| 2019-05-09 15:55:29 | COMMERCIAL CHANGE OF OCCUPANCY, SECOND BUILDING REVIEW |
| | CHECKLIST. |
| | CODE: FBC 6TH EDITION (2017) AND CITY AMENDMENTS. |
| | |
| | NOTE: |
| | BUILDING REVIEW MAY BE APPROVED WITH PROVISO. PROVISO |
| | MEANS CONTRACTOR WILL SUBMIT REQUIRED INFORMATION AFTER |
| | THE PERMIT IS ISSUED BUT BEFORE INSPECTIONS TO AVOID |
| | CONFLICTS/DELAYS. REVISION FEES MAY APPLY. CONTRACTOR |
| | TO ADVICE IF PROVISO OPTION IS PREFERRED AT THIS TIME |
| | OR IF RE-SUBMITTING REQUIRED INFORMATION BEFORE PERMIT |
| | ISSUANCE. |
| | |
| | |
| | |
| | |
| | 1- SHEET CS1.0: |
| | A)ACCORDING TO OCCUPANCY LOAD (88 PERSONS) SHOWN ON |
| | SHEET CS1, TWO EXITS ARE REQUIRED. SEC. 1006.2.1 FBC. |
| | LIFE SAFETY PLAN ON SAME SHEET SHOWS ONLY ONE EXIT FOR |
| | THE RETAIL AREA TO THE MAIN ENTRY DOORS AND ONLY ONE |
| | EXIT FOR THE SALES COUNTER AREA TO THE REAR DOORS. THE |
| | TWO EXITS OPTIONS ARE REQUIRED FOR FOR ALL THE PERSONS |
| | IN THIS ESTABLISHMENT. REVISE AS LIFE SAFETY PLAN AS |
| | REQUIRED SHOWING BOTH EXITS AVAILABLE FOR EVERYBODY. |
| | |
| | RESPONSE: |
| | OCCUPANT LOAD CHART AND LIFE SAFETY PLAN SUBMITTED |
| | DON'T REFLECT WHAT WAS SAID ON THE RESPONSE LETTER. |
| | PLEASE REVISE THE OCCUPANT LOAD CHART SHOWING THE |
| | BREAKDOWN OF THE SPACES AS EXPLAINED ON THE RESPONSE |
| | LETTER AND REVISE THE LIFE SAFETY PLAN SHOWING THE |
| | NUMBER OF PEOPLE PER ROOM. ALSO, PROVIDE A NOTE ON PLAN |
| | INDICATING THE POSTING OF THE OCCUPANT LOAD PER ROOM AS |
| | REQUIRED BY SEC. 1004.3 FBC-BUILDING. |
| | |
| | B)CLARIFY HOW EGRESS THROUGH THE SALES COUNTER AREA |
| | FROM THE RETAIL AREA IS GOING TO BE ACHIEVED SINCE THE |
| | DOORS LEADING TO THIS AREA SEEM TO BE LOCKED. SEC. |
| | 1016.2 FBC DOESN'T ALLOW EGRESS THROUGH INTERVENING |
| | SPACES THAT CAN BE LOCKED. |
| | |
| | RESPONSE: |
| | DOOR SCHEDULE AND DOOR HARDWARE SCHEDULE SOWN ON SHEET |
| | A2.0 WERE REVISED AND ARE CONFUSING. DOOR & SECURITY |
| | SCHEDULE, DOOR HARDWARE SCHEDULE AND FLOOR PLAN SHOWING |
| | ALL THE DOORS NEED TO BE COORDINATED. FOR EXAMPLE WHERE |
| | IS HARDWARE SET #3.1. DOOR HARDWARE SCHEDULE SHOW TWO |
| | SINGLE DOORS #EX-02 WITH DIFFERENT HARDWARE #. PROVIDE |
| | FLOOR PLAN SHOWING ALL THE DOOR PROPERLY NUMBERED AND |
| | MATCHING THE DOOR SCHEDULE. |
| | ALSO, THERE ARE NO NOTES SPECIFYING ADA THRESHOLDS AT |
| | THE ENTRY AND EXIT DOORS. |
| | |
| | C)OK. THIS WILL BE COORDINATED WITH ITEM #1A ABOVE. |
| | |
| | 2- BASED ON THE REQUIRED NUMBER OF EXITS REQUIRED BY |
| | THE OCCUPANT LOAD SHOWN ON SHEET CS1.O BOTH EXITS NEED |
| | TO BE ACCESSIBLE MEANS OF EGRESS. PROVIDE DETAILS AND |
| | SPECIFICATIONS SHOWING HOW THE REAR EXIT COMPLIES WITH |
| | THE ACCESSIBLE MEANS OF EGRESS. SEC. 1012.8 FBC |
| | EXISTING BUILDING. SEC. 207 FBC-ACCESSIBILITY AND SEC. |
| | 1007.1 2003 INTERNATIONAL BUILDING CODE. |
| | |
| | RESPONSE: |
| | RAMP SHOWN BY THE REAR EGRESS DOORS SHOWN ON THE LIFE |
| | SAFETY NEEDS TO SHOW THE HANDRAIL REQUIRED BY SEC. |
| | 405.8 FBC-ACCESSIBILITY AND THE RAMP EDGE PROTECTION AS |
| | REQUIRED BY SEC. 405.9 FBC-ACCESSIBILITY. |
| | |
| | 3- CLARIFY BUILDING USE SHOWN ON THE BUILDING CODE |
| | INFORMATION: THIS IS NOT ALTERATION LEVEL 2. ACCORDING |
| | TO SEC. 506 FBC-EXISTING BUILDING THIS IS A CHANGE OF |
| | OCCUPANCY. THE BUILDING IS CURRENTLY USED AS BUSINESS |
| | OCCUPANCY. REVISE AS REQUIRED. |
| | |
| | RESPONSE: |
| | THIS IS NOT ALTERATION LEVEL 2. THIS IS AN ALTERATION |
| | LEVEL 3 (THE WORK AREA EXCEEDS 50 PERCENT OF THE |
| | BUILDING AREA) AND THIS IS A CHANGE OF OCCUPANCY FROM |
| | BUSINESS TO MERCANTILE. |
| | ALSO, NON-SEPARATED OCCUPANCIES IS SEC. 508.3 |
| | FBC-BUILDING NOT SEC. 508.4. |
| | |
| | |
| | 4- OK. THE 18" MIN. ON PULL SIDE TO BE VERIFIED IN THE |
| | FIELD. |
| | |
| | 5- OK. |
| | |
| | 6- PLEASE NOTE THAT SUBMITTAL OF ADDITIONAL AND/OR |
| | REVISED MATERIALS MAY RESULT IN NEW PLAN REVIEW |
| | COMMENTS. |
| | |
| | |
| | WHEN RESUBMITTING PLANS PLEASE INDICATE THE REVISION. A |
| | TRANSMITTAL LETTER LISTING THE ORIGINAL REVIEW COMMENT |
| | NUMBER, WITH A DESCRIPTION OF THE REVISION MADE, |
| | IDENTIFYING THE SHEET OR SPECIFICATION PAGE WHERE THE |
| | CHANGES CAN BE FOUND WILL HELP TO EXPEDITE YOUR PERMIT. |
| | THANK YOU FOR YOUR ANTICIPATED COOPERATION. |
| | |
| | IF YOU HAVE ANY QUESTIONS, PLEASE CONTACT |
| | JULIO GOMEZ |
| | COMMERCIAL COMBINATION PLANS EXAMINER |
| | DEVELOPMENT SERVICES DEPARTMENT |
| | BUILDING DIVISION |
| | (561)805-6712 |
| | [email protected] |
| | |