Plan Review Notes
Plan Review Notes For Permit 18100540
Permit Number 18100540
Review Stop M
Sequence Number 2
Notes
Date Text
2020-03-10 18:06:302ND REVIEW FBC-2014 MECHANICAL
 PERMIT #18100540
 550 N QUADRILLE BLVD
 3/2/20
  
 CODES IN EFFECT:
  
 FBC B- FLORIDA BUILDING CODE SIXTH EDITION 2014
 FBC M- FLORIDA MECHANICAL CODE SIXTH EDITION 2014
 FBC EC- FLORIDA ENERGY CONSERVATION CODE SIXTH EDITION
 2014
 FBC FG- FLORIDA FUEL GAS CODE SIXTH EDITION 2014
 FS- FLORIDA STATUTES
 FAC- FLORIDA ADMINISTRATIVE CODE
 WPB- WEST PALM BEACH AMENDMENTS TO THE FBC SIXTH
 EDITION 2017
  
 1) ENERGYGAUGE COMPLIANCE REPORT PAGE 47: THE COOLING
 TOWER MUST MEET THE MINIMUM EFFICIENCY REQUIREMENT
 LISTED IN TABLE C403.2.3(8) FBC EC. PLEASE CORRECT THE
 N/A CHECKMARK. A) PLEASE NOTE THAT THE PLANS FOR THE
 PROPOSED PROJECT ARE BEING DESIGNED IN ACCORDANCE WITH
 THE FLORIDA BUILDING CODE- 2014 FIFTH EDITION. AS A
 RESULT THE 2017 VERSION OF THE ENERGYGAUGE COMPLIANCE
 SOFTWARE CANNOT BE USED. PLEASE SUBMIT THE 2014
 ENERGYGAUGE SOFTWARE VERSION.
  
 2) THE STAIR PRESSURIZATION RATIONAL ANALYSIS SHALL BE
 ELECTRONICALLY SIGNED AND SEALED BY THE ENGINEER WHO
 PREPARED THE DOCUMENT- FL. STATUTE 471.025 AND SECTION
 61G15-23.005 FLORIDA ADMINISTRATIVE CODE. IN ADDITION,
 THE ARCHITECT OF RECORD AND THE MECHANICAL ENGINEER OF
 RECORD SHALL EACH PROVIDE A REVIEW AND APPROVAL STAMP
 ON THE DOCUMENT- SECTION 107.2.1 WPB. PLEASE NOTE THAT
 SPECIAL INSPECTION AND COMMISSIONING OF THE SYSTEMS
 SHALL BE CONDUCTED IN ACCORDANCE WITH SECTION 909.18.1
 FBC B, AND A FINAL COMMISSIONING REPORT SHALL BE
 PROVIDED TO THE CITY OF WEST PALM BEACH BUILDING
 DIVISION AND THE WPB FIRE DEPARTMENT AS A CONDITION OF
 RECEIVING A FINAL CERTIFICATE OF OCCUPANCY FOR THE
 BUILDING- SEE SECTIONS 909.3 AND 909.18.8.1- 909.20 FBC
 B. THE ENGINEER OF RECORD AND SMOKE CONTROL ARE ADVISED
 TO LOOK AT THE ISSUES LISTED BELOW.
 A) MISSING FROM THE REPORT IS A DETAILED NARRATIVE
 DESCRIPTION OF HOW THE FIRE ALARM AND PRESSURIZATIONS
 SYSTEMS IN THE TWO TOWERS AND PODIUM WILL COORDINATE
 AND INTERACT TOGETHER UNDER EMERGENCY ALARM CONDITIONS.
 FOR EXAMPLE- WILL ALL THE INTERIOR EXIT STAIRWAYS BE
 PRESSURIZED IN THE TOWERS AND THE PODIUM IF AN ALARM
 OCCURS IN JUST ONE AREA OF THE BUILDING SUCH AS THE
 PODIUM OR ONE OF THE TOWERS, OR WILL JUST THE STAIRWAYS
 IN THE AREA OF THE INCIDENT BE PRESSURIZED?
 B) STAIR 1 HAS AN EXTENSION AT THE GROUND FLOOR THAT IS
 MISLABELED AS A CORRIDOR, AND SHOULD BE LABELED AS AN
 EXIT PASSAGEWAY- SECTION 1022.3.1 FBC B. THE PASSAGEWAY
 SHALL BE PRESSURIZED IN THE SAME MANNER AS THE
 STAIRWAY- SECTION 1022.10.1 FBC B.
 C) ITEM 4.2 OF THE REPORT SPECIES SMOKE DETECTION AT
 THE ENTRANCE TO THE PRESSURIZED STAIRWELLS, AND DUCT
 SMOKE DETECTORS ARE SHOWN ON THE PLANS IN THE
 PRESSURIZATION DUCTS AND FAN HOUSINGS. PLEASE NOTE THAT
 SECTION 606.2.1 FBC M REQUIRES UL LISTED AND LABELED
 DUCT SMOKE DETECTORS IN THE RETURN DUCTS OF AIR
 DISTRIBUTION SYSTEMS, BUT NOT IN PRESSURIZATION SUPPLY
 DUCTS. PLEASE PROVIDE A WRITTEN SEQUENCE OF OPERATION
 FOR THE DETECTORS AND A PRODUCT SUBMITTAL. THE
 SUBMITTAL SHALL INDICATE THE DEVICES ARE LISTED AND
 LABELED FOR USE IN PRESSURIZATION SYSTEMS- SECTION
 107.2.1 WPB.
 D) FIRE WRAPPING AND FLAMEBAR DUCTWORK ARE BEING USED
 THROUGHOUT THE BUILDING TO PROVIDE THE REQUIRED 2-HR.
 FIRE BARRIER ENCLOSURE FOR THE PRESSURIZATION DUCTS
 THAT ARE CONNECTING THE O/A INLETS AND FANS TO THE
 STAIRWAYS. 1) FIRE WRAP: PLEASE VERIFY AND ACKNOWLEDGE
 IN THE ANALYSIS THAT THE WRAPPING HAS THE REQUIRED UL
 LISTING AND LABELING TO PROVIDE THE REQUIRED FIRE
 RESISTANCE PER SECTION 703.2.1 FBC B. 2) FLAMEBAR:
 PROVIDE A COMPLETE FLAMEBAR DUCTWORK SUBMITTAL PACKAGE
 INCLUDING UL LISTED ASSEMBLIES AND JOB-SPECIFIC
 INSTALLATION DETAILS- JOINTS, CONNECTIONS, SUPPORTS.
 PLEASE NOTE THAT THE MECHANICS ASSEMBLING THE DUCTWORK
 SHALL BE CERTIFIED TO DO THE INSTALLATIONS AND THE
 CERTS SHALL BE ONSITE AT TIME OF INSPECTION.
  
 3) SHEETS M.606 & M.607: PLEASE PROVIDE INDIVIDUAL O/A
 CFM TOTALS FOR THE OFFICE TOWER, HOTEL TOWER, AND
 RESIDENTIAL TOWER AND PODIUM.
 A) INDICATE WHAT THE "K" SYMBOL MEANS THAT IS SHOWN IN
 THE ZONE POPULATION COLUMN OF THE SCHEDULES.
 B) THE PROVIDED (ACTUAL OUTDOOR AIRFLOW RATE) CFMS IN
 MANY OF THE ROOMS AND SPACES SHOWN IN THE TABLES IS
 LESS THAN THE REQUIRED CFMS FOR EXAMPLE THE BALLROOM,
 PREFUNCTION, CONFERENCE, RESIDENTIAL LOBBY, TENNIS
 EVENT, MAIL, FITNESS, HOTEL ELEVATOR LOBBY ETC. PLEASE
 CORRECT THE SCHEDULES- TABLE 403.3.1.1 FBC M.
 C) PROVIDE VENTILATION CALCULATIONS FOR THE INDOOR
 TENNIS COURTS AND THE INDOOR POOL- TABLE 403.3.1.1 FBC
 M.
  
 4) PLEASE NOTE THAT THE PLANS FOR THE PROPOSED PROJECT
 ARE BEING DESIGNED IN ACCORDANCE WITH THE FLORIDA
 BUILDING CODE- 2014 FIFTH EDITION. AS A RESULT, ALL
 PREVIOUS REVIEW COMMENTS REQUIRING DUCT SMOKE DETECTORS
 IN THE SUPPLY SYSTEMS OF THE AIR HANDLERS ARE NOT
 APPLICABLE. WHERE REQUIRED, THE DUCT SMOKE DETECTORS
 SHALL BE INSTALLED IN THE RETURN AIR SYSTEMS.
  
 PODIUM
  
 5) M201, 202, 203, 204, 205: THE REVISED PLANS ARE
 MISSING DUCT SIZES, AND LABELS FOR DUCTS, DIFFUSERS
 RETURN GRILLS, VAV'S, AHU'S, SENSORS ETC.- SECTION
 107.2.1 WPB.
  
 6) M201.A & ALSI.101: THE VESTIBULE AT STAIR #3 IS
 NEITHER FIRE-RATED OR VENTILATED- TABLE 1028.1 FBC B
 AND TABLE 403.3.1.1 FBC M.
  
 7) M201.A: PROVIDE CONSTRUCTION DETAILS FOR THE
 FIRE-RATED PRESSURIZATION DUCT ENCLOSURE AT STAIR #3-
 SECTION 703.2.1 & 717.2.1 FBC B.
  
 8) M201.B: SHOW THE FUTURE TERMINATION LOCATIONS AND
 REQUIRED CLEARANCES FOR THE KITCHEN HOOD GREASE EXHAUST
 DUCT, AND ALL OTHER KITCHEN EXHAUST DUCTS- SEE SECTION
 506 FBC M.
  
 9) M201B: FIRE DAMPERS MISSING AT DUCTS PENETRATING THE
 1-HR FIRE RATED WALLS AT THE RECEIVING, LUGGAGE,
 CORRIDOR 0141, OFFICE ROOM WALLS- SECTION 607.5.2 FBC
 M.
  
 10) M201.C: PROVIDE PRODUCT SUBMITTALS FOR THE DIESEL
 FIRE PUMP AND THE PUMP EXHAUST DUCTWORK- SECTIONS 4.2
 AND 11.5.2.5 NFPA 20. PLEASE NOTE THAT THE SUBMITTALS
 MAY BE DEFERRED BY REQUEST. A) SHOW THE LOCATION OF THE
 PUMP IN THE ROOM AND REFER TO SECTION 11.3.2.4.3 NFPA
 20 FOR EXHAUST REQUIREMENTS FOR RADIATOR-COOLED
 ENGINES. A DIRECT DUCT CONNECTION TO THE PUMP VIA A
 FLEXIBLE SECTION MAY BE REQUIRED. B) PLEASE ADD NOTES
 TO INDICATE THE VENTILATION SYSTEM FOR THE PUMP AS
 DESIGNED WILL BE CAPABLE OF MAINTAINING A MAXIMUM
 TEMPERATURE OF 120 DEGREES F IN THE ROOM, WILL PROVIDE
 ADEQUATE COMBUSTION AIR, AND WILL REMOVE ALL HAZARDOUS
 VAPORS- SECTION 11.3.2.1 NFPA 20. PLEASE NOTE THERE IS
 NO AC SYSTEM IN THE ROOM.
  
 11) M201.C: PROVIDE THE SEQUENCE OF OPERATION FOR THE
 GENERATOR FUEL STORAGE TANK ROOM EXHAUST SYSTEM-
 SECTION 502.8.1.1 FBC M.
  
 12) M.301C & M711- DIESEL FIRE PUMP AND FUEL TANK: A)
 PROVIDE FUEL TANK, FILL AND VENT PIPE SPECIFICATIONS,
 PIPE SIZING CALCULATIONS, PIPE INSTALLATION DETAILS-
 JOINTS AND CONNECTIONS, AND PIPE SUPPORT DETAILS-
 SECTION 1302, 1303, 1305 FBC M. B) SHOW THE REMOTE FILL
 PIPING LOCATION AND FILL PIPING RUN- SECTION 1305.6 FBC
 M. C) INDICATE THE REQUIRED CLEARANCES FOR THE VENT
 PIPING TO BUILDING OPENINGS- SECTION 1305.7 FBC M. IT
 APPEARS THE LOCATIONS ARE STILL INSIDE THE BUILDING
 FOOTPRINT WHICH IS NOT ALLOWED.
  
 13) M301.C & M711- GENERATOR FUEL TANK: PROVIDE THE
 FILL AND VENT PIPING SPECIFICATIONS, PIPE SIZING
 CALCULATIONS, PIPE INSTALLATION DETAILS- JOINTS AND
 CONNECTIONS, AND PIPE SUPPORT DETAILS- SECTION 1302,
 1303, 1305 FBC M. B) THE EMERGENCY VENT LINE FROM THE
 TANK SHALL TERMINATE OUTSIDE OF THE BUILDING- SECTION
 1305.7 FBC M & SECTION 27.8.2.6 NFPA 30. C) INDICATE
 HOW THE LINES WILL BE PROTECTED- SECTION 1305.7 FBC M.
 D) INDICATE THE REQUIRED CLEARANCES FOR THE FILL AND
 VENT PIPING TO BUILDING OPENINGS- SECTION 1305.7 FBC M.
 IT APPEARS THE LOCATIONS ARE STILL INSIDE THE BUILDING
 FOOTPRINT WHICH IS NOT ALLOWED.
  
 14) M.711: THE LOCATIONS OF THE 3-HR. FIRE-RATED FUEL
 LINE SHAFTS THROUGHOUT THE BUILDING ARE NOT SHOWN
 CLEARLY AND ACCURATELY ON THE LIFE SAFETY,
 ARCHITECTURAL, AND MECHANICAL AIR DISTRIBUTION PLANS.
 THE LIFE SAFETY PLANS APPEAR TO SHOW THEM IN THE SAME
 SHAFT WITH AN HVAC DUCT WHICH IS NOT ALLOWED. PLEASE
 SHOW THE LOCATIONS, NOTE THEM CLEARLY ON THE PLANS, AND
 PROVIDE CONSTRUCTION DETAILS FOR THE SHAFT- SECTION
 713.1 FBC B. A) PLEASE EMBOLDEN THE KEY NOTES IN THE
 DIAGRAM.
  
 15) M201.C: PROVIDE A SUBMITTAL FOR THE 2-HR FIRE RATED
 EXHAUST DUCT WRAP. PLEASE NOTE THE WRAP SHALL BE LISTED
 AND LABELED FOR USE ON HAZARDOUS EXHAUST DUCTS- SECTION
 510.7.3 FBC M.
  
 16) M201.C NOTE #1: THE 3' CLEARANCE TO OPERABLE
 OPENINGS IS ALLOWABLE FOR EXHAUST DUCTS SERVING A TYPE
 II HOOD ONLY. PLEASE PROVIDE MORE INFORMATION AND
 SUBMIT MANUFACTURER'S SPECIFICATIONS FOR THE HOOD,
 EXHAUST DUCT, AND THE COOKING APPLIANCE- SEE SECTIONS
 506.3.13.3 AND 506.4.2 FBC M. PLEASE NOTE THAT SEPARATE
 PERMITS ARE REQUIRED FOR KITCHEN EXHAUST AND FIRE
 SUPPRESSION SYSTEMS- SECTION 107.2.1 WPB.
  
 17) M201C: CU 5 SHALL BE INSTALLED OUTDOORS IN
 ACCORDANCE WITH THE LISTING AND LABELING OF THE
 APPLIANCE AND MANUFACTURER'S GUIDELINES- SECTION 304.1
 FBC M.
  
 18) M201.C: FIRE DAMPERS MISSING AT THE AHU-13 SUPPLY
 AND RETURN DUCT PENETRATIONS- SECTIONS 606.2 AND
 607.6.1 FBC M.22) M202.B: FIRE DAMPER MISSING FOR THE
 8X6 ERU SUPPLY DUCT PENETRATING FIRE-RATED WALL AT THE
 FIRE LOBBY.
  
 19) M202A AND ALL ENCLOSED GARAGE FLOORS: THE PLANS
 SHOW THE GARAGE FANS WILL BE EXHAUSTING THE AIR INTO
 THE SPACE BETWEEN THE EXTERIOR WALLS AND THE GREEN
 SCREEN. PLEASE VERIFY THAT THE EXHAUST AIR WILL BE ABLE
 TO FLOW FREELY OUT OF THE BUILDING AND NOT BE
 OBSTRUCTED BY THE SCREEN.
  
 20) M202.B, C, & D C: NO O/A PROVIDED AT THE ELEVATOR
 OR FIRE LOBBIES- TABLE 403.3.1.1 AND SECTION 404.3 FBC
 M.
  
 21) M202.C: SHOW THE SIZE OF THE SPF/01 PRESSURIZATION
 DUCT- SECTION 107.2.1 WPB.
  
 22) M202.C: FIRE DAMPER MISSING AT THE AHU-13 SUPPLY
 DUCT FLOOR PENETRATION- SECTION 607.6.1 FBC M.
  
 23) M202.C & D - M206.C & D: ACCORDING TO THE SCHEDULE
 AHU-14 SUPPLYING AIR TO THE RESIDENTIAL UNITS (AND ALL
 OTHER AHU'S IN THE SCHEDULE ON SHEET M.602) IS NOT
 BEING EQUIPPED WITH A MOTORIZED OUTSIDE AIR DAMPER
 (NOTE #8 IN THE SCHEDULE). THE PLAN SHOWS AN ACD FOR
 AHU-14, HOWEVER PLEASE NOTE SECTION C403.2.4.4 FBC EC
 REQUIRES OUTDOOR AIR SUPPLY DUCTS TO BE EQUIPPED WITH
 GRAVITY OR MOTORIZED DAMPERS THAT WILL AUTOMATICALLY
 SHUT WHEN THE SYSTEMS OR SPACES ARE NOT IN USE. PROVIDE
 DAMPERS FOR EACH DUCT SUPPLYING O/A TO THE VHP'S.
  
 24) M202 C & D- M206.C & D, M605, M707: REFER TO
 SECTION 504.8 FBC M AND PROVIDE THE FOLLOWING DETAILS
 AND INFORMATION CONCERNING THE CLOTHES DRYER EXHAUST
 SYSTEMS- TYPE OF DUCTWORK, SEQUENCE OF OPERATION FOR
 THE EXHAUST FANS, AND HOW MAKEUP AIR IS BEING PROVIDED.
 A) PROVIDE AIR BALANCE CALCULATIONS FOR THE RESIDENTIAL
 UNITS THAT INCLUDE THE CLOTHES DRYER AND TOILET EXHAUST
 SYSTEMS.
  
 25) M203.B, C, & D C: NO O/A PROVIDED AT THE ELEVATOR
 OR FIRE LOBBIES- TABLE 403.3.1.1 AND SECTION 404.3 FBC
 M.
  
 26) M203.B, 204.B, 205.B, 206.B: IT APPEARS THAT
 FIRE-WRAPPING IS BEING USED TO CREATE CONTINUOUS
 VERTICAL TO HORIZONTAL SHAFTS FOR THE ERU-01 SUPPLY
 DUCTS AND THE RETURN/SMOKE PURGE DUCTS. PLEASE PROVIDE
 A UL LISTED ASSEMBLY SHOWING THE FIRE WRAPPING USED IN
 THIS CONFIGURATION- PLEASE SEE SECTION 703.2.1 FBC B.
  
 27) M203.B- M206.B: SECTION C403.2.4.4 FBC EC REQUIRES
 OUTDOOR AIR SUPPLY DUCTS TO BE EQUIPPED WITH GRAVITY OR
 MOTORIZED DAMPERS THAT WILL AUTOMATICALLY SHUT WHEN THE
 SYSTEMS OR SPACES ARE NOT IN USE. PROVIDE DAMPERS FOR
 EACH DUCT SUPPLYING O/A TO THE FCU'S.
  
 28) M204.C, & D: NO O/A PROVIDED AT THE ELEVATOR OR
 FIRE LOBBIES- TABLE 403.3.1.1 AND SECTION 404.3 FBC M.
  
 29) M205.B: CU-2 SHALL BE INSTALLED OUTDOORS IN
 ACCORDANCE WITH THE LISTING AND LABELING OF THE
 APPLIANCE AND MANUFACTURER'S GUIDELINES- SECTION 304.1
 FBC M.
  
 30) M205.B: SUBMIT MANUFACTURER'S SPECIFICATIONS FOR
 THE WATER HEATER INTAKE VENT AND EXHAUST FLUE
 FIRE-WRAPPING- SECTION 304.1 FBC M. THE SPECS SHALL
 SHOW THE PRODUCT CAN BE USED FOR THIS TYPE OF
 INSTALLATION IN LIEU OF A FIRE-RATED SHAFT
  
 31) M205.D: NO O/A PROVIDED AT THE ELEVATOR OR FIRE
 LOBBIES- TABLE 403.3.1.1 AND SECTION 404.3 FBC M.
  
 32) M205.C & M206.C: IT APPEARS FD'S ARE MISSING AT THE
 AHU-14 SUPPLY AND RETURN DUCT FLOOR/CEILING
 PENETRATIONS.
  
 33) M205.C: PLEASE CLARIFY THE PURPOSE OF THE FSD SHOWN
 IN THE MIDDLE OF THE 24X20 SUPPLY DUCT FROM AHU-14.
  
 34) M205.C & M206.C POOL EQUIPMENT ROOM: A) PROVIDE A
 POOL EQUIPMENT SCHEDULE AND SUBMIT MANUFACTURER'S
 SPECIFICATIONS FOR THE POOL HEATERS AND DIRECT VENT
 EXHAUST AND INTAKE DUCTS- SECTION 301.3 FBC FG. B)
 PROVIDE A GAS PIPING PLAN AND ISOMETRIC DRAWING-
 SECTION 402.1 FBC FG. C) THE AIR INTAKE LOUVER SHALL
 COMMUNICATE DIRECTLY TO THE OUTDOORS AND CANNOT DRAW
 VENTILATION AIR FROM THE ENCLOSED GARAGE SPACE- TABLE
 403.3.1.1 FOOTNOTE B. D) REFER TO SECTION 414.1.3 FBC B
 AND PROVIDE A LIST OF POOL TREATMENT CHEMICALS AND
 THEIR QUANTITIES TO BE USED AND STORED IN THE ROOM. E)
 INDICATE THE SEQUENCE OF OPERATION FOR EF 62 AND THE
 TYPE OF EXHAUST DUCTWORK TO BE INSTALLED- REFER TO
 SECTIONS 510.2- 510.9 FBC M. F) INDICATE THE REQUIRED
 CLEARANCES FOR THE EXHAUST OUTLET- SECTION 501.3.1 FBC
 M. G) SHOW COMPLIANCE WITH SECTION 305.3.2 FBC FG:
 CONNECTION OF A PARKING GARAGE WITH ANY ROOM IN WHICH
 THERE IS A FUEL-FIRED APPLIANCE SHALL BE BY MEANS OF A
 VESTIBULE PROVIDING A TWO-DOORWAY SEPARATION, EXCEPT
 THAT A SINGLE DOOR IS PERMITTED WHERE THE SOURCES OF
 IGNITION IN THE APPLIANCE ARE ELEVATED IN ACCORDANCE
 WITH SECTION 305.3.
  
 35) M206.A, EMERGENCY GENERATOR: THE EXHAUST DUCT FROM
 EF-53 SHALL RUN INDEPENDENTLY AND DIRECTLY TO THE
 EXTERIOR OF THE BUILDING, AND SHALL NOT CONNECT INTO
 THE RADIATOR EXHAUST PLENUM- SECTION 510.6.7 FBC M.
 PLEASE NOTE THAT THE GENERATOR WILL BE UNDER SEPARATE
 PERMIT. A COMPLETE SEPARATE PLAN AND SUBMITTAL PACKAGE
 WILL BE REQUIRED INCLUDING AN ENLARGED DRAWING OF THE
 EPSS (EMERGENCY GENERATOR) ROOM SHOWING THE LOCATIONS
 OF THE GENERATOR AND SUB-BASE TANK, FUEL OIL PIPE AND
 EXHAUST PIPE RUNS AND TERMINATION LOCATIONS, AND ALL
 OTHER ASSOCIATED EQUIPMENT INCLUDING EMERGENCY
 ELECTRICAL PANELS ETC. PLEASE INCLUDE THE REQUIRED
 CLEARANCE DISTANCE MEASUREMENTS FOR ALL EQUIPMENT VENT
 PIPING RUNS AND SPECIFICATIONS INCLUDING FILL PIPING
 LOCATIONS. THE SUBMITTAL PACKAGE SHALL INCLUDE:
 A) MANUFACTURER'S SPECIFICATIONS FOR THE GENERATOR AND
 THE 190-GALLON FUEL TANK, FUEL PIPING, ENGINE EXHAUST
 PIPE, MUFFLER, AND ALL OTHER ASSOCIATED SYSTEM
 COMPONENTS- SECTION 304.1 FBC M
 B) THE UL 2200 CERTIFICATE OF COMPLIANCE FOR THE
 GENERATOR- SECTION 915.1 FBC M.
 C) THE MANUFACTURER'S SPECIFICATIONS AND/OR UL
 CERTIFICATE SHALL INDICATE THE GENERATOR IS COMPLIANT
 WITH THE NFPA 37 AND NFPA 110 STANDARD AND IS
 CLASSIFIED AS A LEVEL 1 EPSS- SECTION 4.4.1 NFPA 110.
 D) PRODUCT CUT SHEET FOR THE FUEL TANK THAT INCLUDES
 THE TANK'S UL LISTING- UL 142 OR UL 2085- SEE SECTION
 21.4.2.1.1 NFPA 30.
 E) GENERATOR EXHAUST PIPE SPECIFICATIONS AND PROVIDE AN
 EXHAUST PIPE DIAGRAM SHOWING THE TOTAL SYSTEM RUN AND
 LENGTH MEASUREMENT, AND TERMINATION LOCATION PLEASE
 INCLUDE ALL COMPONENTS OF THE SYSTEM INCLUDING THE
 SILENCER, AND ANY CONTRACTOR SUPPLIED PIPING- SEE
 SECTIONS 8.1 ? 8.4 NFPA 37, AND SECTION 501.3.1 FBC M.
 F) BACKPRESSURE CALCULATIONS FOR THE GENERATOR EXHAUST
 PIPE RUN- SECTION 304.1 FBC M.
 G) DETAILS AND SPECIFICATIONS FOR NORMAL AND EMERGENCY
 RELIEF VENTING OF THE TANK, INCLUDING VENT PIPING RUNS
 AND TERMINATION LOCATIONS AT THE EXTERIOR OF THE
 BUILDING- SECTION 24.13 NFPA 30.
  
 36) M206.A: REFER TO SECTION 7.7.1 NFPA 110- 2016 AND
 VERIFY THAT THE VENTILATION AIRFLOW IN THE
 GENERATOR/TANK (EPS) ROOM IS DESIGNED TO LIMIT THE
 MAXIMUM AIR TEMPERATURE IN THE ROOM TO THE MAXIMUM
 AMBIENT AIR TEMPERATURE REQUIRED BY THE GENERATOR
 MANUFACTURER. CONSIDERATION SHALL BE GIVEN TO ALL THE
 HEAT EMITTED TO THE ROOM BY THE ENERGY CONVERTER,
 EXHAUST PIPES, AND ALL OTHER HEAT PRODUCING EQUIPMENT-
 SECTION 7.7.1.1. DESIGN OF THE HEATING, COOLING, AND
 VENTILATION SYSTEM SHALL AMONG OTHER THINGS, INCLUDE
 PROVISIONS FOR FACTORS SUCH AS HEAT, COLD, HUMIDITY,
 LOUVERS, ETC.- SECTION
 'S SPECS FOR THE BOILERS AND WATER HEATERS- SECTIONS
 402.1, 503.1, AND 624.1 FBC FG.
  
 38) M206.B: PROVIDE A DUCT SMOKE DETECTOR IN THE RETURN
 AIR SYSTEM OF ERU-01- SECTION 606.2.1 FBC M.
  
 39) M206.C: NOTE THE REQUIRED CLEARANCES FOR THE
 COMBUSTION AIR INTAKE DUCTS PER MANUFACTURER'S
 SPECIFICATIONS, AND PER SECTION 304.1 (8) FBC FG.
  
 40) M206.C: SHOW O/A SUPPLY TO THE RESIDENTIAL UNITS OR
 INDICATE NATURAL VENTILATION IN THE NOTES- SECTION 402
 FBC M.
  
 41) M206.C: PLEASE PLACE NOTES ON THE PLAN TO INDICATE
 THE WHAT TYPE OF HORIZONTAL 2-HR FIRE-RATED ENCLOSURES
 WILL BE INSTALLED FOR THE DRYER AND TOILET EXHAUST
 DUCTS AND INDICATE WHERE THE DETAILS ARE FOUND IN THE
 PLANS- SECTION 107.2.1 WPB.
  
 42) M206.C: THE REVISED PLAN SHOWS SPF-13 PRESSURIZING
 THE CORRIDOR BUT NOT THE STAIRWAY WHICH IS NOW SHOWN
 CLOSED OFF WITH DOORS- SECTION 909.6 FBC B AND 513.6
 FBC M.
  
 43) M207.A: THE VENTILATION CALCULATIONS SHOWN AT THE
 TOP OF THE PAGE ARE NOT IN COMPLIANCE WITH TABLE
 403.3.1.1 FBC M. PLEASE REVISE AND PROVIDE AIR BALANCE
 CALCULATIONS FOR ALL ROOMS AND SPACES USING EXHAUST
 VENTILATION SYSTEMS- SECTION 501.4 FBC M. A) INCLUDE
 THE AHU SERVING THE LAP POOL IN THE CALCULATIONS.
 PLEASE NOTE THAT THIS APPEARS TO BE A SYSTEM OF SUPPLY
 AND RETURN AIR, HOWEVER THE CALCULATION INDICATES
 O/A/EXHAUST. PLEASE CORRECT OR PROVIDE EXHAUST IN THE
 ROOM.
  
 44) M207.A POOL EQUIPMENT ROOM: A) PROVIDE A POOL
 EQUIPMENT SCHEDULE AND SUBMIT MANUFACTURER'S
 SPECIFICATIONS FOR THE POOL HEATERS AND DIRECT VENT
 EXHAUST AND INTAKE DUCTS- SECTION 301.3 FBC FG. B)
 PROVIDE A GAS PIPING PLAN AND ISOMETRIC DRAWING-
 SECTION 402.1 FBC FG. C) REFER TO SECTION 414.1.3 FBC B
 AND PROVIDE A LIST OF POOL TREATMENT CHEMICALS AND
 THEIR QUANTITIES TO BE USED AND STORED IN THE ROOM. D)
 INDICATE THE SEQUENCE OF OPERATION FOR EF 48 AND THE
 TYPE OF EXHAUST DUCTWORK TO BE INSTALLED- REFER TO
 SECTIONS 510.2- 510.9 FBC M. E) INDICATE THE REQUIRED
 CLEARANCES FOR THE EXHAUST OUTLET- SECTION 501.3.1 FBC
 M.36
  
 45) M207.A LAUNDRY: PLACE A NOTE INDICATING UNDER
 SEPARATE PERMIT AS WAS INDICATED IN THE RESPONSE
 NARRATIVE.
  
 46) M207.B: PER THE NOTE, THE KITCHENS ARE UNDER
 SEPARATE PERMIT, HOWEVER IT WILL BE HELPFUL TO SHOW THE
 PROPOSED LOCATIONS OF KITCHEN HOOD EXHAUST DUCT
 TERMINATIONS ON THE PLAN (THERE IS NO NOTE INDICATING A
 SCRUBBER IS TO BE USED PER THE RESPONSE NARRATIVE).
 PLEASE BE ADVISED THAT THE REQUIREMENT FOR KITCHEN
 EXHAUST MAKEUP AIR TEMPERATURE UNDER SECTION 508.1.1
 WILL BE ENFORCED UNDER THE SEPARATE PERMIT.
  
 47) M207.B: LABEL THE ELEVATOR RELIEF VENT- SECTION
 107.2.1 WPB.
  
 48) M208.A & B: THE RR-4 RETURN FROM THE TENNIS COURTS
 APPEARS TO BE CONNECTED TO TWO SUPPLY DIFFUSERS. WHICH
 SYSTEM(S) ARE THESE DUCTS CONNECTED TO?- SECTION
 107.2.1 WPB.
  
 49) M208.B HOTEL POOL EQUIPMENT ROOM: A) PROVIDE A POOL
 EQUIPMENT SCHEDULE AND SUBMIT MANUFACTURER'S
 SPECIFICATIONS FOR THE POOL HEATERS AND DIRECT VENT
 EXHAUST AND INTAKE DUCTS- SECTION 301.3 FBC FG. B)
 PROVIDE A GAS PIPING PLAN AND ISOMETRIC DRAWING-
 SECTION 402.1 FBC FG. C) REFER TO SECTION 414.1.3 FBC B
 AND PROVIDE A LIST OF POOL TREATMENT CHEMICALS AND
 THEIR QUANTITIES TO BE USED AND STORED IN THE ROOM. D)
 INDICATE THE SEQUENCE OF OPERATION FOR EF-52 AND THE
 TYPE OF EXHAUST DUCTWORK TO BE INSTALLED- REFER TO
 SECTIONS 510.2- 510.9 FBC M. E) INDICATE THE REQUIRED
 CLEARANCES FOR THE POOL ROOM EXHAUST OUTLET- SECTION
 501.3.1 FBC M, AND THE POOL HEATER INTAKE OPENINGS AND
 EXHAUST OUTLETS.
  
 50) M208.C: NO VENTILATION PROVIDED TO THE ELEVATOR
 LOBBY.
 HOTEL TOWER
  
 51) M209, 210, 211, 212: PROVIDE A DETAIL SHOWING THE
 FCU INSTALLATION IN THE CLOSET INCLUDING THE RETURN AIR
 SYSTEM, AND REQUIRED CLEARANCE AND ACCESS FOR SERVICE
 AND REPLACEMENT OF THE UNIT- SECTION 306.1 FBC M.
  
 52) M209-M211 TENNIS COURT SYSTEMS: PLEASE CORRECT THE
 REFERENCES TO PLAN SHEETS M.224 AND M.226 WHICH ARE NOT
 RELATED TO THE TENNIS COURT SYSTEMS- SECTION 107.2.1
 WPB.
  
 53) M209 & M210: THE DRYERS APPEAR TO BE REMOVED FROM
 THE HOTEL FLOOR PLANS. PLEASE REMOVE GENERAL NOTE #3
 CONCERNING THE MAKEUP AIR IN THE CLOSETS.
  
 54) M209, M210, M211, & M212: THE KITCHEN EXHAUST SHALL
 RUN INDEPENDENTLY AND NOT BE CONNECTED TO THE TOILET
 EXHAUST DUCT SYSTEM- SECTIONS 501.2 & 505.1 FBC M.
  
 OFFICE TOWER
  
 55) M.701 AND ALL OFFICE FLOOR PLAN SHEETS: PROVIDE
 DUCT SMOKE DETECTORS AT EACH FLOOR LEVEL OF THE ERU-03
 RETURN AIR RISER- SECTION 606.2.3 FBC M. PROVIDE DS
 SYMBOLS ON THE PLANS TO INDICATE THE LOCATIONS.
  
 56) M.218: THE MECHANICAL ROOM VENTILATION CALCULATIONS
 ARE NOT IN COMPLIANCE WITH SECTION 1105.6.3.1 FOR
 NORMAL CONDITIONS, AND SECTION 1105.6.3.2 FOR EMERGENCY
 CONDITIONS. PLEASE CORRECT THE CALCULATIONS AND PROVIDE
 A SEQUENCE OF OPERATION FOR EF-58.
  
 57) M.218 & M.603: PROVIDE THE MISSING PERFORMANCE DATA
 FOR THE COOLING TOWERS IN THE SCHEDULE.
  
 58) M.218: PROVIDE SITE SPECIFIC STRUCTURAL ENGINEERING
 FOR INSTALLATION OF THE COOLING TOWERS, CONDENSER
 UNITS, ROOFTOP AND ALL OTHER EXPOSED MECHANICAL
 EQUIPMENT AND APPLIANCES- SECTION 301.15 FBC M. PLEASE
 NOTE THE ENGINEERING MAY BE DEFERRED AND CAN BE NOTED
 AS SUCH ON THE PLAN SHEET.
  
 59) M.219: IT APPEARS THAT AN AC-4 AND AC-9 ARE TO BE
 INSTALLED INSIDE THE ELEVATOR HOISTWAYS WHICH IS
 PROHIBITED- SECTION 303.8 FBC M.
  
 60) THERE ARE NO COOLING AND HEATING CALCULATIONS FOR
 ERU-03 & OAU-1.
  
 RESIDENTIAL TOWER
  
 61) M.220: PROVIDE A DUCT SMOKE DETECTOR IN THE RETURN
 AIR SYSTEM OF AHU-12- SECTION 606.2.1 FBC M.
  
 62) M.222: CHANGE THE REFERENCE TO SHEET M.228 TO
 M.229- SECTION 107.2.1 WPB.
  
 63) M.222: PROVIDE CONSTRUCTION DETAILS FOR THE 2-HR
 FIRE-RATED ELEVATOR RELIEF DUCT ENCLOSURE- SECTION
 703.2.1 FBC B.
  
 64) M.227: PROVIDE SITE SPECIFIC STRUCTURAL ENGINEERING
 FOR INSTALLATION OF THE COOLING TOWERS, GENERATOR, OAU
 AND ROOFTOP DUCTWORK, CONDENSING UNITS, AND ALL OTHER
 MECHANICAL EQUIPMENT AND APPLIANCES- SECTION 301.15 FBC
 M. PLEASE NOTE THE ENGINEERING MAY BE DEFERRED AND CAN
 BE NOTED AS SUCH ON THE PLAN SHEET.
  
 65) M.228: PROVIDE SITE SPECIFIC STRUCTURAL ENGINEERING
 FOR INSTALLATION OF ROOFTOP CONDENSING UNITS, AND ALL
 OTHER EXPOSED MECHANICAL EQUIPMENT AND APPLIANCES-
 SECTION 301.15 FBC M. PLEASE NOTE THE ENGINEERING MAY
 BE DEFERRED AND CAN BE NOTED AS SUCH ON THE PLAN SHEET.
  
 66) M.228: IT APPEARS THAT AN AC-4 IS TO BE INSTALLED
 INSIDE THE ELEVATOR HOISTWAY WHICH IS PROHIBITED-
 SECTION 303.8 FBC M.
  
 67) M.229: LABEL THE MAIN RETURN AIR GRILL AND OPENING
 SIZE- SECTION 601.5 FBC M.
  
 68) M.229: INDICATE THE HEIGHT OF EF-A10 FROM THE
 FINISHED FLOOR- SEE SECTION 306.5 FBC M.
  
 69) M.229: PROVIDE A MECHANICAL ROOF PLAN FOR THE
 TENNIS COURT STRUCTURE WHICH SHOWS THE LOCATIONS OF THE
 CONDENSING UNITS, GRAVITY INTAKES AND EXHAUST FANS AS
 CALLED OUT ON M.229. A) PROVIDE ENGINEERING FOR ALL
 ROOFTOP MECHANICAL INSTALLATIONS- MAY BE DEFERRED WITH
 A NOTE ON THE PLAN. B) PROVIDE CLEARANCE DISTANCE
 MEASUREMENTS FOR ALL SERVICEABLE MECHANICAL EQUIPMENT
 TO ROOF EDGES- SEE SECTION 304.11 FBC M.
  
 70) M.259- M261 RESIDENTIAL UNITS: PLEASE PROVIDE
 DETAILS OR NOTES ON THE PLAN INDICATING COMPLIANCE WITH
 THE FOLLOWING ITEMS.
 A) IDENTIFY ALL ROOMS ON THE PLANS.
 B) PROVIDE A FRONT VIEW DRAWING OF THE AIR HANDLER IN
 THE CLOSET SHOWING REQUIRED CLEARANCES, CONDENSATE
 DISPOSAL DETAILS, SUPPLY PLENUM AND RETURN AIR
 CONNECTIONS.
 C) INDICATE DIFFUSER AND RETURN GRILL DIMENSIONS OR
 PROVIDE A SCHEDULE ON THE PLAN. PLEASE NOTE BALANCED
 RETURN AIR IS REQUIRED- TRANSFER DUCTS SHALL BE SIZED
 1-1/2 TIMES THE AREA OF THE SUPPLY DUCT TO THE ROOM,
 RETURN GRILLS SHALL BE SIZED AT 50 CFMS PER 100 SQ.
 INCHES, AND ALL AIR SUPPLIED TO MASTER BEDROOMS SHALL
 BE RETURNED- SEE SECTION 601.5 FBC M
 D) PROVIDE COOKING APPLIANCE SCHEDULES AND SUBMIT
 MANUFACTURER?S SPECIFICATIONS FOR EACH COOKING
 APPLIANCE. MAY BE DEFERRED AND NOTED AS SUCH ON THE
 PLANS.
 E) PROVIDE EXHAUST VENTILATION FOR THE KITCHENS AT A
 RATE OF 100 CFM INTERMITTENT OR 25 CFMS CONTINUOUS-
 TABLE 403.3.1.1.
 F) SUBMIT MANUFACTURER'S SPECIFICATIONS FOR THE CLOTHES
 DRYERS AND THE DRYER EXHAUST BOOSTER FAN. PLEASE NOTE
 THAT THERE IS NO REQUIREMENT FOR BOOSTER FANS IN THE
 FBC-14 MECHANICAL CODE. DRYERS SHALL BE EXHAUSTED IN
 ACCORDANCE WITH MANUFACTURER?S SPECIFICATIONS AND
 INSTALLATION INSTRUCTIONS- SECTION 504.1 FBC M.
 G) PROVIDE A SUBMITTAL FOR THE X-VENT BOXES.
  
 71) M.501: PROVIDE DUCT CONNECTION, SUPPORT AND HANGING
 DETAILS PER THE CURRENT SMACNA HVAC DUCT CONSTRUCTION
 STANDARD- METAL AND FLEXIBLE 2005, AND SMACNA FIBROUS
 GLASS DUCT- 2010.
  
 72) PLEASE PROVIDE COMPLETE CONDENSATE DISPOSAL PLANS
 INCLUDING RISER DRAWINGS FOR THE TOWER AND PODIUM
 SYSTEMS- SECTION 307.2.1 FBC M.
  
 73) PLEASE LABEL ALL ELEVATOR EQUIPMENT ROOMS ON THE
 PLANS AND SHOW THE REQUIRED VENTILATION SYSTEMS-
 SECTION 3006.2 FBC B.
  
 ENERGY COMPLIANCE REPORT
  
 74) THE PROJECT IS BEING DESIGNED UNDER THE 2014
 FLORIDA BUILDING CODES. SUBMIT THE 2014 ENERGYGAUGE
 COMPLIANCE REPORT.
  
 75) M.218 & M.603: THE SYSTEM FULL LOAD AND IPLV
 COMPLIANCE DATA FOR THE CHILLERS IN THE SCHEDULE DOES
 NOT MATCH THE DATA IN THE ENERGY REPORT- SEE TABLE
 C403.2.3(7) FBC EC.
  
 76) NO COMPLIANCE DATA FOR OAU-1, THE WATER HEATERS,
 SERVICE WATER PIPING, AIR COOLED SPLIT SYSTEMS- AC-1-
 9, INDOOR POOL AHU-08, AND THE CAPACITIES FOR FCU?S
 2-18,
  
 77) M.603: THE TOTAL MBH LISTED IN THE SCHEDULE FOR
 AHU-12, 13, & 14 DOES NOT MATCH THE CAPACITIES LISTED
 IN THE REPORT.
  
 78) M.604: THE CAPACITY LISTED FOR FCU-01 IN THE
 SCHEDULE DOES NOT MATCH THE REPORT.
  
 79) M.604 VHP'S: A) MBH IN SCHEDULE FOR VHP- 2, 3 & 4
 DOESN'T MATCH DATA IN THE REPORT. B) PLEASE INDICATE
 THE NUMBER OF EACH VHP (1-7)) TO BE INSTALLED ON THE
 PROJECT.
  
 80) M.604 HHP'S: A) NO DATA IN THE REPORT FOR HHP-2, 5,
 6, 7, 8, & 9. B) PLEASE INDICATE THE NUMBER OF EACH HHP
 (1-9)) TO BE INSTALLED ON THE PROJECT.
  
 HEAT LOAD CALCULATIONS
  
 81) SHEET M.602: THE COOLING CAPACITIES (MBH) SHOWN IN
 THE AHU AND ERU SCHEDULE ARE EITHER UNDER OR OVER THE
 HEAT LOADS SHOWN IN CALCULATIONS- SECTION C403.2.2 FBC
 EC.
  
 A) AHU-01 OFFICE/LOBBY: SCHEDULE- 207 MBH, CALCS- 436
 MBH.
  
 B) AHU-02 LOBBY/CAFE: SCHEDULE- 158 MBH, CALCS- 177
 MBH.
  
 C) AHU-03 HOTEL LOBBY: SCHEDULE- 275 MBH, CALCS- 320
 MBH
  
 D) AHU-04 RETAIL/RESTAURANT: SCHEDULE- 903 MBH, CALCS-
 773 MBH
  
 E) AHU-05 DAYCARE: SCHEDULE- 126 MBH, CALCS- 193 MBH
  
 F) AHU-07A & B: SCHEDULE 1,417 MBH, CALCS- 1,650 MBH.
  
 G) AHU-08 INDOOR POOL: SCHEDULE- 359 MBH, CALCS- 251
 MBH.
  
 H) AHU-09 FITNESS/SPA: SCHEDULE- 265 MBH, CALCS- 667
 MBH.
  
 I) AHU-10A & B TENNIS COURT ASSEMBLY: SCHEDULE- 1,387
 MBH, CALCS- 1,552 MBH. PLEASE NOTE THAT THERE IS
 ANOTHER CALCULATION FOR THE ?TENNIS COURT? INDICATING
 890 MBH. PLEASE CLARIFY.
  
 J) AHU-12 RES/LOUNGE: SCHEDULE- 404 MBH, CALCS- 357
 MBH.
  
 K) AHU-13 RES LOBBY: SCHEDULE- 453 MBH, CALCS
  
 L) ERU-1: SCHEDULE- 761 MBH, CALCS 911 MBH.
  
 M) THERE ARE NO COOLING AND HEATING CALCULATIONS FOR
 ERU-03 & OAU-1.
  
  