| 2021-05-26 13:28:33 | FAILED |
| | |
| | 1) SHEET T1 LISTS THE SCOPE OF WORK INCLUDES THE |
| | INSTALLATION OF AN ENCLOSURE CABINET. NONE OF THE PLANS |
| | SHOW AN ENCLOSURE CABINET. PLEASE CLARIFY WHAT THIS |
| | MEANS. THE CITY DOES NOT PERMIT FREESTANDING OR POLE |
| | MOUNTED CABINETS. |
| | |
| | 2) THE POLE STYLE AND HEIGHT MEET CITY REQUIREMENTS. |
| | THE POLE COLOR IS TO MATCH THE EXISTING DECORATIVE CITY |
| | LIGHT POLES (SPECKLED BLACK) LOCATED ON NORTH CLEMATIS |
| | STREET. |
| | |
| | 3) THE GENERAL POLE LOCATION IS APPROVED BY THE SPECIAL |
| | EVENTS AND PLANNING STAFF; HOWEVER, THE PLANS NEED TO |
| | BE UPDATED TO SHOW THE FOLLOWING: |
| | |
| | A. THE STEALTH POLE SHOWN ON SHEET C3, ELEVATION AND |
| | EQUIPMENT PLAN, HAS A 14-INCH DIAMETER. SCALING THE |
| | POLE ON THE SURVEY AND SITE PLAN SHOW A SEVEN (7) INCH |
| | DIAMETER POLE. THE SURVEY AND SITE PLAN NEED TO SHOW |
| | THE CORRECT POLE SIZE AND DIMENSIONS FROM THE VARIOUS |
| | FEATURES SHOWN. |
| | |
| | B. THE CENTER OF THE POLE NEEDS TO BE OFFSET FROM THE |
| | INSIDE EDGE OF THE CURVED CONCRETE VALLEY GUTTER THE |
| | SAME DIMENSION AS THE CENTER OF THE DECORATIVE CONCRETE |
| | SPHERES. THIS SHIFT OF THE PROPOSED WIRELESS POLE A |
| | LITTLE CLOSER TO THE CURB LINE WILL CREATE A UNIFORM |
| | RHYTHM OF STREET FURNITURE ALONG THE CURB LINE. |
| | |
| | 4) THE UTILITY POWER PLAN WAS NOT INCLUDED THAT SHOWS |
| | HOW THE UNDERGROUND POWER IS BEING PROVIDED TO THE |
| | POLE. THE UNDERGROUND POWER PATH, INCLUDING ANY BORE |
| | PITS AND HANDHOLES ARE REQUIRED TO BE SHOWN ON THE |
| | WIRELESS COMMUNICATION FACILITY ROW PERMIT APPLICATION. |
| | |
| | 5) PROVIDE A SURVEY, PREPARED BY A FLORIDA LICENSED |
| | SURVEYOR, SHOWING THE RIGHT-OF-WAY LINE AND THE EDGE OF |
| | THE SIDEWALK, WITH DIMENSIONS FOR THE UNDERGROUND POWER |
| | ROUTE SO THAT STAFF CAN VERIFY THAT IT IS WITHIN A |
| | RIGHT-OR-WAY AND DOES NOT CONFLICT WITH ANY UNDERGROUND |
| | FACILITIES, INCLUDING LANDSCAPE ROOT AREAS. |
| | |
| | 6) THE ENGINEERING PLAN (UTILITY POWER PLAN) NEEDS TO |
| | SHOW THE RIGHT-OF-WAY LINE (BASED ON THE SURVEY) AND |
| | CLEARLY DEMONSTRATE THAT THE HANDHOLES, BORE PITS AND |
| | UNDERGROUND POWER BORE ARE COMPLETELY LOCATED WITHIN |
| | THE RIGHT-OF-WAY. |
| | |
| | CONTACT ERIC SCHNEIDER @ (561) 822-1446 |