| Date |
Text |
| 2019-04-25 13:30:18 | ****CORRECTIONS**** |
| | W.P.B. PERMIT: 19021196 |
| | REVIEWED: APRIL 25, 2019 |
| | |
| | DYLAN BATTLES |
| | BUILDING PLANS EXAMINER PX4191 |
| | [email protected] |
| | 561-805-6718 |
| | |
| | FBC[AMENDED] = FLORIDA BUILDING CODE,6TH EDITION (2017) |
| | FBC[B] = FBC BUILDING |
| | FBC[EXISTING] = FBC EXISTING BUILDING |
| | FBC[A] = FBC ACCESSIBILITY |
| | FBC[E] = FBC ENERGY CONSERVATION |
| | FBC[R] = FBC RESIDENTIAL |
| | |
| | 1) ART IN PUBLIC PLACES. THE CITY OF WEST PALM BEACH |
| | ART IN PUBLIC PLACES ORDINANCE REQUIREMENT THAT APPLIES |
| | TO ANY REMODEL OR NEW CONSTRUCTION PROJECT FOR WHICH |
| | THE PERMIT APPLICATION WAS SUBMITTED AFTER 6/29/14, AND |
| | THE TOTAL PROJECT CONSTRUCTION COSTS ARE EQUAL TO OR |
| | GREATER THAN $750,000 WILL NEED TO COMPLY WITH THIS |
| | ORDINANCE. PER CITY OF WEST PALM BEACH ORDINANCE NO. |
| | 4504-14, AND CITY OF WEST PALM BEACH CODE OF |
| | ORDINANCES, ARTICLE V, ART IN PUBLIC PLACES, SECTION |
| | 78-123(A) AND SECTION 78-126(A), THE ART ASSESSMENT IS |
| | 1% OF THE TOTAL PROJECT CONSTRUCTION COST. PER CITY OF |
| | WEST PALM BEACH CODE OF ORDINANCES, ARTICLE V, ART IN |
| | PUBLIC PLACES, SECTION 78-122, RENOVATION AND NEW |
| | CONSTRUCTION PROJECTS ARE ASSESSED CUMULATIVELY, SO THE |
| | ART ASSESSMENT WILL BE APPLICABLE TO ALL FUTURE |
| | PROJECTS. SEC. 78-129. - PUBLIC ART ASSESSMENT FOR |
| | PRIVATE DEVELOPMENT. (A) APPLICABILITY. THE PROVISIONS |
| | OF THIS ARTICLE AND THE PUBLIC ART ASSESSMENT SECTION |
| | SHALL APPLY TO ALL PRIVATE DEVELOPMENT PROJECTS, |
| | INCLUDING NEW CONSTRUCTION, OR THE RENOVATION OR |
| | IMPROVEMENT OF AN EXISTING BUILDING, WHERE TOTAL |
| | CONSTRUCTION COSTS ARE EQUAL TO OR GREATER THAN |
| | $750,000.00. ALL BUILDINGS WITHIN NEW PLANNED |
| | DEVELOPMENTS SHALL BE ASSESSED CUMULATIVELY TOWARDS |
| | THIS ART IN PUBLIC PLACES REQUIREMENT, EVEN IF THE |
| | BUILDINGS ARE PERMITTED SEPARATELY OR DEVELOPED IN |
| | PHASES. THE PROVISIONS OF THIS SECTION APPLY TO NEW |
| | DEVELOPMENT OR NEW CONSTRUCTION WITHIN EXISTING PLANNED |
| | DEVELOPMENTS. |
| | - THIS PROJECT MEETS THE CRITERIA TO PROVIDE AIPP. |
| | PLEASE CONTACT: MS. SYBILLE WELTER ART IN PUBLIC PLACES |
| | COORDINATOR 822-1515 E-MAIL: [email protected] |
| | |
| | 2) 106.1 FBC[AMENDED] LIVE LOADS POSTED. WHERE THE LIVE |
| | LOADS FOR WHICH EACH FLOOR OR PORTION THEREOF OF A |
| | COMMERCIAL OR INDUSTRIAL BUILDING IS OR HAS BEEN |
| | DESIGNED TO EXCEED 50 PSF (2.40 KN/M2), SUCH DESIGN |
| | LIVE LOADS SHALL BE CONSPICUOUSLY POSTED BY THE OWNER |
| | IN THAT PART OF EACH STORY IN WHICH THEY APPLY, USING |
| | DURABLE SIGNS. IT SHALL BE UNLAWFUL TO REMOVE OR DEFACE |
| | SUCH NOTICES? |
| | - 106.2 FBC[AMENDED] ISSUANCE OF CERTIFICATE OF |
| | OCCUPANCY. A CERTIFICATE OF OCCUPANCY REQUIRED BY |
| | SECTION 111 SHALL NOT BE ISSUED UNTIL THE FLOOR LOAD |
| | SIGNS, REQUIRED BY SECTION 106.1, HAVE BEEN INSTALLED. |
| | (MECHANICAL LOFTS?) |
| | |
| | 3) 107.2.5 FBC[AMENDED] PROVIDE SURVEY OF PROPERTY |
| | SHOWING EASEMENTS AND DISTANCE FROM PROPERTY LINES TO |
| | NEW STRUCTURE. |
| | |
| | 4) 107.2.5 FBC[AMENDED](FL. STATUTE 472.025)SURVEY TO |
| | BE SIGNED AND SEALED BY THE SURVEYOR OF RECORD. |
| | |
| | 5) 107.3.5 FBC[AMENDED] STRUCTURAL DRAWING CALL FOR |
| | LIGHT GAGE STEEL, METAL DECKING AND 5/8 PLYWOOD. ABOVE |
| | METAL DECKING. SHEET A6.1 SHOWS INSULATION AND THEN |
| | PLYWOOD. |
| | - COORDINATE THESE DETAILS AND PROVIDE ATTACHMENT |
| | DETAIL AND SPACING FOR THE ROOF DECK. |
| | |
| | 6) 107.5.3 FBC[AMENDED] CODE EDITION. |
| | - SHEET A0.1 REFER TO IBC IN SECTION 12 AND 13. PLEASE |
| | CHANGE TO FBC. |
| | |
| | 7) 301.1 FBC[E] CLIMATE ZONE TABLE. |
| | - SHEET A0.1 IN ENERGY CODE SECTION REFERS TO ZONE 2A. |
| | THE PROPOSED STRUCTURE IS IN ZONE 1A. PLEASE REVIEW AND |
| | UPDATE. |
| | |
| | 8) 319 FBC[R] ADDRESS IS NEEDED FOR THIS BUILDING. THE |
| | PERMIT CANNOT BE ISSUED UNTIL AND ADDRESS HAS BEEN |
| | ASSIGNED TO THE PROPERTY. |
| | - PLEASE CALL MICHAEL ORIO BY PHONE AT 561-494-1080, OR |
| | BY E-MAIL [email protected] |
| | |
| | 9) 401.2 FBC[CE] APPLICATION. COMMERCIAL BUILDINGS |
| | SHALL COMPLY WITH ONE OF THE FOLLOWING: |
| | 1. THE REQUIREMENTS OF ANSI/ASHRAE/IESNA 90.1, |
| | EXCLUDING SECTION 9.4.1.1(G) OF THE STANDARD. |
| | 2. THE REQUIREMENTS OF SECTIONS C402 THROUGH C405. IN |
| | ADDITION, COMMERCIAL BUILDINGS SHALL COMPLY WITH |
| | SECTION C406 AND TENANT SPACES SHALL COMPLY WITH |
| | SECTION C406.1.1. |
| | 3. THE REQUIREMENTS OF SECTIONS C402.5, C403.2, C404, |
| | C405.2, C405.3, C405.5, C405.6 AND C407. THE BUILDING |
| | ENERGY COST SHALL BE EQUAL TO OR LESS THAN 85 PERCENT |
| | OF THE STANDARD REFERENCE DESIGN BUILDING. |
| | - IS OPTION 2 BEING UTILIZED FOR THIS PROJECT? PLEASE |
| | REVIEW CODE SECTIONS BEING REFERENCEED ON SHEET A0.1. |
| | YOU SHOULD BE REFERING TO CHAPTER 4 OF FBC ENERGY 2017 |
| | 6TH EDITION. USING TABLEC402.4 IS OK, BUT SHGC SHOULD |
| | BE FOR ZONE 1. IT LOOKS LIKE ZONE 2 DATA WAS USED. |
| | |
| | 10) 606.2 FBC[A] CLEAR FLOOR SPACE. A CLEAR FLOOR SPACE |
| | COMPLYING WITH 305, POSITIONED FOR A FORWARD APPROACH, |
| | AND KNEE AND TOE CLEARANCE COMPLYING WITH 306 SHALL BE |
| | PROVIDED. |
| | - PROVIDE DIMENSION, OR SHOW CLEAR FLOOR SPACE, |
| | ACCESSIBLE STALLS ON ENLARGED BATHROOMS DRAWINGS SHEET |
| | A7.4. (FOR OTHER COMMENTS SEE PLUMBING REVIEW) |
| | |
| | 11) 1028.4 FBC[B] EGRESS COURTS. |
| | A. ARE THE GATES AT THE COURTYARDS ABLE TO BE OPENED |
| | FROM THE EGRESS SIDE? |
| | B. ARE THERE ANY CLOSERS ON DOORS? IF SO PLEASE ADD TO |
| | DOOR SCHEDULE. |
| | |
| | 12) 1604.3.1 FBC[B] DEFLECTIONS. THE DEFLECTIONS OF |
| | STRUCTURAL MEMBERS SHALL NOT EXCEED THE MORE |
| | RESTRICTIVE OF THE LIMITATIONS OF SECTIONS 1604.3.2 |
| | THROUGH 1604.3.5 OR THAT PERMITTED BY TABLE 1604.3. |
| | - IF STRUCTURAL CALCULATIONS ARE AVAILABLE, PLEASE |
| | UPLOAD INTO SUPPORTING DOCUMENTS. |
| | |
| | 13) 1606.2 FBC[B] DESIGN DEAD LOAD. FOR PURPOSES OF |
| | DESIGN, THE ACTUAL WEIGHTS OF MATERIALS OF CONSTRUCTION |
| | AND FIXED SERVICE EQUIPMENT SHALL BE USED. IN THE |
| | ABSENCE OF DEFINITE INFORMATION, VALUES USED SHALL BE |
| | SUBJECT TO THE APPROVAL OF THE BUILDING OFFICIAL. |
| | - (PLEASE PROVIDE DEAD LOAD DATA) |
| | |
| | 14) 1607.3 FBC[B] UNIFORM LIVE LOADS. THE LIVE LOADS |
| | USED IN THE DESIGN OF BUILDINGS AND OTHER STRUCTURES |
| | SHALL BE THE MAXIMUM LOADS EXPECTED BY THE INTENDED USE |
| | OR OCCUPANCY BUT SHALL IN NO CASE BE LESS THAN THE |
| | MINIMUM UNIFORMLY DISTRIBUTED LIVE LOADS GIVEN IN TABLE |
| | 1607.1. |
| | - (SEE TABLE 1607.1 FOR MINIMUM LIVE LOADS) |
| | |
| | 15) 1816.1 FBC[B] TERMITE PROTECTION. TERMITE |
| | PROTECTION SHALL BE PROVIDED BY REGISTERED |
| | TERMITICIDES, INCLUDING SOIL APPLIED PESTICIDES, |
| | BAITING SYSTEMS, AND PESTICIDES APPLIED TO WOOD, OR |
| | OTHER APPROVED METHODS OF TERMITE PROTECTION LABELED |
| | FOR USE AS A PREVENTATIVE TREATMENT TO NEW |
| | CONSTRUCTION. SEE SECTION 202, ?REGISTERED |
| | TERMITICIDE.? UPON COMPLETION OF THE APPLICATION OF THE |
| | TERMITE PROTECTIVE TREATMENT, A CERTIFICATE OF |
| | COMPLIANCE SHALL BE ISSUED TO THE BUILDING DEPARTMENT |
| | BY THE LICENSED PEST CONTROL COMPANY THAT CONTAINS THE |
| | FOLLOWING STATEMENT: ?THE BUILDING HAS RECEIVED A |
| | COMPLETE TREATMENT FOR THE PREVENTION OF SUBTERRANEAN |
| | TERMITES. TREATMENT IS IN ACCORDANCE WITH RULES AND |
| | LAWS ESTABLISHED BY THE FLORIDA DEPARTMENT OF |
| | AGRICULTURE AND CONSUMER SERVICES.? |
| | - DO PLANS INDICATE TERMITE TREATMENT? PLEASE INDICATE |
| | PAGE, OR ADD NOTES AS APPLICABLE TO 1816.1. |
| | |
| | 16) 2207.4 FBC[B] STEEL JOIST DRAWINGS. STEEL JOIST |
| | PLACEMENT PLANS SHALL BE PROVIDED TO SHOW THE STEEL |
| | JOIST PRODUCTS AS SPECIFIED ON THE APPROVED |
| | CONSTRUCTION DOCUMENTS AND ARE TO BE UTILIZED FOR FIELD |
| | INSTALLATION IN ACCORDANCE WITH SPECIFIC PROJECT |
| | REQUIREMENTS AS STATED IN SECTION 2207.2. STEEL JOIST |
| | PLACEMENT PLANS SHALL INCLUDE, AT A MINIMUM, THE |
| | FOLLOWING: |
| | 1. LISTING OF APPLICABLE LOADS AS STATED IN SECTION |
| | 2207.2 AND USED IN THE DESIGN OF THE STEEL JOISTS AND |
| | JOIST GIRDERS AS SPECIFIED IN THE APPROVED CONSTRUCTION |
| | DOCUMENTS. |
| | 2. PROFILES FOR JOIST AND JOIST GIRDER CONFIGURATIONS |
| | THAT DIFFER FROM THOSE DEFINED BY THE SJI |
| | SPECIFICATIONS LISTED IN SECTION 2207.1. |
| | 3. CONNECTION REQUIREMENTS FOR: 3.1. JOIST SUPPORTS. |
| | 3.2. JOIST GIRDER SUPPORTS. 3.3. FIELD SPLICES. 3.4. |
| | BRIDGING ATTACHMENTS. |
| | 4. LIVE AND TOTAL LOAD DEFLECTION CRITERIA FOR JOISTS |
| | AND JOIST GIRDER CONFIGURATIONS THAT DIFFER FROM THOSE |
| | DEFINED BY THE SJI SPECIFICATIONS LISTED IN SECTION |
| | 2207.1. |
| | 5. SIZE, LOCATION AND CONNECTIONS FOR BRIDGING. |
| | 6. JOIST HEADERS. STEEL JOIST PLACEMENT PLANS DO NOT |
| | REQUIRE THE SEAL AND SIGNATURE OF THE JOIST |
| | MANUFACTURER?S REGISTERED DESIGN PROFESSIONAL. |
| | - PROVIDE PRE-ENGINEERED ROOF TRUSS SUBMITTAL, OR |
| | INDICATE THAT IT WILL BE A DEFERRED SUBMITTAL. (SEE |
| | BELOW FOR DEFERRED SUBMITTALS) |
| | |
| | 107.3.4.1 FBC[AMENDED] DEFERRED SUBMITTALS. FOR THE |
| | PURPOSES OF THIS SECTION, DEFERRED SUBMITTALS ARE |
| | DEFINED AS THOSE PORTIONS OF THE DESIGN THAT ARE NOT |
| | SUBMITTED AT THE TIME OF THE APPLICATION AND THAT ARE |
| | TO BE SUBMITTED TO THE BUILDING OFFICIAL WITHIN A |
| | SPECIFIED PERIOD. DEFERRAL OF ANY SUBMITTAL ITEMS SHALL |
| | HAVE THE PRIOR APPROVAL OF THE BUILDING OFFICIAL. THE |
| | REGISTERED DESIGN PROFESSIONAL IN RESPONSIBLE CHARGE |
| | SHALL LIST THE DEFERRED SUBMITTALS ON THE CONSTRUCTION |
| | DOCUMENTS FOR REVIEW BY THE BUILDING OFFICIAL. |
| | |
| | DOCUMENTS FOR DEFERRED SUBMITTAL ITEMS SHALL BE |
| | SUBMITTED TO THE REGISTERED DESIGN PROFESSIONAL IN |
| | RESPONSIBLE CHARGE WHO SHALL REVIEW THEM AND FORWARD |
| | THEM TO THE BUILDING OFFICIAL WITH A NOTATION |
| | INDICATING THAT THE DEFERRED SUBMITTAL DOCUMENTS HAVE |
| | BEEN REVIEWED AND FOUND TO BE IN GENERAL CONFORMANCE TO |
| | THE DESIGN OF THE BUILDING. THE DEFERRED SUBMITTAL |
| | ITEMS SHALL NOT BE INSTALLED UNTIL THE DEFERRED |
| | SUBMITTAL DOCUMENTS HAVE BEEN APPROVED BY THE BUILDING |
| | OFFICIAL. |
| | |
| | 17) PLEASE PROVIDE A LIST OF DEFERRED SUBMITTALS SO |
| | THAT I WILL NOT ASK FOR ITEMS THAT WILL BE SUPPLIED AT |
| | A LATER DATE, OR INDICATE WHICH PAGE A LIST CAN BE |
| | FOUND. SOME ITEMS THAT CAN BE DEFERRED INCLUDE WINDOWS, |
| | DOORS, ROOFING, ROOF TRUSSES AND OTHERS THAT APPLY TO |
| | THIS PROJECT. |
| | |
| | 18) SEPARATE PERMIT NEEDED FOR GENERATOR. |
| | |
| | NOTES: |
| | |
| | -PLEASE PROVIDE COMMENT RESPONSE SHEET TO EXPLAIN HOW |
| | EACH COMMENT IS BEING ADDRESSED. |
| | |
| | -COMMENTS ARE A BRIEF OVERVIEW OF CODE SECTIONS. |
| | FURTHER REVIEW OF THE REFERENCED CODE SECTIONS WILL BE |
| | REQUIRED. |
| | |
| | -ADDITIONAL COMMENTS MAY BE FORTHCOMING PENDING REVIEW |
| | OF MATERIALS REQUESTED. |
| | |
| | PLEASE FEEL FREE TO CONTACT ME AT 561-805-6718 (M-F |
| | 8-5) TO DISCUSS COMMENTS, OR E-MAIL ANYTIME |
| | [email protected] |
| | |
| | |
| | |