| 2019-04-08 17:58:15 | 1ST REVIEW FBC-2017 MECHANICAL |
| | PERMIT #18100540 |
| | 550 N QUADRILLE BLVD |
| | 4/2/19 |
| | CODES IN EFFECT: |
| | |
| | FBC B- FLORIDA BUILDING CODE SIXTH EDITION 2017 |
| | FBC M- FLORIDA MECHANICAL CODE SIXTH EDITION 2017 |
| | FBC EC- FLORIDA ENERGY CONSERVATION CODE SIXTH EDITION |
| | 2017 |
| | FBC FG- FLORIDA FUEL GAS CODE SIXTH EDITION 2017 |
| | FS- FLORIDA STATUTES |
| | FAC- FLORIDA ADMINISTRATIVE CODE |
| | WPB- WEST PALM BEACH AMENDMENTS TO THE FBC SIXTH |
| | EDITION 2017 |
| | PLAN REVIEW RESULTS: DENIED. |
| | |
| | THE MECHANICAL PLANS HAVE FAILED FOR THE DEFICIENCIES |
| | AND OMISSIONS LISTED BELOW. PLEASE REVIEW ALL COMMENTS, |
| | INCLUDING THOSE LISTED FOR ADVISORY PURPOSES, AND |
| | RESUBMIT CORRECTED PLANS AND REQUIRED DOCUMENTS. WHEN |
| | RESUBMITTING, PLEASE PROVIDE A RESPONSE LETTER |
| | ADDRESSING EACH ITEM ALONG WITH THE CITY RE-SUBMITTAL |
| | FORM. |
| | PRIOR TO MECHANICAL PERMIT ISSUANCE, THE GENERAL |
| | CONTRACTOR AND MECHANICAL SUB-CONTRACTOR FOR THE |
| | PROJECT ARE REQUESTED TO ATTEND A MEETING AT THE WPB |
| | BUILDING DEPARTMENT WITH THE STAFF- CHIEF MECHANICAL |
| | INSPECTOR, PLANS EXAMINER, AND OTHER OFFICIALS- TO |
| | DISCUSS TIMELINES AND GUIDELINES FOR INSPECTIONS AND |
| | THE DOCUMENT SUBMITTAL PROCESS . FURTHER INFORMATION |
| | WILL FOLLOW ONCE ALL PLANS ARE APPROVED. |
| | |
| | 1) THE FOLLOWING LIST OF DOCUMENTS WERE NOT SUBMITTED |
| | BUT ARE REQUIRED TO PERFORM A COMPLETE MECHANICAL |
| | REVIEW FOR THE PROJECT. |
| | 1A) SMOKE CONTROL RATIONAL ANALYSIS- SECTION 513.4 FBC |
| | M: A RATIONAL ANALYSIS SUPPORTING THE TYPES OF SMOKE |
| | CONTROL SYSTEMS TO BE EMPLOYED, THEIR METHODS OF |
| | OPERATION, THE SYSTEMS SUPPORTING THEM AND THE METHODS |
| | OF CONSTRUCTION TO BE UTILIZED SHALL ACCOMPANY THE |
| | SUBMITTED CONSTRUCTION DOCUMENTS AND SHALL INCLUDE, BUT |
| | NOT BE LIMITED TO, THE ITEMS INDICATED IN SECTIONS |
| | 513.4.1 THROUGH 513.4.7. |
| | 513.4.1 STACK EFFECT: THE SYSTEM SHALL BE DESIGNED SUCH |
| | THAT THE MAXIMUM PROBABLE NORMAL OR REVERSE STACK |
| | EFFECTS WILL NOT ADVERSELY INTERFERE WITH THE SYSTEM'S |
| | CAPABILITIES. IN DETERMINING THE MAXIMUM PROBABLE STACK |
| | EFFECTS, ALTITUDE, ELEVATION, WEATHER HISTORY AND |
| | INTERIOR TEMPERATURES SHALL BE USED. |
| | 513.4.2 TEMPERATURE EFFECT OF FIRE: BUOYANCY AND |
| | EXPANSION CAUSED BY THE DESIGN FIRE IN ACCORDANCE WITH |
| | SECTION 513.9 SHALL BE ANALYZED. THE SYSTEM SHALL BE |
| | DESIGNED SUCH THAT THESE EFFECTS DO NOT ADVERSELY |
| | INTERFERE WITH ITS CAPABILITIES. |
| | 513.4.3 WIND EFFECT: THE DESIGN SHALL CONSIDER THE |
| | ADVERSE EFFECTS OF WIND. SUCH CONSIDERATION SHALL BE |
| | CONSISTENT WITH THE WIND-LOADING PROVISIONS OF THE |
| | FLORIDA BUILDING CODE, BUILDING. |
| | 513.4.4 HVAC SYSTEMS: THE DESIGN SHALL CONSIDER THE |
| | EFFECTS OF THE HEATING, VENTILATING AND |
| | AIR-CONDITIONING (HVAC) SYSTEMS ON BOTH SMOKE AND FIRE |
| | TRANSPORT. THE ANALYSIS SHALL INCLUDE ALL PERMUTATIONS |
| | OF SYSTEMS STATUS. THE DESIGN SHALL CONSIDER THE |
| | EFFECTS OF FIRE ON THE HVAC SYSTEMS. |
| | 513.4.5 CLIMATE: THE DESIGN SHALL CONSIDER THE EFFECTS |
| | OF LOW TEMPERATURES ON SYSTEMS, PROPERTY AND OCCUPANTS. |
| | AIR INLETS AND EXHAUSTS SHALL BE LOCATED SO AS TO |
| | PREVENT SNOW OR ICE BLOCKAGE. |
| | 513.4.6 DURATION OF OPERATION: ALL PORTIONS OF ACTIVE |
| | OR ENGINEERED SMOKE CONTROL SYSTEMS SHALL BE CAPABLE OF |
| | CONTINUED OPERATION AFTER DETECTION OF THE FIRE EVENT |
| | FOR A PERIOD OF NOT LESS THAN EITHER 20 MINUTES OR 1.5 |
| | TIMES THE CALCULATED EGRESS TIME, WHICHEVER IS GREATER. |
| | 513.4.7 SMOKE CONTROL SYSTEM INTERACTION: THE DESIGN |
| | SHALL CONSIDER THE INTERACTION EFFECTS OF THE OPERATION |
| | OF MULTIPLE SMOKE CONTROL SYSTEMS FOR ALL DESIGN |
| | SCENARIOS. |
| | THE SMOKE ANALYSIS SHALL CONTAIN A PROJECT DESCRIPTION |
| | OF SMOKE CONTROL SYSTEMS, SPRINKLER AND STANDPIPE |
| | SYSTEMS, FIRE ALARM SYSTEMS, SHAFT VENTING, AND CONTROL |
| | SYSTEMS. INCLUDED IN THE ANALYSIS SHALL BE SPECIAL |
| | INSPECTION AND TEST REQUIREMENTS, TESTING PROCEDURES, |
| | AND FINAL COMMISSIONING REQUIREMENTS FOR THE SYSTEMS. |
| | IMPORTANT NOTE: ACCEPTANCE TESTING OF THE PROJECT'S |
| | SMOKE CONTROL SYSTEMS SHALL BE COMPLETED UNDER NORMAL |
| | AND EMERGENCY POWER. PLEASE PROVIDE A DESCRIPTION OF |
| | THE EMERGENCY PROCEDURE THAT INCLUDES BOTH EMERGENCY |
| | GENERATORS AND HOW THE FIRE ALARM AND LIFE SAFETY |
| | SYSTEMS IN THE TWO TOWERS AND PODIUM WILL COORDINATE |
| | AND INTERACT TOGETHER. |
| | |
| | 1B) AC COOLING AND HEATING CALCULATIONS- SECTION |
| | C403.2.1 FBC EC: DESIGN LOADS ASSOCIATED WITH HEATING, |
| | VENTILATING AND AIR CONDITIONING OF THE BUILDING SHALL |
| | BE DETERMINED IN ACCORDANCE WITH ANSI/ASHRAE/ACCA |
| | STANDARD 183 OR ACCA MANUAL N OR BY AN APPROVED |
| | EQUIVALENT COMPUTATIONAL PROCEDURE USING THE DESIGN |
| | PARAMETERS SPECIFIED IN CHAPTER 3. HEATING AND COOLING |
| | LOADS SHALL BE ADJUSTED TO ACCOUNT FOR LOAD REDUCTIONS |
| | THAT ARE ACHIEVED WHERE ENERGY RECOVERY SYSTEMS ARE |
| | UTILIZED IN THE HVAC SYSTEM IN ACCORDANCE WITH THE |
| | ASHRAE HVAC SYSTEMS AND EQUIPMENT HAND-BOOK BY AN |
| | APPROVED EQUIVALENT COMPUTATIONAL PROCEDURE. DESIGN |
| | LOADS SHALL BE ATTACHED TO THE CODE COMPLIANCE FORM |
| | SUBMITTED TO THE BUILDING DEPARTMENT WHEN THE BUILDING |
| | IS PERMITTED OR, IN THE EVENT THE MECHANICAL PERMIT IS |
| | OBTAINED AT A LATER TIME, THE SIZING CALCULATION SHALL |
| | BE SUBMITTED WITH THE APPLICATION FOR THE MECHANICAL |
| | PERMIT. |
| | |
| | 1C) ENERGY EFFICIENCY COMPLIANCE REPORT- SECTION C401.2 |
| | FBC EC. |
| | COMMERCIAL BUILDINGS SHALL COMPLY WITH ONE OF THE |
| | FOLLOWING:\] |
| | 1.THE REQUIREMENTS OF ANSI/ASHRAE/IESNA 90.1, EXCLUDING |
| | SECTION 9.4.1.1(G) OF THE STANDARD. |
| | 2.THE REQUIREMENTS OF SECTIONS C402 THROUGH C405. IN |
| | ADDITION, COMMERCIAL BUILDINGS SHALL COMPLY WITH |
| | SECTION C406 AND TENANT SPACES SHALL COMPLY WITH |
| | SECTION C406.1.1. |
| | 3.THE REQUIREMENTS OF SECTIONS C402.5, C403.2, C404, |
| | C405.2, C405.3, C405.5, C405.6 AND C407. THE BUILDING |
| | ENERGY COST SHALL BE EQUAL TO OR LESS THAN 85 PERCENT |
| | OF THE STANDARD REFERENCE DESIGN BUILDING. |
| | PLEASE REVIEW SECTION C101.5.1 FBC EC: THE FLORIDA |
| | BUILDING COMMISSION SHALL APPROVE SPECIFIC COMPUTER |
| | SOFTWARE. THE CODE OFFICIAL SHALL BE PERMITTED TO |
| | APPROVE WORKSHEETS, COMPLIANCE MANUALS AND OTHER |
| | SIMILAR MATERIALS THAT MEET THE INTENT OF THIS CODE. |
| | |
| | 1D) COMMISSIONING PLAN: COMMISSIONING OF THE MECHANICAL |
| | SYSTEMS AND SERVICE WATER HEATING SYSTEMS IS REQUIRED |
| | PER SECTION C408.2 FBC EC. COMMISSIONING PLAN. "PRIOR |
| | TO THE FINAL MECHANICAL AND PLUMBING INSPECTIONS, THE |
| | LICENSED DESIGN PROFESSIONAL, ELECTRICAL ENGINEER, |
| | MECHANICAL ENGINEER, OR APPROVED AGENCY SHALL PROVIDE |
| | EVIDENCE OF MECHANICAL SYSTEMS COMMISSIONING AND |
| | COMPLETION IN ACCORDANCE WITH THE PROVISIONS OF THIS |
| | SECTION". |
| | A COMMISSIONING PLAN SHALL BE DEVELOPED BY A LICENSED |
| | DESIGN PROFESSIONAL, ELECTRICAL ENGINEER, MECHANICAL |
| | ENGINEER OR APPROVED AGENCY AND SHALL INCLUDE THE |
| | FOLLOWING ITEMS: |
| | 1. A NARRATIVE DESCRIPTION OF THE ACTIVITIES THAT WILL |
| | BE ACCOMPLISHED DURING EACH PHASE OF COMMISSIONING, |
| | INCLUDING THE PERSONNEL INTENDED TO ACCOMPLISH EACH OF |
| | THE ACTIVITIES. |
| | 2. A LISTING OF THE SPECIFIC EQUIPMENT, APPLIANCES OR |
| | SYSTEMS TO BE TESTED AND A DESCRIPTION OF THE TESTS TO |
| | BE PERFORMED. |
| | 3. FUNCTIONS TO BE TESTED INCLUDING, BUT NOT LIMITED |
| | TO, CALIBRATIONS AND ECONOMIZER CONTROLS. |
| | 4. CONDITIONS UNDER WHICH THE TEST WILL BE PERFORMED. |
| | TESTING SHALL AFFIRM WINTER AND SUMMER DESIGN |
| | CONDITIONS AND FULL OUTSIDE AIR CONDITIONS. |
| | 5. MEASURABLE CRITERIA FOR PERFORMANCE' |
| | |
| | 2) SUBMITTALS: REQUIRED SUBMITTALS LISTED BELOW SHALL |
| | HAVE SHOP DRAWING STAMPS BY THE EOR AND BE IN THE FIELD |
| | AT TIME OF INSPECTION. |
| | A) SMOKE CONTROL FANS INCLUDING SMOKE EXHAUST FANS, AND |
| | STAIRWELL AND ELEVATOR PRESSURIZATION FANS. |
| | B) FIRE DAMPERS AND FIRE/SMOKE DAMPERS. |
| | C) MOTORIZED AND GRAVITY DAMPERS |
| | D) DUCT SMOKE DETECTORS |
| | E) LOUVERS FOR EXHAUST AND OUTSIDE AIR INTAKES |
| | INCLUDING MANUFACTURER'S SPECIFICATIONS AND FL. PRODUCT |
| | APPROVALS AND/OR MIAMI-DADE NOA'S |
| | F) AC STAND NOA'S OR FL. PRODUCT APPROVALS |
| | G) C0, N02, & CO2 SENSORS, AND REFRIGERANT LEAK |
| | DETECTORS. |
| | H) COOLING TOWERS AND CHILLERS |
| | I) FACTORY BUILT DUCTWORK |
| | J) DUCT FIRE WRAPPING |
| | K) CLOTHES DRYERS |
| | L) TOILET AND DRYER EXHAUST WALL CAPS |
| | M) COOKING APPLIANCES |
| | N) TEST AND BALANCE REPORTS |
| | O) SMOKE CONTROL TEST REPORTS. |
| | |
| | 2A) SUBMITTALS TO BE PROVIDED TO THE BUILDING |
| | DEPARTMENT FOR REVIEW. |
| | A) SIGNED AND SEALED STRUCTURAL ENGINEERING FOR |
| | INSTALLATION OF ALL EXTERIOR MECHANICAL EQUIPMENT AND |
| | APPLIANCES. ALL DELEGATED ENGINEERING SHALL BEAR THE |
| | SHOP DRAWING STAMP OF THE STRUCTURAL ENGINEER RECORD. |
| | B) GENERATORS AND FUEL TANKS AND ALL ASSOCIATED |
| | EQUIPMENT, VENT FLUES, AND FUEL OIL PIPING. |
| | C) BOILERS AND WATER HEATERS INCLUDING COMBUSTION AIR |
| | DUCTS AND VENT FLUES. |
| | D) COMMISSIONING REPORTS |
| | PLEASE NOTE: ALL SUBMITTALS AND SHOP DRAWINGS SHALL |
| | BEAR THE APPROVAL STAMP AND SIGNATURE OF THE DESIGN |
| | PROFESSIONAL OF RECORD. ALL REQUIRED SUBMITTALS MAY BE |
| | DEFERRED IN ACCORDANCE WITH SECTION 107.3.4.1 WPB. IT |
| | WILL BE HELPFUL TO UPLOAD A MASTER LIST OF DEFERRED |
| | SUBMITTALS IN DOCUMENT FORM, OR IN THE FORM OF NOTES ON |
| | THE MECHANICAL PLANS. |
| | DEFERRED SUBMITTALS: FOR THE PURPOSES OF THIS SECTION, |
| | DEFERRED SUBMITTALS ARE DEFINED AS THOSE PORTIONS OF |
| | THE DESIGN THAT ARE NOT SUBMITTED AT THE TIME OF THE |
| | APPLICATION AND THAT ARE TO BE SUBMITTED TO THE |
| | BUILDING OFFICIAL WITHIN A SPECIFIED PERIOD. DEFERRAL |
| | OF ANY SUBMITTAL ITEMS SHALL HAVE THE PRIOR APPROVAL OF |
| | THE BUILDING OFFICIAL. THE REGISTERED DESIGN |
| | PROFESSIONAL IN RESPONSIBLE CHARGE SHALL LIST THE |
| | DEFERRED SUBMITTALS ON THE CONSTRUCTION DOCUMENTS FOR |
| | REVIEW BY THE BUILDING OFFICIAL. |
| | DOCUMENTS FOR DEFERRED SUBMITTAL ITEMS SHALL BE |
| | SUBMITTED TO THE REGISTERED DESIGN PROFESSIONAL IN |
| | RESPONSIBLE CHARGE WHO SHALL REVIEW THEM AND FORWARD |
| | THEM TO THE BUILDING OFFICIAL WITH A NOTATION |
| | INDICATING THAT THE DEFERRED SUBMITTAL DOCUMENTS HAVE |
| | BEEN REVIEWED AND FOUND TO BE IN GENERAL CONFORMANCE TO |
| | THE DESIGN OF THE BUILDING. |
| | |
| | 3) SEPARATE PERMITS: SEPARATE PERMITS ARE REQUIRED FOR |
| | COMMERCIAL KITCHEN EXHAUST HOODS, FIRE SUPPRESSION |
| | SYSTEMS, AND WALK-IN COOLERS AND FREEZERS. PLEASE PLACE |
| | NOTES ON THE MAIN BUILDING PLANS ACCORDINGLY AND |
| | PROVIDE THE FOLLOWING INFORMATION FOR THE KITCHEN |
| | HOODS. |
| | A) LOCATIONS OF HOODS, EXHAUST AND MAKEUP AIR FANS AND |
| | DUCTWORK, EXHAUST AND MAKEUP AIR OUTLETS AND INLETS, |
| | MUA UNITS IF PROVIDED. |
| | B) AIR BALANCE CALCULATIONS. |
| | C) ADVISORY: REFER TO SECTION 508.1.1 FBC M. MAKEUP AIR |
| | TEMPERATURE: THE TEMPERATURE DIFFERENTIAL BETWEEN |
| | MAKEUP AIR AND THE AIR IN THE CONDITIONED SPACE SHALL |
| | NOT EXCEED 10 DEGREES F (6 DEGREES C) EXCEPT WHERE THE |
| | ADDED HEATING AND COOLING LOADS OF THE MAKEUP AIR DO |
| | NOT EXCEED THE CAPACITY OF THE HVAC SYSTEM. |
| | |
| | 4) PROVIDE VENTILATION CALCULATIONS AND A SCHEDULE THAT |
| | INDICATES THE REQUIRED AND PROVIDED OUTDOOR AND EXHAUST |
| | AIRFLOW RATES. THE O/A CFMS LISTED IN THE 100% O/A-ERU |
| | AND AHU EQUIPMENT SCHEDULES SHALL CORRELATE WITH THE |
| | CALCULATIONS. PLEASE ALSO PROVIDE AIR BALANCE |
| | CALCULATIONS ? TABLE 403.3.1.1 FBC M & SECTION C403.2.7 |
| | FBC EC. |
| | 5) PROVIDE CALCULATIONS FOR THE POST FIRE SMOKE PURGE |
| | SYSTEM AND FANS- SEE SECTION 403.4.7 FBC B. |
| | 6) PARKING GARAGE EXHAUST- PODIUM LEVELS 1- 6 (SHEETS |
| | M201, 202, 203, 204, 205, 206) PROVIDE CALCULATIONS- |
| | TABLE 403.3.1.1 AND SECTION 404.1 FBC M. A) INDICATE |
| | THE SEQUENCE OF OPERATION FOR THE EXHAUST SYSTEM- |
| | SECTION 404.2 FBC M. ADVISORY: PLEASE PROVIDE NOTES AND |
| | DETAILS ON THE PLANS THAT ARE CONSISTENT WITH THE |
| | SEQUENCING NOTES ON SHEET M.813. B) SUBMIT |
| | MANUFACTURER'S SPECIFICATIONS FOR THE CO AND NO2 |
| | SENSORS (MAY BE DEFERRED PER COMMENT #2). C) REFER TO |
| | SECTION C403.2.6.2 FBC EC FOR ENERGY COMPLIANCE |
| | REQUIREMENTS. |
| | |
| | PODIUM |
| | 7) SHEETS M.201-M.208 A, B, C, & D QUADRANTS: DUCT |
| | SMOKE DETECTORS ARE REQUIRED IN THE SUPPLY SYSTEMS OF |
| | THE AHU'S PER SECTION 606.2.1 FBC M. PLEASE PROVIDE DS |
| | SYMBOLS ON THE PLANS AND RISER DRAWINGS TO SHOW THE |
| | LOCATIONS. |
| | 8) M.201-M.208 A, B, C, & D QUADRANTS: DUCT SMOKE |
| | DETECTORS ARE REQUIRED IN THE SUPPLY SYSTEMS OF THE |
| | 100% O/A ERU SYSTEMS, AND AT EACH STORY OF THE RA/EA |
| | RISER- SECTION 606.2.3. PLEASE PROVIDE DS SYMBOLS ON |
| | THE PLANS AND RISER DRAWINGS TO SHOW THE LOCATIONS. |
| | 9) M.201-M.208 A, B, C, & D QUADRANTS: SHOW CLEARANCE |
| | DISTANCE MEASUREMENTS FOR O/A INTAKES AND EXHAUST |
| | OUTLETS IN COMPLIANCE WITH SECTIONS 401.4 AND 501.3.1 |
| | FBC M OR PROVIDE GENERAL KEYNOTES. |
| | 10) M.201-M.208 A, B, C, & D QUADRANTS: REFER TO |
| | SECTION 306.1 AND VERIFY ACCESS IS PROVIDED FOR AC AND |
| | FAN UNITS LOCATED ABOVE HARD CEILING. SHOW AN ACCESS |
| | PANEL WITH DIMENSIONS ON THE DRAWINGS WHERE REQUIRED- |
| | SECTION 306.1 FBC M.1 |
| | 11) M.201-M.208 A, B, C, & D QUADRANTS: PLACE NOTES TO |
| | INDICATE LOCATIONS OF ABOVE CEILING PLENUMS AND NO |
| | COMBUSTIBLE MATERIALS PERMITTED. |
| | 12) SHEETS M.201-M.208 A, B, C, & D QUADRANTS: BRANCH |
| | AND FLEX DUCT SIZES NOT SHOWN- SECTION 603.1 FBC M. |
| | 13) M.201- M.208 A, B, C, D QUADRANTS WHERE APPLICABLE: |
| | FIRE DAMPERS MISSING FOR THE O/A BRANCH DUCTS |
| | PENETRATING THE FIRE-RATED CORRIDOR/SUITE, AND |
| | CORRIDOR/RESIDENTIAL UNIT WALLS- SECTION 607.5.3 FBC M. |
| | 14) M.201- M.208 A, B, C, D QUADRANTS WHERE APPLICABLE: |
| | PLACE NOTES TO INDICATE NO COMBUSTIBLE MATERIALS |
| | PERMITTED IN THE VHP CLOSETS INCLUDING THE DOORS- |
| | SECTION 602.2.1 FBC M. IT APPEARS THE DOORS WILL BE |
| | LOUVERED TO ALLOW RETURN AIR TO THE HEAT PUMPS, |
| | OTHERWISE INDICATE MEANS OF RETURN AIR- SECTION 601.6 |
| | FBC M. |
| | 15) M.201- M.208 A, B, C, D: AUTOMATICALLY OPERATING |
| | SHUTOFF DAMPERS ARE REQUIRED FOR THE O/A DUCTS SERVING |
| | THE SUITES AND THE UNITS- SECTION C403.2.4.3 FBC EC. |
| | 16) M.201A: AN AUTOMATIC SHUTOFF DAMPER IS REQUIRED FOR |
| | THE O/A SUPPLY TO AHU-5- SECTION C403.2.4.3 FBC EC |
| | 17) SHEET ALS1.101 & M.201B: FIRE DAMPERS MISSING FOR |
| | TOILET EXHAUST DUCT PENETRATING OFFICE/LOBBY & |
| | VALET/LOBBY WALLS, & 48X20 EXHAUST DUCT PENETRATING |
| | MENS WC/VALET WALL- SECTION 607.5.2 FBC M. |
| | 18) M.201B: IDENTIFY THE AC SYSTEM CONNECTED TO THE |
| | SUPPLY AND RETURN DROPS IN THE OFFICE/LOBBY ROOM- |
| | PROVIDE A NOTE ON THE PLAN- SECTION 107.2.1 WPB. A) |
| | IDENTIFY WITH A NOTE THE SYSTEM CONNECTED TO THE 40X20 |
| | RETURN DUCT- SECTION 107.2.1 WPB. B) FIRE DAMPERS |
| | MISSING FOR THE 48X20 EXHAUST DUCT PENETRATING |
| | FIRE-RATED WALLS AT THE FIRE LOBBY, RECEIVING ROOM, AND |
| | MENS WC. C) FIRE DAMPER MISSING FOR THE 6X6 SUPPLY |
| | PENETRATING FIRE-RATED WALL AT THE FIRE LOBBY. |
| | 19) M.201C: LABEL THE SYSTEM CONNECTED TO THE 60X24 |
| | DROPS IN THE SCREENING ROOM- SECTION 107.2.1 WPB. |
| | 20) ALS1.101 & M.201C: THERE ARE NUMEROUS FIRE DAMPERS |
| | MISSING FOR SUPPLY, RETURN, AND EXHAUST DUCTS RUNNING |
| | THROUGH THE FIRE-RATED WALLS AT THE TRASH ROOM, OFFICE, |
| | RESIDENT?S LOUNGE, ETC.- SECTION 607.5.2 FBC M. MANY OF |
| | THESE ARE BRANCHING OFF THE TWO MAIN 60X24 DUCTS. |
| | 21) M.201C: SHOW THE LOCATION OF MAU-01. |
| | 22) M.201C: SUBMIT MANUFACTURER'S SPECIFICATIONS AND UL |
| | CERTIFICATE FOR THE 2000-GALLON FUEL TANK. |
| | 23) M.201C: VENTILATION IS REQUIRED FOR THE FUEL TANK |
| | ROOM AND IT CANNOT BE ACHIEVED NATURALLY BECAUSE OF THE |
| | ROOM LOCATION. REFER TO SECTION 24.10.2 NFPA 30 AND |
| | PROVIDE A MECHANICAL VENTILATION SYSTEM THAT INCLUDES |
| | CALCULATIONS AND SPECIFICATIONS FOR EXHAUST AND MAKEUP |
| | AIR. A) PROVIDE DETAILS AND SPECIFICATIONS FOR NORM AND |
| | EMERGENCY RELIEF VENTING OF THE TANK, INCLUDING VENT |
| | PIPING RUNS AND TERMINATION LOCATIONS AT THE EXTERIOR |
| | OF THE BUILDING- SECTION 24.13 NFPA 30. |
| | 24) THE EXHAUST SYSTEM FOR THE FIRE PUMP ROOM IS |
| | INCOMPLETE- PLEASE PROVIDE THE TYPE AND SIZE OF EXHAUST |
| | DUCT, LOCATION OF EXHAUST FAN, FAN EQUIPMENT SCHEDULE, |
| | EXHAUST CALCULATIONS AND SEQUENCE OF OPERATION, AND |
| | SOURCE OF MAKEUP AIR. |
| | 25) M.201D: FIRE DAMPERS MISSING FOR THE DUCTS |
| | PENETRATING THE FIRE-RATED WALLS AT THE SERVICE |
| | CORRIDOR AND AHU LOBBY ROOM- SECTION 607.5.2 FBC M. |
| | 26) M202B: THE EXHAUST FROM EF-A01 & EF-A02 SHALL |
| | DISCHARGE TO THE OUTDOORS AND NOT INTO THE ENCLOSED |
| | GARAGE- SECTION 501.3 FBC M. |
| | 27) M.202B: DUCTWORK IN THE OPEN AREA IS INCOMPLETE- NO |
| | DUCT SIZES, AIRFLOWS, SYSTEM IDENTIFICATION ETC.- |
| | SECTION 107.2.1 WPB. |
| | 28) M.202B: PROVIDE NOTES AT AHU-03 TO INDICATE WHICH |
| | AREA IS BEING CONDITIONED BY THE SYSTEM, AND HOW O/A IS |
| | BEING PROVIDED AND AUTOMATICALLY CONTROLLED- SECTION |
| | C404.2.4.3 FBC EC. |
| | 29) M.202B: FIRE DAMPER MISSING FOR THE 8X8 SUPPLY DUCT |
| | PENETRATING FIRE-RATED WALL AT THE FIRE LOBBY. |
| | 30) M.202C: PROVIDE A TERMINATION CAP FOR THE PFP SMOKE |
| | PURGE DUCT, AND INDICATE MINIMUM 10' CLEARANCE TO THE |
| | O/A INTAKES LOCATED IN PROXIMITY OF THE OUTLET- SECTION |
| | 501.3.1 FBC M. |
| | 31) M.202C: AUTOMATIC SHUTOFF DAMPERS ARE REQUIRED FOR |
| | THE O/A SUPPLY DUCTS TO AHU-5 AND SPF-01- SECTION |
| | C403.2.4.3 FBC EC. |
| | 32) M.202C: IDENTIFY THE SOURCE OF THE O/A DUCT TRUCK |
| | SUPPLYING THE VERTICAL HEAT PUMPS (VHP) IN THE UNITS |
| | AND PROVIDE AUTOMATIC SHUTOFF DAMPERS AT EACH SUPPLY- |
| | SECTION 107.2.1 WPB AND SECTION C403.2.4.3 FBC EC. |
| | 33) M.202C: THE 22X22 SPF-01 INTAKE DUCT SHALL BE |
| | COMPLETELY ENCLOSED IN A FIRE-RATED HORIZONTAL ASSEMBLY |
| | AS REQUIRED BY SECTION 909.20.6.1 FBC B. SUBMIT |
| | MANUFACTURER?S SPECIFICATIONS FOR THE 2-HR FIRE |
| | WRAPPING (MAY BE DEFERRED SUBMITTAL). A FIRE/SMOKE |
| | DAMPER IS REQUIRED AT SG-3 PENETRATION INTO STAIR-1 - |
| | SECTION 1023.5 FBC B. |
| | 34) M.202D: PROVIDE NOTES AT AHU-04 TO INDICATE WHICH |
| | AREA IS BEING CONDITIONED BY THE SYSTEM, AND HOW O/A IS |
| | BEING PROVIDED AND AUTOMATICALLY CONTROLLED- SECTION |
| | C404.2.4.3 FBC EC. |
| | 35) M.202D: FIRE DAMPERS MISSING FOR THE O/A BRANCH |
| | DUCTS PENETRATING THE FIRE-RATED CORRIDOR WALLS. |
| | 36) M.203B: IDENTIFY THE SOURCE OF THE O/A DUCT TRUCK |
| | SUPPLYING THE FAN COIL UNITS (FCU) IN THE UNITS AND |
| | PROVIDE AUTOMATIC SHUTOFF DAMPERS FOR THE SUPPLY AT |
| | EACH UNIT- SECTION 107.2.1 WPB AND SECTION C403.2.4.3 |
| | FBC EC. |
| | 37) M.203B: INDICATE WHAT AIR IS BEING RETURNED VIA THE |
| | 54X24 RA DUCT IN THE SHAFT. THE PLAN SHOWS NO DUCTS |
| | CONNECTING TO IT. |
| | 38) M.203B: FIRE DAMPER MISSING FOR THE 6X6 SUPPLY DUCT |
| | PENETRATING FIRE-RATED WALL AT THE FIRE LOBBY. |
| | 39) M.203C: THE SPF-03 INTAKE DUCT SHALL BE COMPLETELY |
| | ENCLOSED IN A FIRE-RATED HORIZONTAL ASSEMBLY AS |
| | REQUIRED BY SECTION 909.20.6.1 FBC B. A FIRE/SMOKE |
| | DAMPER IS REQUIRED AT SG-2 PENETRATION INTO STAIR-2 - |
| | SECTION 1023.5 FBC B. |
| | 40) M.203C & D: IDENTIFY THE SOURCE OF THE O/A DUCT |
| | TRUCK SUPPLYING THE VERTICAL HEAT PUMPS (VHP) IN THE |
| | UNITS AND PROVIDE AUTOMATIC SHUTOFF DAMPERS FOR THE |
| | SUPPLY AT EACH UNIT- SECTION 107.2.1 WPB AND SECTION |
| | C403.2.4.3 FBC EC. |
| | 41) M.203C & D: FIRE DAMPERS MISSING FOR THE O/A BRANCH |
| | DUCTS PENETRATING THE FIRE-RATED CORRIDOR WALLS- |
| | SECTION 607.5.3 FBC M. |
| | 42) M.203C & D: PLACE NOTES TO INDICATE NO COMBUSTIBLE |
| | MATERIALS PERMITTED IN THE VHP CLOSETS INCLUDING THE |
| | DOORS- SECTION 602.2.1 FBC M. IT APPEARS THE DOORS WILL |
| | BE LOUVERED TO ALLOW RETURN AIR TO THE HEAT PUMPS., |
| | OTHERWISE INDICATE MEANS OF RETURN AIR- SECTION 601.6 |
| | FBC M. |
| | 43) M.204B: FIRE DAMPERS MISSING FOR THE O/A BRANCH |
| | DUCTS PENETRATING THE FIRE-RATED CORRIDOR/SUITE WALLS- |
| | SECTION 607.5.3 FBC M. |
| | 44) M.204B: INDICATE WHAT AIR IS BEING RETURNED VIA THE |
| | 54X24 RA DUCT IN THE SHAFT. THE PLAN SHOWS NO DUCTS |
| | CONNECTING TO IT. |
| | 45) M.204B: FIRE DAMPER MISSING FOR THE 6X6 SUPPLY DUCT |
| | PENETRATING FIRE-RATED WALL AT THE FIRE LOBBY. |
| | 46) M.204C & D: IDENTIFY THE SOURCE OF THE O/A DUCT |
| | TRUCK SUPPLYING THE VERTICAL HEAT PUMPS (VHP) IN THE |
| | UNITS AND PROVIDE AUTOMATIC SHUTOFF DAMPERS FOR THE |
| | SUPPLY AT EACH UNIT- SECTION 107.2.1 WPB AND SECTION |
| | C403.2.4.3 FBC EC. |
| | 47) M.204C & D: FIRE DAMPERS MISSING FOR THE O/A BRANCH |
| | DUCTS PENETRATING THE FIRE-RATED CORRIDOR WALLS- |
| | SECTION 607.5.3 FBC M. |
| | 48) M.205B: SHOW THE O/A AND EXHAUST DUCT RUNS AND |
| | INLET AND OUTLET LOCATIONS FOR ERU-01- SECTION 107.2.1 |
| | WPB AND SECTIONS 401.4 & 501.3.1 FBC M. |
| | 49) M.205B: FIRE DAMPER MISSING FOR THE 6X6 SUPPLY DUCT |
| | PENETRATING FIRE-RATED WALL AT THE FIRE LOBBY. |
| | 50) M.205C: SHOW THE O/A AND EXHAUST DUCT RUNS AND |
| | INLET AND OUTLET LOCATIONS FOR ERU-02- SECTION 107.2.1 |
| | WPB AND SECTIONS 401.4 & 501.3.1 FBC M. |
| | 51) M.205C & D: FIRE DAMPERS MISSING FOR THE O/A BRANCH |
| | DUCTS PENETRATING THE FIRE-RATED CORRIDOR WALLS- |
| | SECTION 607.5.3 FBC M. |
| | 52) M.205C & D: IDENTIFY THE SOURCE OF THE O/A DUCT |
| | TRUCK SUPPLYING THE VERTICAL HEAT PUMPS (VHP) IN THE |
| | UNITS AND PROVIDE AUTOMATIC SHUTOFF DAMPERS FOR THE |
| | SUPPLY AT EACH UNIT- SECTION 107.2.1 WPB AND SECTION |
| | C403.2.4.3 FBC EC. |
| | 53) M.206A: PROVIDE AN ENLARGED DRAWING OF THE EPSS |
| | (EMERGENCY GENERATOR) ROOM SHOWING THE LOCATIONS OF THE |
| | GENERATOR AND FUEL TANK, FUEL OIL PIPE AND EXHAUST PIPE |
| | RUNS AND TERMINATION LOCATIONS, AND ALL OTHER |
| | ASSOCIATED EQUIPMENT INCLUDING EMERGENCY ELECTRICAL |
| | PANELS ETC. PLEASE INCLUDE THE REQUIRED CLEARANCE |
| | DISTANCE MEASUREMENTS FOR ALL EQUIPMENT VENT PIPING |
| | RUNS AND SPECIFICATIONS INCLUDING FILL PIPING |
| | LOCATIONS. |
| | A) SUBMIT MANUFACTURER'S SPECIFICATIONS FOR THE |
| | GENERATOR AND THE 190-GALLON FUEL TANK, FUEL PIPING, |
| | ENGINE EXHAUST PIPE, MUFFLER, AND ALL OTHER ASSOCIATED |
| | SYSTEM COMPONENTS- SECTION 304.1 FBC M |
| | B) SUBMIT THE UL 2200 CERTIFICATE OF COMPLIANCE FOR THE |
| | GENERATOR- SECTION 915.1 FBC M. |
| | C) THE MANUFACTURER'S SPECIFICATIONS AND/OR UL |
| | CERTIFICATE SHALL INDICATE THE GENERATOR IS COMPLIANT |
| | WITH THE NFPA 37 AND NFPA 110 STANDARDS |
| | D) SUBMIT A CUT SHEET FOR THE FUEL TANK THAT INCLUDES |
| | THE TANK'S UL LISTING- UL 142 OR UL 2085- SEE SECTION |
| | 21.4.2.1.1 NFPA 30. |
| | E) REFER TO 4.1 NFPA 110 AND INDICATE THE |
| | CLASSIFICATION AND LEVEL OF THE EPSS SYSTEM. PLEASE |
| | INCLUDE THIS INFORMATION IN THE SMOKE CONTROL RATIONAL |
| | ANALYSIS. |
| | F) SUBMIT THE GENERATOR EXHAUST PIPE SPECIFICATIONS AND |
| | PROVIDE AN EXHAUST PIPE DIAGRAM SHOWING THE TOTAL |
| | SYSTEM RUN AND LENGTH MEASUREMENT, AND TERMINATION |
| | LOCATION PLEASE INCLUDE ALL COMPONENTS OF THE SYSTEM |
| | INCLUDING THE SILENCER, AND ANY CONTRACTOR SUPPLIED |
| | PIPING- SEE SECTION 8.1 ? 8.4 NFPA 37, AND SECTION |
| | 501.3.1 FBC M. |
| | G) PROVIDE BACKPRESSURE CALCULATIONS FOR THE GENERATOR |
| | EXHAUST PIPE RUN- SECTION 304.1 FBC M. |
| | H) REFER TO SECTIONS 7.7.2,1 &, 7.7.2.3 & 7.7.3 NFPA |
| | 110: PER THE ENGINEER'S PLAN AND NARRATIVE, THE |
| | VENTILATION AIR FOR THE GENERATOR ROOM IS BEING DRAWN |
| | IN THROUGH A LOUVERED OPENING IN THE 2HR. FIRE-RATED |
| | WALL GENERATOR ROOM WALL THAT ADJACENT TO THE PARKING |
| | GARAGE WHICH IS NOT PERMITTED PER SECTION 7.7.2.1 & |
| | 7.7.2.3. THESE SECTIONS STATE THAT VENTILATION AIR MUST |
| | BE SUPPLIED DIRECTLY FROM A SOURCE OUTSIDE THE |
| | BUILDING. SECTION 7.7.2.3 PROHIBITS THE USE OF A FIRE |
| | DAMPER TO PROTECT THE OPENING, THEREFORE THE |
| | VENTILATION OPENING LOCATION WOULD NOT BE COMPLIANT |
| | BECAUSE OPENINGS IN FIRE BARRIERS REQUIRE PROTECTION |
| | ACCORDING TO SECTION 607.5.2 FBC M. INDICATE HOW |
| | VENTILATION WILL BE PROVIDED FOR THE GENERATOR/FUEL |
| | TANK ROOM. |
| | J) PROVIDE DETAILS AND SPECIFICATIONS FOR NORM AND |
| | EMERGENCY RELIEF VENTING OF THE TANK, INCLUDING VENT |
| | PIPING RUNS AND TERMINATION LOCATIONS AT THE EXTERIOR |
| | OF THE BUILDING- SECTION 24.13 NFPA 30. |
| | K) M-401: REFER TO SECTION 7.7.1 NFPA 110- 2016 AND |
| | VERIFY THAT THE VENTILATION AIRFLOW IN THE |
| | GENERATOR/TANK (EPS) ROOM IS DESIGNED TO LIMIT THE |
| | MAXIMUM AIR TEMPERATURE IN THE ROOM TO THE MAXIMUM |
| | AMBIENT AIR TEMPERATURE REQUIRED BY THE GENERATOR |
| | MANUFACTURER. CONSIDERATION SHALL BE GIVEN TO ALL THE |
| | HEAT EMITTED TO THE ROOM BY THE ENERGY CONVERTER, |
| | EXHAUST PIPES, AND ALL OTHER HEAT PRODUCING EQUIPMENT- |
| | SECTION 7.7.1.1. DESIGN OF THE HEATING, COOLING, AND |
| | VENTILATION SYSTEM SHALL AMONG OTHER THINGS, INCLUDE |
| | PROVISIONS FOR FACTORS SUCH AS HEAT, COLD, HUMIDITY, |
| | LOUVERS, ETC.- SECTION 7.7.7. 57) M.205A, B, C, & D: |
| | SHOW CLEARANCE DISTANCE MEASUREMENTS FOR O/A INTAKES |
| | AND EXHAUST OUTLETS IN COMPLIANCE WITH SECTIONS 401.4 |
| | AND 501.3.1 FBC M OR PROVIDE GENERAL KEYNOTES. |
| | 54) M.206A & B: INDICATE WHAT APPLIANCES ARE CONNECTED |
| | TO THE INTAKE VENT AND EXHAUST FLUE PIPES AT THE H. |
| | AMENITIES ROOM. SHOW THE APPLIANCES IN THE ROOM, |
| | PROVIDE EQUIPMENT SCHEDULES ON THE PLAN AND SUBMIT |
| | MANUFACTURER?S SPECIFICATIONS- SECTIONS 503.1 AND 624.1 |
| | FG. ASSUMING THESE APPLIANCES ARE GAS-FIRED PLEASE |
| | PROVIDE THE GAS PIPING REQUIREMENTS TO THE MAIN GAS |
| | PLAN- SECTION 402.1 FBC FG. |
| | 55) M.206B: FIRE DAMPERS MISSING FOR THE O/A BRANCH |
| | DUCTS PENETRATING THE FIRE-RATED CORRIDOR/SUITE WALLS- |
| | SECTION 607.5.3 FBC M. |
| | 56) M.206B: THE 16X6 O/A DUCT SHALL NOT PENETRATE AND |
| | RUN THROUGH THE INTERIOR EXIT STAIRWAY- 1023.5 FBC B. |
| | 57) M.206B: THE ERU EXHAUST SHALL TERMINATE OUTDOORS OF |
| | THE BUILDING. IT APPEARS TO BE EXHAUSTING INTO AN |
| | INTERSTITIAL SPACE- SECTION 501.3 FBC M. |
| | 58) M.206C: FIRE DAMPERS MISSING FOR THE O/A BRANCH |
| | DUCTS PENETRATING THE FIRE-RATED CORRIDOR WALLS- |
| | SECTION 607.5.3 FBC M. |
| | 59) M.206C: DUCT DROPS TO ERU-02 ARE MISLABELED AS |
| | DROPS TO AHU-02- SECTION 107.2.1 FBC M. |
| | 60) M.206C: IN-LINE EXHAUST FANS ARE SHOWN ON EXHAUST |
| | DUCTS THAT ARE SPECIFIED TO HAVE FIRE WRAPPING WHICH IS |
| | NOT IN COMPLIANCE WITH EITHER THE FAN OR THE DUCT WRAP |
| | LISTING AND INSTALLATION INSTRUCTIONS- SECTION 304.1 |
| | FBC M. |
| | 61) M.206C: THE SPF-13 INTAKE DUCT SHALL BE COMPLETELY |
| | ENCLOSED IN A FIRE-RATED HORIZONTAL ASSEMBLY AS |
| | REQUIRED BY SECTION 909.20.6.1 FBC B. A FIRE/SMOKE |
| | DAMPER IS REQUIRED AT SG-3 PENETRATION INTO STAIR-12 - |
| | SECTION 1023.5 FBC B. |
| | 62) M.207A: FIRE DAMPERS MISSING FOR SUPPLY AND RETURN |
| | DUCTS FROM AHU-08 & AHU-09 PENETRATING FIRE-RATED WALLS |
| | AT POOL EQUIP, POOL DECK, FITNESS STUDIO, AND MENS WC |
| | WALLS- SECTION 607.5.2 FBC M. |
| | 63) M.207A: FIRE DAMPERS MISSING FOR SUPPLY AND RETURN |
| | DUCTS FROM AHU-08 & AHU-09 PENETRATING FIRE-RATED WALLS |
| | AT MENS WC AND PREFUNCTION- SECTION 607.5.2 FBC M. A) |
| | INDICATE THE DIMENSIONS OF THE AHU-09 SUPPLY DUCT. |
| | 64) M.207A: THE EXHAUST DUCT FROM MENS WC AND WOMENS WC |
| | SHALL DISCHARGE TO THE OUTDOORS- SECTION 501.3 FBC M. |
| | 65) M.207A: AUTOMATIC DAMPERS ARE REQUIRED FOR THE O/A |
| | INTAKES AT AHU-08 & 09- SECTION C403.2.4.3 FBC EC. |
| | 66) M.207A: PROVIDE EXHAUST VENTILATION CALCULATIONS |
| | FOR EF-A07 & EF-A09. IT APPEARS ONE OF FANS IS |
| | CONNECTED TO THE RA DUCT AT AHU-09. |
| | 67) M.207A: IT APPEARS THE PRESSURIZATION DUCTS FROM |
| | SPF-07, 10, & 15 ARE ENCLOSED IN FIRE WRAPPING. PLEASE |
| | CLARIFY BY PLACING A NOTE ON THE PLAN- SECTION |
| | 909.20.6.1 FBC B. |
| | 68) M.207A: SUBMIT MANUFACTURER'S SPECIFICATIONS FOR |
| | THE 3-HR FIRE WRAP ENCLOSING THE GENERATOR EXHAUST |
| | DUCT. TERMINATE DUCT AT THE EXTERIOR WITH AN ENDCAP. |
| | 69) M.207A: PROVIDE AN ENLARGED DRAWING OF THE LAUNDRY |
| | ROOM THAT SHOWS THE LOCATION OF ALL EQUIPMENT, AND THE |
| | EXHAUST AND MAKEUP AIR SYSTEM DETAILS AND |
| | SPECIFICATIONS. SUBMIT MANUFACTURER'S SPECIFICATIONS |
| | FOR THE DRYERS PER SECTION- 504.1 FBC M. |
| | 70) M.207A: INDICATE THE TYPE OF DUCTWORK TO BE USED IN |
| | THE LAP POOL ROOM- SECTION 603 FBC M. |
| | 71) M.207A: PROVIDE EXHAUST VENTILATION CALCULATIONS |
| | FOR THE POOL ROOM AND SHOW HOW MAKEUP AIR IS BEING |
| | PROVIDED- SECTION 501.4 FBC M. CLARIFY IF THE POOL |
| | EQUIPMENT IS TO BE INSTALLED UNDER SEPARATE PERMIT- |
| | PLACE A NOTE ON THE PLANS. |
| | 72) M.207B: VERIFY THE EXHAUST AIR LOUVER FOR THE |
| | FUTURE KITCHEN IS IN COMPLIANCE WITH SECTION 506.3.13.2 |
| | AND 506.3.13.3 FBC M. REFER TO COMMENT #3 FOR MORE |
| | INFORMATION. |
| | 73) M.207B: FIRE DAMPERS MISSING FOR THE O/A BRANCH |
| | DUCTS PENETRATING THE FIRE-RATED CORRIDOR WALLS- |
| | SECTION 607.5.3 FBC M. |
| | 74) M.207B: FIRE/SMOKE DAMPERS REQUIRED AT SG-3 |
| | PRESSURIZATION INLETS AT STAIR-4 AND STAIR-8. |
| | 75) M.207C: FIRE DAMPERS REQUIRED FOR THE AHU-09 SUPPLY |
| | DUCT AND 36X30 TRANSFER DUCT PENETRATING THE FITNESS |
| | AND SPA FIRE-RATED WALLS, AND THE 10' DUCT PENETRATING |
| | THE SPA/FITNESS OFFICE WALL- SECTION 607.5.2 FBC M. |
| | FIRE WRAPPING OF THE DUCT IN JUST THESE SECTIONS OF THE |
| | DUCT MUST BE VERIFIED TO BE CONSISTENT WITH THE |
| | MANUFACTURER'S LISTING AND INSTALLATION INSTRUCTIONS- |
| | SECTION 304.1 FBC M. |
| | 76) M.207C: NO DIFFUSER IS SHOWN AT THE END OF THE |
| | 16X14 SUPPLY DUCT AT THE SPA- SECTION 603. |
| | 77) M.207C: FIRE DAMPERS MISSING FOR THE LOCKER ROOM |
| | EXHAUST DUCTS PENETRATING THE FIRE-RATED LOCKER ROOM |
| | WALLS- SECTION 607.5.3 FBC M. |
| | 79) M.207C: FIRE DAMPERS MISSING FOR THE LOCKER ROOM |
| | SUPPLY AND RETURN DUCTS PENETRATING THE FIRE-RATED |
| | LOCKER ROOM WALLS- SECTION 607.5.2 FBC M. |
| | 80) M.207C: IT APPEARS NO O/A HAS BEEN PROVIDED FOR |
| | UNITS A6, B1, AND S6- TABLE 403.3.1.1. FBC M. |
| | 81) M.207D: FIRE DAMPERS MISSING AT THE DUCTS |
| | PENETRATING THE CORRIDOR/WOMENSWC/MENSWC FIRE RATED |
| | WALLS- SECTION 607.5.2 FBC M. |
| | 82) M.208A: LABEL THE PRESSURIZATION FAN SHOWN AT THE |
| | UNIDENTIFIED INTERIOR EXIT STAIRWAY THE INTAKE DUCT |
| | SHALL BE COMPLETELY ENCLOSED IN A FIRE-RATED HORIZONTAL |
| | ASSEMBLY AS REQUIRED BY SECTION 909.20.6.1 FBC B. A |
| | FIRE/SMOKE DAMPER IS REQUIRED AT THE DIFFUSER |
| | PENETRATION INTO THE STAIRWAY- SECTION 1023.5 FBC |
| | 83) M.208A: FIRE DAMPERS AND O/A DAMPER MISSING AT THE |
| | 28X28 INTAKE DUCT PENETRATING INTO THE STORAGE ROOM |
| | 84) M.208A: FIRE DAMPERS MISSING FOR THE TENNIS COURTS |
| | SUPPLY AND RETURN DUCTS PENETRATING INTO THE STORAGE |
| | ROOM. |
| | 85) M.208AAC SYSTEM FOR THE TENNIS COURTS IN THE |
| | STORAGE ROOM NOT IDENTIFIED. |
| | 86) M.208C: IT APPEARS NO O/A HAS BEEN PROVIDED FOR |
| | UNITS B1, B2, B3, & A4- TABLE 403.3.1.1. FBC M. |
| | 87) M.208C: FIRE DAMPERS MISSING FOR THE 18X14 SUPPLY |
| | AND RETURN DUCTS PENETRATING THROUGH THE FIRE-RATED |
| | CORRIDOR WALL- SECTION 607.5.3 FBC M. |
| | 88) M.208D: FIRE DAMPERS MISSING FOR THE BRANCH DUCT |
| | PENETRATING THE FIRE LOBBY WALL, AND ALL OTHER BRANCH |
| | DUCTS PENETRATING FIRE-RATED CORRIDOR WALLS- SECTION |
| | 607.5.2 & 607.5.3 FBC M. |
| | |
| | HOTEL TOWER |
| | 89) SHEETS M.209, M.211, & M.212: DUCT SMOKE DETECTORS |
| | ARE REQUIRED IN THE SUPPLY SYSTEMS OF THE AHU'S PER |
| | SECTION 606.2.1 FBC M. PLEASE PROVIDE DS SYMBOLS ON THE |
| | PLANS AND RISER DRAWINGS TO SHOW THE LOCATIONS. |
| | 91) M.209, M.211, M.212: DUCT SMOKE DETECTORS ARE |
| | REQUIRED IN THE SUPPLY SYSTEMS OF THE 100% O/A ERU |
| | SYSTEMS, AND AT EACH STORY OF THE RA/EA RISER- SECTION |
| | 606.2.3. PLEASE PROVIDE DS SYMBOLS ON THE PLANS AND |
| | RISER DRAWINGS TO SHOW THE LOCATIONS. |
| | 92) M.209, M.211, M.212: PROVIDE A FIRE-RATED ENCLOSURE |
| | AND ACCESS PANEL FOR THE DEF'S AND SUBMIT SPECS FOR THE |
| | FAN AND THE EXHAUST DUCT FIRE WRAPPING- SECTIONS 304.1 |
| | & 306.1. A) REFER TO SECTION 504.1 AND SUBMIT |
| | MANUFACTURER'S SPECIFICATIONS FOR THE CLOTHES DRYERS. |
| | PROVIDE ON THE PLANS DRYER EXHAUST DUCT DIAGRAMS THAT |
| | SHOW THE TOTAL RUN LENGTHS OF THE SYSTEMS CONSISTENT |
| | WITH THE MANUFACTURER'S GUIDELINES. B) REFER TO SECTION |
| | 504.9 AND PROVIDE A SEQUENCE OF OPERATION FOR THE |
| | DEF?S. |
| | 93) M.209, M.211, M.212: FIRE DAMPERS MISSING FOR THE |
| | O/A BRANCH DUCTS AND TOILET EXHAUST DUCTS PENETRATING |
| | THE FIRE-RATED CORRIDOR/SUITE WALLS- SECTION 607.5.3 |
| | FBC M. |
| | 94) M.209, M.211, M.212: SHOW CLEARANCE DISTANCE |
| | MEASUREMENTS FOR THE EXHAUST OUTLETS IN COMPLIANCE WITH |
| | SECTIONS 501.3.1 FBC M OR PROVIDE GENERAL KEYNOTES. |
| | 95) M.209, M.211, M.212: REFER TO SECTION 306.1 AND |
| | VERIFY ACCESS IS PROVIDED FOR AC AND FAN UNITS LOCATED |
| | ABOVE HARD CEILING. SHOW AN ACCESS PANEL WITH |
| | DIMENSIONS ON THE DRAWINGS WHERE REQUIRED- SECTION |
| | 306.1 FBC M. |
| | 96) M.209, M.211, M.212: INDICATE LOCATIONS OF ABOVE |
| | CEILING PLENUMS AND AIR HANDLER CLOSETS AND NOTE NO |
| | COMBUSTIBLE MATERIALS PERMITTED. |
| | 97) M.209, M.211, M.212: BRANCH DUCT SIZES NOT SHOWN- |
| | SECTION 603.1 FBC M. |
| | 98) M.209, M.211, M.212: AUTOMATICALLY OPERATING |
| | SHUTOFF DAMPERS ARE REQUIRED FOR THE O/A DUCTS SERVING |
| | THE SUITES- SECTION C403.2.4.3 FBC EC. |
| | |
| | OFFICE TOWER |
| | 100) SHEETS M.213, M.214, M.215: INCOMPLETE PLANS AND |
| | DETAILS. IT APPEARS THAT OFFICE SHELL SPACES ARE |
| | DEPICTED HOWEVER THERE ARE NO NOTES TO CLARIFY. PLEASE |
| | LABEL ALL THE ROOMS SHOWN ON THE PLAN- SECTION 107.2.1 |
| | WPB. |
| | 101) M.213, M.214, M.215: LABEL THE SYSTEMS IN THE MECH |
| | RM- SECTION 107.2.1 WPB.102) |
| | 102) M.213, M.214, M.215: FIRE/SMOKE DAMPERS MISSING |
| | FOR THE 64X28 SUPPLY AND RETURN DUCTS PENETRATING THE |
| | FIRE-RATED MECH RM WALLS- SECTION 607.5.3 FBC M. |
| | 103) M.213, M.214, M.215: NO O/A OR CONDITIONING HAS |
| | BEEN PROVIDED IN THE FIRE AND ELEVATOR LOBBIES- SECTION |
| | 107.2.1 WPB. |
| | 104): M.213, M.214, M.215: DUCT SMOKE DETECTORS ARE |
| | REQUIRED IN THE SUPPLY SYSTEMS OF THE AHU'S PER SECTION |
| | 606.2.1 FBC M. PLEASE PROVIDE DS SYMBOLS ON THE PLANS |
| | AND RISER DRAWINGS TO SHOW THE LOCATIONS. |
| | 105) M.213, M.214, M.215: DUCT SMOKE DETECTORS ARE |
| | REQUIRED IN THE SUPPLY SYSTEMS OF THE 100% O/A ERU |
| | SYSTEMS, AND AT EACH STORY OF THE RA/EA RISER- SECTION |
| | 606.2.3. PLEASE PROVIDE DS SYMBOLS ON THE PLANS AND |
| | RISER DRAWINGS TO SHOW THE LOCATIONS. |
| | 106) M.216: LABEL ALL ROOMS AND AREAS SHOWN ON THE |
| | PLANS- SECTION 107.2.1 WPB. |
| | 107) M.216: FIRE DAMPERS MISSING FOR ERU-03 SUPPLY AND |
| | RETURN DUCTS PENETRATING THE FIRE-RATED MECHANICAL ROOM |
| | WALLS- SECTION 607.5.3 FBC M. |
| | 108) M.216: NO O/A OR CONDITIONING HAS BEEN PROVIDED IN |
| | THE FIRE AND ELEVATOR LOBBIES- SECTION 107.2.1 WPB. |
| | 109) M.216: LABEL THE AIR INLET OPENING AT THE ERU-03 |
| | MECHANICAL ROOM- SECTION 107.2.1 WPB. |
| | 110) M.216: IT APPEARS THE SMOKE PURGE EXHAUST AND |
| | ERU-03 RETURN DUCTS ARE CONNECTED OR IN THE SAME SHAFT- |
| | PLEASE CLARIFY- SECTION 107.2.1 WPB. |
| | 110) M.216: PROVIDE ENLARGED DRAWINGS OF THE CHILLER |
| | MECHANICAL ROOMS AND SHOW HOW THE ROOMS ARE BEING |
| | VENTILATED PER SECTIONS 1105.6 FBC M. A) PROVIDE NORMAL |
| | AND EMERGENCY VENTILATION CALCULATIONS AND DETAILS- |
| | SECTIONS 1105.6.3.1 & 1105.6.3.2 FBC M. C) SHOW THE |
| | LOCATIONS OF REFRIGERANT DETECTORS AND SUBMIT |
| | MANUFACTURER'S SPECIFICATIONS. D) SHOW HOW THE CHILLERS |
| | ARE BEING ANCHORED TO THE STRUCTURE. E) LABEL ALL |
| | EQUIPMENT IN THE ROOM AND PROVIDE AN EQUIPMENT |
| | SCHEDULE. |
| | 111) M.216: PROVIDE AN ENLARGED DRAWING OF THE COOLING |
| | TOWER ROOM AND SHOW HOW THE ROOM IS BEING VENTILATED- |
| | NATURALLY OR MECHANICALLY- PROVIDE CALCULATIONS AND |
| | DETAILS. A) SHOW VAPOR PLUME DISCHARGE LOCATIONS AND |
| | REQUIRED CLEARANCE DISTANCES PER SECTION 908.3 FBC M. |
| | B) SHOW HOW THE TOWERS ARE BEING ANCHORED TO THE |
| | STRUCTURE- SECTION 908.4 FBC M (ENGINEERING FOR SUPPORT |
| | AND PLATFORM STRUCTURES MAY BE DEFERRED). C) PROVIDED |
| | WATER PIPING SUPPLY AND RETURN DIAGRAMS. D) SHOW THE |
| | WATER FEED LINE PIPE AND BACKFLOW PREVENTER |
| | CONNECTIONS- SECTION 908.5 FBC M. |
| | 112) M.217: CLARIFY IF THE ELEVATOR HOISTWAYS ARE TO BE |
| | VENTILATED AND PROVIDE DETAILS- SECTION 909.21.2 FBC B. |
| | 113) M.216 & M.217: SHOW THE LOCATION OF THE ELEVATOR |
| | CONTROL ROOM AND SHOW COMPLIANCE WITH SECTION 3005.2 |
| | FBC B FOR INDEPENDENT VENTILATION SYSTEMS. |
| | |
| | RESIDENTIAL TOWER |
| | 114) SHEETS M.218, M.219, M.220, & M.221: DUCT SMOKE |
| | DETECTORS ARE REQUIRED IN THE SUPPLY SYSTEMS OF THE |
| | AHU'S PER SECTION 606.2.1 FBC M. PLEASE PROVIDE DS |
| | SYMBOLS ON THE PLANS AND RISER DRAWINGS TO SHOW THE |
| | LOCATIONS. |
| | 115) M.218, M.219, M.220, & M.221: DUCT SMOKE DETECTORS |
| | ARE REQUIRED IN THE SUPPLY SYSTEMS OF THE 100% O/A ERU |
| | SYSTEMS, AND AT EACH STORY OF THE RA/EA RISER- SECTION |
| | 606.2.3. PLEASE PROVIDE DS SYMBOLS ON THE PLANS AND |
| | RISER DRAWINGS TO SHOW THE LOCATIONS. |
| | 116) M.218, M.219, M.220, & M.221: INDICATE HOW O/A IS |
| | BEING PROVIDED TO THE UNITS AND PROVIDE CALCULATIONS- |
| | SECTION 401.2 FBC M. |
| | 117) M.218, M.219, M.220, & M.221: SHOW CLEARANCE |
| | DISTANCE MEASUREMENTS FOR THE TOILET AND DRYER EXHAUST |
| | OUTLETS IN COMPLIANCE WITH SECTIONS 501.3.1 FBC M OR |
| | PROVIDE GENERAL KEYNOTES. |
| | 118) M.218, M.219, M.220, & M.221: REFER TO SECTION |
| | 306.1 AND VERIFY ACCESS IS PROVIDED FOR AC AND FAN |
| | UNITS LOCATED ABOVE HARD CEILING. SHOW AN ACCESS PANEL |
| | WITH DIMENSIONS ON THE DRAWINGS WHERE REQUIRED- SECTION |
| | 306.1 FBC M. |
| | 119) M.218, M.219, M.220, & M.221: INDICATE LOCATIONS |
| | OF ABOVE CEILING PLENUMS AND AIR HANDLER CLOSETS AND |
| | NOTE NO COMBUSTIBLE MATERIALS PERMITTED.120 |
| | 120) M.218, M.219, M.220, & M.221: BRANCH DUCT SIZES |
| | NOT SHOWN- SECTION 603.1 FBC M. |
| | 121) M.218, M.219, M.220, & M.221: AUTOMATICALLY |
| | OPERATING SHUTOFF DAMPERS WILL BE REQUIRED FOR O/A |
| | DUCTS SERVING THE UNITS- SECTION C403.2.4.3 FBC EC. |
| | 122) M.218, M.219, M.220, & M.221: PROVIDE VENTILATION |
| | FOR THE CORRIDORS, ELEVATOR AND FIRE LOBBIES- TABLE |
| | 403.3.1.1 FBC M. |
| | 123) M.220: NO DUCT LAYOUT PLANS PROVIDED- SECTION |
| | 107.2.1 FBC M. |
| | 124) M.218, M.219, M.220, & M.221: REFER TO SECTION |
| | 504.1 AND SUBMIT MANUFACTURER'S SPECIFICATIONS FOR THE |
| | CLOTHES DRYERS. PROVIDE ON THE PLANS DRYER EXHAUST DUCT |
| | DIAGRAMS THAT SHOW THE TOTAL RUN LENGTHS OF THE SYSTEMS |
| | CONSISTENT WITH THE MANUFACTURER'S GUIDELINES. |
| | 125) M.222: PROVIDE ENLARGED DRAWINGS OF THE MECHANICAL |
| | ROOM AND SHOW HOW THE ROOMS IS BEING VENTILATED PER |
| | SECTIONS 1105.6 FBC M. A) PROVIDE NORMAL AND EMERGENCY |
| | VENTILATION CALCULATIONS AND DETAILS- SECTIONS |
| | 1105.6.3.1 & 1105.6.3.2 FBC M. C) SHOW THE LOCATIONS OF |
| | REFRIGERANT DETECTORS AND SUBMIT MANUFACTURER'S |
| | SPECIFICATIONS. D) SHOW HOW THE CHILLERS ARE BEING |
| | ANCHORED TO THE STRUCTURE. E) LABEL ALL EQUIPMENT IN |
| | THE ROOM AND PROVIDE AN EQUIPMENT SCHEDULE. E) PROVIDE |
| | MANUFACTURER?S SPECIFICATIONS FOR THE BOILERS- SECTION |
| | 631.1 FBC FG. PLEASE NOTE THAT OPEN FAME GAS EQUIPMENT |
| | SHALL NOT USE COMBUSTION AIR FROM THE MACHINERY ROOM- |
| | SECTION 1105.5 FBC FG. |
| | 126) M.222: PROVIDE AN ENLARGED DRAWING OF THE COOLING |
| | TOWER ROOM AND SHOW HOW THE ROOM IS BEING VENTILATED- |
| | NATURALLY OR MECHANICALLY- PROVIDE CALCULATIONS AND |
| | DETAILS. A) SHOW VAPOR PLUME DISCHARGE LOCATIONS AND |
| | REQUIRED CLEARANCE DISTANCES PER SECTION 908.3 FBC M. |
| | B) SHOW HOW THE TOWERS ARE BEING ANCHORED TO THE |
| | STRUCTURE- SECTION 908.4 FBC M (ENGINEERING FOR SUPPORT |
| | AND PLATFORM STRUCTURES MAY BE DEFERRED). C) PROVIDED |
| | WATER PIPING SUPPLY AND RETURN DIAGRAMS. D) SHOW THE |
| | WATER FEED LINE PIPE AND BACKFLOW PREVENTER |
| | CONNECTIONS- SECTION 908.5 FBC M. |
| | 127) M.222: SUBMIT MANUFACTURER'S SPECIFICATIONS FOR |
| | THE GENERATOR, FUEL PIPING, ENGINE EXHAUST PIPE, |
| | MUFFLER, AND ALL OTHER ASSOCIATED SYSTEM COMPONENTS- |
| | SECTION 304.1 FBC M. A) SUBMIT THE UL 2200 CERTIFICATE |
| | OF COMPLIANCE FOR THE GENERATOR- SECTION 915.1 FBC M. |
| | THE MANUFACTURER'S SPECIFICATIONS AND/OR UL CERTIFICATE |
| | SHALL INDICATE THE GENERATOR IS COMPLIANT WITH THE NFPA |
| | 37 AND NFPA 110 STANDARDS. B) SUBMIT MANUFACTURER'S |
| | SPECIFICATIONS FOR THE FUEL TANK THAT INCLUDES THE |
| | TANK'S UL LISTING- UL 142 OR UL 2085- SEE SECTION |
| | 21.4.2.1.1 NFPA 30. C) REFER TO 4.1 NFPA 110 AND |
| | INDICATE THE CLASSIFICATION AND LEVEL OF THE EPSS |
| | SYSTEM. PLEASE INCLUDE THIS INFORMATION IN THE SMOKE |
| | CONTROL RATIONAL ANALYSIS. D) SUBMIT THE GENERATOR |
| | EXHAUST PIPE SPECIFICATIONS AND PROVIDE AN EXHAUST PIPE |
| | DIAGRAM SHOWING THE TOTAL SYSTEM RUN AND LENGTH |
| | MEASUREMENT, AND TERMINATION LOCATION PLEASE INCLUDE |
| | ALL COMPONENTS OF THE SYSTEM INCLUDING THE SILENCER, |
| | AND ANY CONTRACTOR SUPPLIED PIPING- SEE SECTION 8.1. |
| | 8.4 NFPA 37, AND SECTION 501.3.1 FBC M. E) PROVIDE |
| | DETAILS AND SPECIFICATIONS FOR NORMAL AND EMERGENCY |
| | RELIEF VENTING OF THE TANK, INCLUDING VENT PIPING RUNS |
| | AND TERMINATION LOCATIONS- SECTION 24.13 NFPA 30. |
| | 128) M.222: PROVIDE WIND LOAD ENGINEERING FOR |
| | ATTACHMENT OF THE GENERATOR TO THE ROOF STRUCTURE- |
| | SECTION 301.15 FBC M. |
| | 129) M.223: SHOW THE LOCATIONS OF THE ELEVATOR CONTROL |
| | ROOMS AND SHOW COMPLIANCE WITH SECTION 3005.2 FBC B FOR |
| | INDEPENDENT VENTILATION SYSTEMS. |
| | |
| | HOTEL SUITES: |
| | 130) M.250- M.253: SHOW HOW O/A IS BEING PROVIDED TO |
| | THE SUITES- SECTION 401.2 FBC M, AND HOW IT IS BEING |
| | AUTOMATICALLY CONTROLLED- SECTION C403.2.4.3 FBC EC. |
| | 131) M.250- M.253: REFER TO SECTION 306.1 AND VERIFY |
| | ACCESS IS PROVIDED FOR THE FCU'S LOCATED ABOVE HARD |
| | CEILINGS OR IN CLOSETS. SHOW AN ACCESS PANEL WITH |
| | DIMENSIONS ON THE DRAWINGS WHERE REQUIRED- SECTION |
| | 306.1 FBC M. |
| | 132) M.250- M.253: INDICATE LOCATIONS OF ABOVE CEILING |
| | PLENUMS AND AIR HANDLER PLENUM CLOSETS AND NOTE NO |
| | COMBUSTIBLE MATERIALS PERMITTED. |
| | |
| | RESIDENTIAL UNITS |
| | 133) M.254- M.258: LABEL ALL ROOMS AND SPACES ON THE |
| | PLANS- SECTION 107.2.1 WPB. |
| | 134) M.254- M.258: SHOW HOW O/A IS BEING PROVIDED TO |
| | THE UNITS- SECTION 401.2 FBC M, AND HOW IT IS BEING |
| | AUTOMATICALLY CONTROLLED- SECTION C403.2.4.3 FBC EC. |
| | 135) M.254- M.258: PLACE NOTES TO INDICATE NO |
| | COMBUSTIBLE MATERIALS PERMITTED IN THE VHP CLOSETS |
| | INCLUDING THE DOORS- SECTION 602.2.1 FBC M. IT APPEARS |
| | THE DOORS WILL BE LOUVERED TO ALLOW RETURN AIR TO THE |
| | HEAT PUMPS, OTHERWISE INDICATE MEANS OF RETURN AIR- |
| | SECTION 601.6 FBC M. |
| | 136) M.254- M.258: INDICATE HOW AIR IS BEING RETURNED |
| | FROM THE BEDROOMS- SECTION 601.6. |
| | 137) M.254- M.258: REFER TO SECTION 504.1 AND SUBMIT |
| | MANUFACTURER'S SPECIFICATIONS FOR THE CLOTHES DRYERS. |
| | PROVIDE ON THE PLANS DRYER EXHAUST DUCT DIAGRAMS THAT |
| | SHOW THE TOTAL RUN LENGTHS OF THE SYSTEMS CONSISTENT |
| | WITH THE MANUFACTURER'S GUIDELINES. |
| | 138) M.254- M.258: PROVIDE AN ENLARGED DRAWING OF THE |
| | VHP CLOSETS SHOWING REQUIRED CLEARANCES- SECTION |
| | C403.2.9.3.3 FBC EC, AND PRIMARY AND SECONDARY MEANS OF |
| | CONDENSATE DISPOSAL- SECTION 307.2.1, 307.2.2, & |
| | 307.2.3 FBC M. |
| | 139) PROVIDE A CONDENSATE DISPOSAL RISER DRAWING- TABLE |
| | 307.2.2 FBC M. |
| | 140) PROVIDE FIRESTOPPING DETAILS FOR CHILLED AND HOT |
| | WATER PIPES, AND DUCTWORK. |
| | |
| | |
| | WHEN RESUBMITTING, IT IS HELPFUL TO PROVIDE A RESPONSE |
| | LETTER ADDRESSING EACH ITEM ALONG WITH THE CITY |
| | RE-SUBMITTAL FORM. ADDITIONALLY, PLEASE INSERT |
| | CORRECTED PLAN SHEETS INTO THE SETS, REMOVE THE |
| | PREVIOUSLY REVIEWED SHEETS AND MARK VOID ON THEM, AND |
| | KEEP THEM WITH THE SUBMITTALS |
| | |
| | CHRISTOPHER L. COLE |
| | MECHANICAL PLANS EXAMINER |
| | 401 CLEMATIS STREET |
| | WEST PALM BEACH FL 33401 |
| | 561-805-6719 |
| | [email protected] |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |