| 2019-04-12 12:50:55 | 1ST REVIEW FBC-2017 MECHANICAL |
| | PERMIT #19021196 |
| | 4/12/19 |
| | |
| | CODES IN EFFECT: |
| | |
| | FBC B- FLORIDA BUILDING CODE SIXTH EDITION 2017 |
| | FBC M- FLORIDA MECHANICAL CODE SIXTH EDITION 2017 |
| | FBC EC- FLORIDA ENERGY CONSERVATION CODE SIXTH EDITION |
| | 2017 |
| | FBC FG- FLORIDA FUEL GAS CODE SIXTH EDITION 2017 |
| | FS- FLORIDA STATUTES |
| | FAC- FLORIDA ADMINISTRATIVE CODE |
| | WPB- WEST PALM BEACH AMENDMENTS TO THE FBC SIXTH |
| | EDITION 2017 |
| | |
| | PLAN REVIEW RESULTS: DENIED. |
| | |
| | 1) SHEET M0.2- DESIGN CRITERIA: REFER TO TABLE |
| | 403.3.1.1 FBC M AND PROVIDE MINIMUM OUTDOOR AIR AND |
| | EXHAUST VENTILATION CALCULATIONS FOR THE FACILITY. |
| | PLEASE NOTE THAT THE EXHAUST AIR FLOW RATE SHALL BE 0.9 |
| | CFM PER SF. PLEASE INCLUDE AIR BALANCE CALCULATIONS. |
| | |
| | 2) SHEETS M0.3, & M0.4: IT APPEARS THAT ENERGY RECOVERY |
| | VENTILATORS WILL BE REQUIRED FOR THE SYSTEMS SERVING |
| | THE DOG AND CAT AREAS BASED ON THE EQUIPMENT SCHEDULES |
| | FOR AHU'S 1, 3, 4, 5 AND EF'S 1-5, 1-6, 3-1, 3-2, 4-1, |
| | 4-2, 5-1, 5-2, & 5-3. REFER TO SECTION AND TABLE |
| | C403.2.7 FBC EC. A) THERE IS NO SEQUENCE OF OPERATION |
| | OR CONTROL DIAGRAMS PROVIDED FOR THE EXHAUST FANS. |
| | PLEASE CLARIFY HOW THE CURRENT EXHAUST VENTILATION |
| | SYSTEM WILL OPERATE- SEE SECTION 501.4 FBC M. |
| | |
| | 3) COMMISSIONING OF THE MECHANICAL AND SERVICE WATER |
| | HEATING SYSTEMS IS REQUIRED PER SECTION C408.2 FBC-17 |
| | ENERGY CONSERVATION. SUBMIT A COMMISSIONING PLAN AS |
| | OUTLINED IN SECTION C408.2.1 AND DESCRIBED IN SECTIONS |
| | C403.2.2- C408.2.3.3. PLEASE NOTE THAT A COPY OF THE |
| | COMMISSIONING REPORT SHALL BE SUBMITTED FOR REVIEW AT |
| | FINAL INSPECTION. |
| | |
| | 4) SHEETS A3.3, M2.1 & M2.2: PLEASE PROVIDE |
| | FIRE-RESISTANT WALL SYMBOLS THAT CORRELATE WITH WALL |
| | SYMBOLS ON THE PLAN IN ORDER TO LOCATE DUCT |
| | PENETRATIONS THAT MAY REQUIRE FIRE DAMPERS- SECTION |
| | 107.2.1 WPB AND SECTION 607 FBC M. |
| | |
| | 5) M2.1 & M2.2: PROVIDE A DUCT SMOKE DETECTOR SYMBOL AT |
| | EACH AHU SUPPLY DROP AND A NOTE FOR CLARIFICATION- |
| | SECTION 606.2.1 FBC M. |
| | |
| | 6) M2.1: SUBMIT MANUFACTURER'S SPECIFICATIONS FOR THE |
| | DRYERS AND DRYER EXHAUST DUCTS- SECTION 614.1 FBC FG. |
| | THE DRYERS APPEAR TO BE COMMERCIAL GAS DRYERS THAT |
| | REQUIRE COMBUSTION AIR. REFER TO SECTION 304.6.2 FBC FG |
| | AND VERIFY THE EXTERIOR WALL LOUVER IS SIZED AND |
| | LOCATED PROPERLY IN THE ROOM. A) PROVIDE A DRYER |
| | EXHAUST DIAGRAM INDICATING THE TYPE AND SIZE OF DRYER |
| | EXHAUST DUCTS, TOTAL BRANCH AND TOTAL RUN LENGTHS, |
| | CLEANOUT LOCATIONS, AND TERMINATION LOCATION AND |
| | CAPPING- SECTION 614.9. PLEASE NOTE THAT DUCTS SHALL |
| | HAVE MINIMUM 6? CLEARANCES TO COMBUSTIBLES- SECTION |
| | 614.9 FBC FG. |
| | |
| | 7) M2.1: SUBMIT FL. PRODUCT APPROVAL AND/OR MIAMI-DADE |
| | NOA'S FOR THE AIR INLET AND EXHAUST OUTLET LOUVERS- |
| | RULE 9N-3 FAC. |
| | |
| | 8) M2.1 & M3.6: SUBMIT MANUFACTURER'S SPECIFICATIONS |
| | FOR THE BOILERS AND THE COMBUSTION AIR DUCT AND EXHAUST |
| | FLUE- SECTION 631.1. A) INDICATE THE TYPE AND SIZE OF |
| | COMBUSTION AIR DUCTS AND SHOW THE DUCT RUNS FROM INLET |
| | TO OUTLET- SECTION 304.11 FBC FG. B) INDICATE THE TYPE |
| | AND SIZE OF EXHAUST FLUE VENTS AND SHOW THE DUCT RUN |
| | FROM INLET TO OUTLET- SECTIONS 502 AND 503 FBC FG. C) |
| | SHOW THE BOILER RELIEF VALVE DISCHARGE PIPING RUNS AND |
| | TERMINATION LOCATIONS. |
| | |
| | 9) PROVIDE WIND LOAD ENGINEERING FOR INSTALLATION OF |
| | THE CHILLERS AND PUMPS- SECTION 301.15 FBC M. |
| | |
| | 10) M4.4: PROVIDE THE WIND LOAD DESIGN CRITERIA USED TO |
| | DETERMINE THE METHODS USED TO ANCHOR THE CONDENSERS, |
| | FANS AND FAN CURBS, A) PROVIDE COMPLETE FASTENING AND |
| | ANCHORING DETAILS, AND SUBMIT THE NOA FOR THE CONDENSER |
| | ROOF STAND- RULE 9N-3 FAC. |
| | |
| | 11) PROVIDE DETAILS SHOWING HOW THE ROOF LADDER WILL BE |
| | CONSTRUCTED AND ATTACHED TO THE STRUCTURE- SEE SECTION |
| | 306.5 FBC M. |
| | |
| | 12) EMERGENCY GENERATOR: IT IS NOT CLEAR WHAT TYPE OF |
| | FUEL WILL POWER THE GENERATOR- NATURAL GAS OR DIESEL |
| | FUEL. |
| | A) SUBMIT MANUFACTURER'S SPECIFICATIONS FOR THE |
| | GENERATOR, FUEL PIPING, ENGINE EXHAUST PIPE, MUFFLER, |
| | AND ALL OTHER ASSOCIATED SYSTEM COMPONENTS- SECTION |
| | 304.1 FBC M. B) SUBMIT THE UL 2200 CERTIFICATE OF |
| | COMPLIANCE FOR THE GENERATOR- SECTION 915.1 FBC M. THE |
| | MANUFACTURER'S SPECIFICATIONS AND/OR UL CERTIFICATE |
| | SHALL INDICATE THE GENERATOR IS IN COMPLIANCE WITH NFPA |
| | 37. C) PROVIDE AN EXHAUST PIPE DIAGRAM SHOWING THE |
| | TOTAL SYSTEM RUN AND LENGTH MEASUREMENT, AND |
| | TERMINATION LOCATION, AND CLEARANCE DISTANCES GRAVITY |
| | OR MECHANICAL AIR INTAKES INTO THE BUILDING. PLEASE |
| | INCLUDE ALL COMPONENTS OF THE SYSTEM INCLUDING THE |
| | SILENCER.- SEE SECTION 8.1- 8.4 NFPA 37, AND SECTION |
| | 501.3.1 FBC M. D) PROVIDE WIND LOAD ENGINEERING FOR |
| | ATTACHMENT OF THE GENERATOR TO THE ROOF STRUCTURE- |
| | SECTION 301.15 FBC M. |
| | |
| | |
| | WHEN RESUBMITTING, IT IS HELPFUL TO PROVIDE A RESPONSE |
| | LETTER ADDRESSING EACH ITEM ALONG WITH THE CITY |
| | RE-SUBMITTAL FORM. ADDITIONALLY, PLEASE INSERT |
| | CORRECTED PLAN SHEETS INTO THE SETS, REMOVE THE |
| | PREVIOUSLY REVIEWED SHEETS AND MARK VOID ON THEM, AND |
| | KEEP THEM WITH THE SUBMITTALS |
| | |
| | CHRISTOPHER L. COLE |
| | MECHANICAL PLANS EXAMINER |
| | 401 CLEMATIS STREET |
| | WEST PALM BEACH FL 33401 |
| | 561-805-6719 |