
| | 4) DUCT SMOKE DETECTORS. |
| | 5) FIRE DAMPERS |
| | 6) GENERATOR |
| | 7) FUEL OIL TANKS |
| | 8) AIR COMPRESSOR |
| | |
| | ALL COMMENTS FROM PREVIOUS PLAN REVIEW |
| | |
| | CHRIS MONTELLO |
| | 561-805-6733 |
| | |
| | |
| | |
| | |
| | |
| | |