| Plan Review Notes For Permit 19030941 |
| Permit Number |
19030941 |
|
| Review Stop |
FIRE |
| Sequence Number |
3 |
|
| Notes |
| Date |
Text |
| 2019-11-13 14:32:57 | PREVIOUS COMMENTS NOT ADDRESSED: | | | 1. MANUFACTURER PRODUCT SPECIFICATIONS NOT INCLUDED IN | | | ITS ENTIRETY. | | | 2. LOAD TEST PAPERWORK SHALLL BE REQUIRED UPON CALLING | | | IN FOR AN ELECTICAL TRANSFER LOAD TEST. | | | 3. GENERATOR IS TO BE TESTED IN COMPLIANCE WITH NFPA | | | 110: | | | | | | 1.1 THIS STANDARD CONTAINS REQUIREMENTS COVERING THE | | | PERFORMANCE OF EMERGENCY AND STANDBY POWER SYSTEMS | | | PROVIDING AN ALTERNATE SOURCE OF ELECTRICAL POWER TO | | | LOADS IN BUILDINGS | | | AND FACILITIES IN THE EVENT THAT THE PRIMARY POWER | | | SOURCE FAILS. | | | 1.1.1 POWER SYSTEMS COVERED IN THIS STANDARD INCLUDE | | | POWER SOURCES, TRANSFER EQUIPMENT, CONTROLS, | | | SUPERVISORY EQUIPMENT, AND ALL RELATED ELECTRICAL AND | | | MECHANICAL AUXILIARY AND ACCESSORY EQUIPMENT NEEDED TO | | | SUPPLY ELECTRICAL POWER TO THE LOAD TERMINALS OF THE | | | TRANSFER EQUIPMENT. | | | 1.1.2 THIS STANDARD COVERS INSTALLATION, MAINTENANCE, | | | OPERATION, AND TESTING REQUIREMENTS AS THEY PERTAIN TO | | | THE PERFORMANCE | | | OF THE EMERGENCY POWER SUPPLY SYSTEM (EPSS). | | | | | | 7.1.3 THE EPSS EQUIPMENT SHALL BE INSTALLED AS REQUIRED | | | TO MEET THE USER?S NEEDS AND TO BE IN ACCORDANCE WITH | | | ALL OF THE FOLLOWING: | | | (1) THIS STANDARD | | | (2) THE MANUFACTURER?S SPECIFICATIONS | | | (3) THE AUTHORITY HAVING JURISDICTION | | | | | | | | | NOTE: SHEET A,1 AND SD2 ARE NOT INCLUDED IN THIS PACKET | | | SUBMISSION. | | | | | | S. THOMAS | | | 561-804-4728 |
|