| 2019-11-20 14:54:53 | NOTE: |
| | BUILDING REVIEW WILL BE APPROVED WITH PROVISO ONCE THE |
| | OWNER SIGNS AND DATE THE ENERGY CALCULATIONS AS |
| | REQUIRED BY SEC. R103.1.1.2 FBC-ENERGY CONSERVATION TO |
| | ISSUE THE PERMIT. |
| | |
| | |
| | ENERGY CALCULATIONS SUBMITTED: |
| | A)THE BUILDING'S OWNER, THE OWNER'S ARCHITECT OR OTHER |
| | AUTHORIZED AGENT LEGALLY DESIGNATED BY THE OWNER SHALL |
| | CERTIFY THAT THE BUILDING IS IN COMPLIANCE WITH THE |
| | CODE PRIOR TO RECEIVING THE PERMIT AS REQUIRED BY SEC. |
| | R103.1.1.2 FBC-ENERGY CONSERVATION. |
| | |
| | |
| | |
| | |
| | BUILDING REVIEW APPROVED WITH PROVISO (PROVIDE REQUIRED |
| | INFORMATION PRIOR TO INSPECTIONS TO AVOID |
| | CONFLICTS/DELAYS): |
| | 1)ENGINEER TO REVISE WINDOWS DESIGN PRESSURES: DESIGN |
| | PRESSURES SHOWN FOR THE HORIZONTAL ROLLING WINDOWS |
| | SEEMS TO BE TOO LOW BASED ON THE BUILDING EXPOSURE. |
| | PROVIDE CALCULATIONS SHOWING WHY THEY ARE SO LOW. SEC. |
| | 107.2.1.2 CITY AMENDMENTS. ALSO, CLARIFY WHY THE DESIGN |
| | PRESSURES FOR HORIZONTAL ROLLING WINDOW LOCATED IN |
| | BEDROOM #2 ARE THE SAME IF THIS WINDOW SEEMS TO BE |
| | LOCATED IN ZONE 5. (NOTE: ACCORDING TO FIGURE R301.2(7) |
| | THE MINIMUM DISTANCE FOR ZONE 5 IS 4'-0") |
| | |
| | |
| | 2-PROVIDE PRODUCT APPROVAL (2 COPIES) REVIEWED BY |
| | ENGINEER OF RECORD FOR: |
| | A)GARAGE DOORS THAT MEET THE DESIGN PRESSURES |
| | CALCULATED BY THE ENGINEER OF RECORD. |
| | |
| | B)HORIZONTAL SLIDING WINDOWS THAT WILL MEET THE REVISED |
| | DESIGN PRESSURES CALCULATED BY THE ENGINEER OF RECORD. |
| | |
| | C)SINGLE HUNG WINDOWS THAT WILL MEET THE DESIGN |
| | PRESSURES CALCULATED BY THE ENGINEER OF RECORD FOR ALL |
| | SIZES SHOWN ON PLANS. |
| | |
| | D)EXTERIOR SWING DOORS. PROVIDE COMPLETE PRODUCT |
| | APPROVAL. MISSING THE DOOR DRAWINGS. |
| | |
| | 3- PROVIDE COMPLETE HURRICANE SHUTTERS INSTALLATION |
| | SCHEDULE (SEE CITY SAMPLE) FOR REVIEW PRIOR TO |
| | INSPECTION TO AVOID CONFLICTS/DELAYS. |
| | |
| | 4-ENGINEER TO PROVIDE CALCULATIONS FOR THE FASTENING OF |
| | THE GARAGE STRUCTURAL BUCK. SPECIFICATIONS SHOWN ON |
| | STRUCTURAL BUCK DETAIL ON SHEET S.3 DON'T MATCH |
| | SPECIFICATIONS SHOWN ON THE GARAGE DOOR PRODUCT |
| | APPROVAL AND THE STRUCTURAL BUCK IS ATTACHED TO FILLED |
| | CONCRETE BLOCK CELL NOT TO CONCRETE. SEC. 107.2.1.2 |
| | CITY AMENDMENTS. |
| | |
| | |
| | IF YOU HAVE ANY QUESTIONS, PLEASE CONTACT |
| | JULIO GOMEZ |
| | COMMERCIAL COMBINATION PLANS EXAMINER |
| | DEVELOPMENT SERVICES DEPARTMENT |
| | BUILDING DIVISION |
| | (561)805-6712 |
| | [email protected] |
| | |