| 2019-08-22 18:27:32 | THIRD BUILDING REVIEW COMMENTS |
| | CODE: FBC 6TH EDITION (2017) AND CITY AMENDMENTS. |
| | |
| | NOTE; |
| | THE COMMENTS REGARDING THE METAL STRUCTURE WERE NOT |
| | ADDRESSED AT ALL. PLEASE SEE BELOW FOR COPY OF |
| | COMMENTS. IF THERE IS ANY QUESTION, PLEASE FEEL FREE TO |
| | CONTACT ME. |
| | |
| | ORIGINAL COMMENT: |
| | 1- DESIGN CRITERIA FOR METAL STRUCTURE PLANS SUBMITTED: |
| | A)ENGINEER STATES RISK CATEGORY III. ENGINEER NEEDS TO |
| | REVISE THE ULTIMATE AND NOMINAL DESIGN WIND SPEED AS |
| | REQUIRED BY SEC. 1609.3 FBC-BUILDING FOR RISK CATEGORY |
| | III. |
| | NOTE: THE CITY ULTIMATE DESIGN FOR RISK CATEGORY III |
| | AND IV IS 180 MPH. SEE SEC. 120.1 CITY AMENDMENTS. |
| | |
| | B) GENERAL NOTE #2 STATES THAT THIS IS A BUILDING FOR |
| | RISK CATEGORY I. COORDINATE WITH RISK CATEGORY |
| | SPECIFIED ON THE DESIGN CRITERIA. COORDINATE WITH ITEM |
| | ABOVE. SEC. 107.2.1 CITY AMENDMENTS. |
| | |
| | C) ENGINEER STATES WIND EXPOSURE "C". THE DESIGN |
| | PRESSURES SHOWN SEEM TO BE TO LOW FOR BUILDING EXPOSURE |
| | C. ENGINEER TO PROVIDE CALCULATIONS SHOWING HOW THE |
| | DESIGN PRESSURES WERE CALCULATED. NOTE: COORDINATE WITH |
| | ITEM #2(A) ABOVE. SEC. 107.2.1.2 CITY AMENDMENTS. |
| | |
| | D) ENGINEER TO SPECIFY IF THE DESIGN PRESSURES SHOWN |
| | ARE ULTIMATE DESIGN WIND SPEED OR NOMINAL DESIGN WIND |
| | SPEEDS. THE ULTIMATE WIND DESIGN WIND SPED NEEDS TO BE |
| | CONVERTED TO NOMINAL DESIGN WIND SPEEDS. SEC. 1609.3.1 |
| | FBC-BUILDING. |
| | |
| | E) ENGINEER OF RECORD TO CLEARLY MARK ON THE PRODUCT |
| | APPROVAL SUBMITTED THE FASTENING OF THE METAL ROOF |
| | PANELS. NOTE: SEE TABLE "A" OF PRODUCT APPROVAL FOR |
| | MAXIMUM DESIGN PRESSURES AND COORDINATE WITH ITEMS |
| | #2(A) AND 2(C) ABOVE. |
| | SEC. 1609.1 FBC-BUILDING. |
| | |
| | F) ENGINEER OF RECORD TO CLEARLY MARK ON THE PRODUCT |
| | APPROVAL SUBMITTED THE FASTENING OF THE METAL WALL |
| | PANELS. NOTE: SEE TABLE "A" OF PRODUCT APPROVAL FOR |
| | MAXIMUM DESIGN PRESSURES AND COORDINATE WITH ITEMS |
| | #2(A) AND 2(C) ABOVE. |
| | SEC. 1609.1 FBC-BUILDING. |
| | |
| | 2- PROVIDE PRODUCT APPROVAL (2 COPIES) AS REQUIRED BY |
| | FAC 61G20-3.001 FOR: |
| | A)METAL ROOF PANELS SPECIFIED ON PLANS. |
| | |
| | B)METAL WALL PANELS SPECIFIED ON PLANS. |
| | |
| | C) ROLL UP DOORS THAT MET THE DESIGN PRESSURES |
| | CALCULATED BY THE ENGINEER OF RECORD. COORDINATE WITH |
| | ITEM #2(A) AND #2(C) ABOVE. |
| | NOTE: DESIGN PRESSURES FOR ROLL UP DOOR MODEL 203 |
| | SPECIFIED BY THE ENGINEER OF RECORD ON THE APPROVED |
| | PRODUCT LIST DOESN'T MEET THE DESIGN PRESSURES. |
| | |
| | |
| | IN ORDER TO AVOID MULTIPLE SUBMITTALS, PLEASE FEEL FREE |
| | TO CONTACT ME IF YOU HAVE ANY QUESTIONS REGARDING THESE |
| | COMMENTS, |
| | JULIO GOMEZ |
| | COMMERCIAL COMBINATION PLANS EXAMINER |
| | DEVELOPMENT SERVICES DEPARTMENT |
| | BUILDING DIVISION |
| | (561)805-6712 |
| | [email protected] |
| | |