| 2019-12-19 10:41:25 | ALTERATION/CHANGE OF OCCUPANCY, THIRD BUILDING REVIEW |
| | CHECKLIST. |
| | CODE: FBC 6TH EDITION (2017) AND CITY AMENDMENTS. |
| | |
| | NOTE: |
| | BUILDING REVIEW MAY BE APPROVED WITH PROVISO. PROVISO |
| | MEANS CONTRACTOR WILL SUBMIT REQUIRED INFORMATION AFTER |
| | THE PERMIT IS ISSUED BUT BEFORE INSPECTIONS TO AVOID |
| | CONFLICTS/DELAYS. REVISION FEES APPLY. CONTRACTOR TO |
| | ADVICE IF PROVISO OPTION IS PREFERRED AT THIS TIME OR |
| | IF RE-SUBMITTING REQUIRED INFORMATION BEFORE PERMIT |
| | ISSUANCE. |
| | |
| | |
| | 1- THRU 3. OK |
| | |
| | 4- WATER TREATMENT PLANT ADMINISTRATION BUILDING |
| | -CHEMICAL CONTAINMENT AREAS ENGINEERING SUBMITTED FROM |
| | DARREL J. GRAZIANI, P.E : |
| | NOTES 1 THRU 3 STATES THAT THE WATER PLANT WILL |
| | INITIATE OPERATIONAL CONTROLS TO LIMIT STORAGE OF |
| | GALLONS IN THE CONTAINMENT AREAS UNTIL MODIFICATIONS TO |
| | THE CONTAINMENT AREAS CAN BE DESIGNED, PERMITTED AND |
| | INSTALLED. PLEASE PROVIDE LETTER FROM WATER TREATMENT |
| | PLANT DIRECTOR ACKNOWLEDGING THAT THE OPERATING |
| | CONTROLS SPECIFIED BY THE ENGINEER WILL BE INITIATED. |
| | THIS LETTER OF ACKNOWLEDGMENT IS REQUESTED FOR CITY |
| | FILE TO MAKE SURE THE QUANTITIES OF THE HAZARDOUS |
| | MATERIALS IN THE CONTAINMENT AREAS WILL NOT EXCEED THE |
| | QUANTITIES STATED BY THE ENGINEER OF RECORD AND TABLE |
| | 307.1(2) FBC-BUILDING. OTHERWISE, THE BUILDING WILL BE |
| | CONSIDERED HIGH HAZARD GROUP H-4 AND MIXED OCCUPANCIES |
| | WILL NOT ALLOWED AND ADDITIONAL REQUIREMENTS WILL |
| | APPLY. |
| | |
| | |
| | 5- THRU 10. OK |
| | |
| | 11- REPEAT COMMENT. REVISE THE STRUCTURAL DESIGN |
| | CRITERIA & CODES INFORMATION ON SHEET A4.0. |
| | (A) THIS IS AN ESSENTIAL FACILITY, THEN THE ULTIMATE |
| | DESIGN WIND SPEED IS 180 NOT 170. SEE FIGURE 1609.3(2) |
| | FBC AND CITY AMENDMENTS SEC. 120 CITY AMENDMENTS. NOTE: |
| | THIS BUILDING IS IN EXPOSURE D NOT C. REVISE AS |
| | REQUIRED. |
| | |
| | (B) REVISE THE DOORS DESIGN PRESSURES TO CORRESPOND TO |
| | THE REVISION REQUIRED ABOVE. |
| | |
| | (C) REVISE THE REFERENCED ASCE-7. THE CORRECT REFERENCE |
| | IS THE ASCE 7-10 NOT ASCE 7-16. REVISE AS REQUIRED. |
| | |
| | 12- REPEAT COMMENT. ALL EXIT DOORS NEED TO HAVE PANIC |
| | HARDWARE AS REQUIRED BY SEC. 1010.1.10 FBC. REVISE DOOR |
| | HARDWARE SCHEDULE AS REQUIRED (INCLUDING THE EXISTING |
| | DOOR E1). THERE ARE NOT SPECIFICATIONS FOR PANIC |
| | HARDWARE ON EXISTING DOOR E1. PLEAE PROVIDE |
| | INFORMATION. |
| | |
| | 13- 16 OK |
| | |
| | 17- WHEN RESUBMITTING PLANS PLEASE INDICATE THE |
| | REVISION & REMOVE ANY VOIDED SHEETS & REPLACE ANY PAGES |
| | AS NECESSARY. A TRANSMITTAL LETTER LISTING THE ORIGINAL |
| | REVIEW COMMENT NUMBER, WITH A DESCRIPTION OF THE |
| | REVISION MADE, IDENTIFYING THE SHEET OR SPECIFICATION |
| | PAGE WHERE THE CHANGES CAN BE FOUND WILL HELP TO |
| | EXPEDITE YOUR PERMIT. THANK YOU FOR YOUR ANTICIPATED |
| | COOPERATION. |
| | |
| | PLEASE NOTE THAT SUBMITTAL OF ADDITIONAL AND/OR REVISED |
| | MATERIALS MAY RESULT IN NEW PLAN REVIEW COMMENTS. |
| | WHEN RESUBMITTING, IT IS HELPFUL TO PROVIDE A RESPONSE |
| | LETTER ADDRESSING EACH ITEM ALONG WITH THE CITY |
| | RE-SUBMITTAL FORM. PLEASE, ADDITIONALLY, INSERT |
| | CORRECTED PAGES INTO TO SUBMITTAL AND REMOVE/VOID THE |
| | PREVIOUSLY REVIEWED SHEETS. |
| | PLEASE DON'T STAPLE OLD DRAWINGS. SUBMIT OLD DRAWINGS |
| | FOR REFERENCE. |
| | |
| | |
| | IF YOU HAVE ANY QUESTIONS, PLEASE CONTACT |
| | JULIO GOMEZ |
| | COMMERCIAL COMBINATION PLANS EXAMINER |
| | DEVELOPMENT SERVICES DEPARTMENT |
| | BUILDING DIVISION |
| | (561)805-6712 |
| | [email protected] |