| Date |
Text |
| 2019-05-10 09:37:49 | 1ST REVIEW FBC-2017 MECHANICAL |
| | PERMIT #19040448 |
| | 5/10/19 |
| | |
| | CODES IN EFFECT: |
| | |
| | FBC B- FLORIDA BUILDING CODE SIXTH EDITION 2017 |
| | FBC M- FLORIDA MECHANICAL CODE SIXTH EDITION 2017 |
| | FBC EC- FLORIDA ENERGY CONSERVATION CODE SIXTH EDITION |
| | 2017 |
| | FS- FLORIDA STATUTES |
| | FAC- FLORIDA ADMINISTRATIVE CODE |
| | WPB- WEST PALM BEACH AMENDMENTS TO THE FBC SIXTH |
| | EDITION 2017 |
| | |
| | PLAN REVIEW RESULTS: DENIED. |
| | |
| | 1) COMMISSIONING OF THE MECHANICAL AND SERVICE WATER |
| | HEATING SYSTEMS IS REQUIRED PER SECTION C408.2 FBC-17 |
| | ENERGY CONSERVATION. SUBMIT A COMMISSIONING PLAN AS |
| | OUTLINED IN SECTION C408.2.1 AND DESCRIBED IN SECTIONS |
| | C403.2.2- C408.2.3.3. PLEASE NOTE THAT A COPY OF THE |
| | COMMISSIONING REPORT SHALL BE SUBMITTED FOR REVIEW AT |
| | FINAL INSPECTION. |
| | |
| | 2) CLARIFY IF THE FLAMINGO EXHAUST SYSTEM WILL BE |
| | INSTALLED UNDER A SEPARATE PERMIT. CURRENTLY THERE ARE |
| | NO PLANS AND SPECIFICATIONS SUBMITTED EXCEPT FOR THE |
| | EXHAUST FAN- SECTION 107.2.1 WPB. |
| | |
| | 3) SHEET M2.1: AN EXHAUST VENTILATION SYSTEM IS |
| | REQUIRED FOR THE CAR SERVICE RECEPTION ROOM IN |
| | COMPLIANCE WITH TABLE 403.3.1.1 AND SECTION 404 FBC M. |
| | THE ROOM HAVING AN OPENING ON ONLY ONE SIDE DOES NOT |
| | MEET THE REQUIREMENT OF HAVING OPENINGS ON TWO OR MORE |
| | SIDES- SEE SECTIONS 406.5, 406.5.2, AND 406.6 FBC B AND |
| | REVISE THE PLANS AND EXHAUST CALCULATIONS IN THE TABLE |
| | ON SHEET M0.1: |
| | |
| | 4) SHEET M2.1 & M2.2: AN EXHAUST VENTILATION SYSTEM IS |
| | REQUIRED FOR THE CAR SHOWROOM IN COMPLIANCE WITH TABLE |
| | 403.3.1.1 AND SECTION 404 FBC M. ALTHOUGH THE SHOWROOM |
| | IS CLASSIFIED AS A BUSINESS OCCUPANCY PER SECTION 304.1 |
| | FBC B, MOTOR VEHICLES WILL BE PARKED IN THE ROOM, AND |
| | THE ROOM IS OPEN TO THE PUBLIC. REVISE THE PLANS, AND |
| | EXHAUST CALCULATIONS IN THE TABLE ON SHEET M0.1: |
| | |
| | 5) M2.1 RECIRCULATION OF AIR FROM THE SERVICE ROOM INTO |
| | THE LOCKER ROOM IS PROHIBITED PER TABLE 403.3.1.1 |
| | FOOTNOTE B. |
| | |
| | 6) M2.1 & M2.2: AUTOMATICALLY CONTROLLED SHUTOFF |
| | DAMPERS ARE REQUIRED FOR THE O/A DUCTS AT EACH AIR |
| | HANDLER LOCATION - SECTION C403.2.4.3 FBC EC. |
| | |
| | 7) M2.1 & M2.2: PLEASE SHOW THE FLEX DUCT SIZES- |
| | SECTION 603.2 FBC M. |
| | |
| | 8) M2.2 & M2.3: PROVIDE CLEARANCE DISTANCE MEASUREMENTS |
| | FOR THE RTU?S AND ROOF FANS TO THE ROOF EDGES- SECTION |
| | 304.11 FBC M. |
| | |
| | 9) M2.2 & M2.3: PROVIDE CLEARANCE DISTANCE MEASUREMENTS |
| | FOR MECHANICAL AND GRAVITY AIR INTAKES TO EXHAUST AIR |
| | OUTLETS- SECTION 401.4 FBC M. |
| | |
| | 10) M2.2, M2.3, & M7.1: PROVIDE COMPLETE WIND LOAD |
| | ENGINEERING FOR INSTALLATION OF THE RTU'S, ROOFTOP |
| | CONDENSERS AND STANDS, ROOFTOP FANS AND CURBS, AND |
| | GRAVITY VENTILATORS. PLEASE INCLUDE THE DESIGN |
| | CRITERIA- SECTION 1609 FBC B, AND SECTION 301.15 FBC M, |
| | AND FL. PRODUCT APPROVALS AND/OR MIAMI-DADE NOA'S FOR |
| | AC ROOF STANDS AND FAN CURBS. |
| | |
| | 11) PROVIDE CONDENSATE DISPOSAL PLANS FOR THE AC |
| | SYSTEMS INCLUDING TYPE AND SIZES OF CONDENSATE PIPING, |
| | PIPING RUNS, PIPING SUPPORTS INSIDE AND ABOVE THE ROOF, |
| | AND DISCHARGE LOCATIONS- SEE SECTION 307.2 FBC M. |
| | |
| | 12) PROVIDE INSTALLATION DETAILS FOR THE CIRCULATION |
| | FANS IN THE SERVICE AND SERVICE RECEPTION AREAS- |
| | SECTION 107.2.1 WPB, AND SECTION 304.1 FBC M. |
| | |
| | 13) EMERGENCY GENERATOR: A) SHOW THE LOCATION ON THE |
| | MECHANICAL PLANS WITH ALL REQUIRED CLEARANCE DISTANCE |
| | MEASUREMENTS. B) SUBMIT MANUFACTURER'S SPECIFICATIONS |
| | FOR THE GENERATOR, EXHAUST AND FUEL OIL PIPING. C) |
| | SUBMIT THE UL 2200 CERTIFICATE FOR THE GENERATOR. D) |
| | PROVIDE AN ENLARGED DRAWING SHOWING THE EXHAUST FLUE |
| | RUN AND TERMINATION LOCATION, AND THE FUEL OIL PIPING |
| | RUN AND SOURCE LOCATION. E) PROVIDE WIND LOAD |
| | ENGINEERING FOR INSTALLATION OF THE GENERATOR AND ALL |
| | ASSOCIATED EXTERIOR EQUIPMENT- SECTION 301.15 FBC M. |
| | REFERENCES: SECTION 915.1 FBC M, SECTIONS 4.1, 6.1, & |
| | 8.1 NFPA 37, SECTION 4.1 NFPA 110. |
| | |
| | 14) PLEASE PROVIDE AN ENLARGED COMPRESSOR ROOM PLAN AND |
| | EQUIPMENT SCHEDULE. IT APPEARS THAT FUEL OIL TANKS WILL |
| | BE INSTALLED IN THE ROOM WHICH REQUIRES THE ROOM, THE |
| | TANK INSTALLATION, AND VENTILATION SYSTEM TO BE IN |
| | COMPLIANCE WITH NFPA 30. A) PLEASE SUBMIT |
| | MANUFACTURER?S SPECIFICATIONS FOR THE TANKS. B) PROVIDE |
| | THE CLASSIFICATION OF THE FUEL AND SUBMIT AN MSDS |
| | SHEET- SECTION 4.3.1. C) PROVIDE EXHAUST VENTILATION |
| | CALCULATIONS FOR EF-4 AND INDICATE THE SEQUENCE OF |
| | OPERATION- SECTION 24.10.1 NFPA 30, AND SECTION 510.2 |
| | FBC M. |
| | |
| | 15) REQUIRED SUBMITTALS LISTED BELOW SHALL BE PROVIDED |
| | WITH THE CORRECTED PLANS OR MAY BE DEFERRED BY REQUEST. |
| | ALL SUBMITTALS SHALL BEAR THE SHOP DRAWING APPROVAL |
| | STAMP BY THE ENGINEER OF RECORD. |
| | |
| | 1) SIGNED AND SEALED STRUCTURAL ENGINEERING FOR |
| | INSTALLATION OF ALL EXTERIOR MECHANICAL EQUIPMENT (AS |
| | NOTED ABOVE IN COMMENT #10). |
| | 2) C0, N02, CO2, FV SENSORS AND CONTROLLERS. |
| | 3) MOTORIZED DAMPERS. |
| | 4) DUCT SMOKE DETECTORS. |
| | 5) FIRE DAMPERS |
| | 6) GENERATOR |
| | 7) FUEL OIL TANKS |
| | 8) AIR COMPRESSOR |
| | |
| | WHEN RESUBMITTING, IT IS HELPFUL TO PROVIDE A RESPONSE |
| | LETTER ADDRESSING EACH ITEM ALONG WITH THE CITY |
| | RE-SUBMITTAL FORM. ADDITIONALLY, PLEASE INSERT |
| | CORRECTED PLAN SHEETS INTO THE SETS, REMOVE THE |
| | PREVIOUSLY REVIEWED SHEETS AND MARK VOID ON THEM, AND |
| | KEEP THEM WITH THE SUBMITTALS |
| | |
| | CHRISTOPHER L. COLE |
| | MECHANICAL PLANS EXAMINER |
| | 401 CLEMATIS STREET |
| | WEST PALM BEACH FL 33401 |
| | 561-805-6719 |
| | [email protected] |
| | |
| | |
| | |
| | |
| | |
| | |