| 2019-07-05 11:00:07 | REVIEW COMMENTS |
| | |
| | 3RD REVIEW: FBC SIXTH EDITION (2017) |
| | ROBERT MCDOUGAL, CBO |
| | COMMERCIAL COMBINATION PLANS EXAMINER |
| | (561) 805-6714 |
| | [email protected] |
| | WPB PERMIT: 18081528 |
| | ADD: 1515 S. FLAGLER DRIVE |
| | CONT: |
| | TEL: |
| | EMAIL: |
| | |
| | 1) ART IN PUBLIC PLACES - WILL COMPLY. |
| | |
| | 2) COMPLIED. |
| | |
| | 3) COMPLIED. |
| | |
| | 4) COMPLIED. |
| | |
| | 5) COMPLIED. |
| | |
| | 6) COMPLIED. |
| | |
| | 7) COMPLIED. |
| | |
| | 8) COMPLIED. |
| | |
| | 9) COMPLIED. |
| | |
| | 10) COMPLIED. |
| | |
| | 11) COMPLIED. |
| | |
| | 12) COMPLIED. |
| | |
| | 13) COMPLIED. |
| | |
| | 14) COMPLIED.. |
| | |
| | 15) COMPLIED. |
| | |
| | 16) COMPLIED. |
| | |
| | 17) COMPLIED. |
| | |
| | 18) COMPLIED. |
| | |
| | 19) COMPLIED. |
| | |
| | 20) COMPLIED. |
| | |
| | 21) COMPLIED. |
| | |
| | 22) COMPLIED. |
| | |
| | 23) COMPLIED. |
| | |
| | 24) COMPLIED. |
| | |
| | 25) COMPLIED. |
| | |
| | 26) COMPLIED. |
| | |
| | 27) COMPLIED. |
| | |
| | 28) COMPLIED. |
| | |
| | 29) COMPLIED. |
| | |
| | 30) COMPLIED. |
| | |
| | 31) COMPLIED. |
| | |
| | 32) COMPLIED. |
| | |
| | 33) COMPLIED. |
| | |
| | 34) COMPLIED. |
| | |
| | 35) COMPLIED. |
| | |
| | 36) COMPLIED. |
| | |
| | 37) COMPLIED. |
| | |
| | 38) COMPLIED. |
| | |
| | 39)COMPLIED. |
| | |
| | 40) NOT COMPLIED. SOME OF THE ITEMS THAT ARE LISTED AS |
| | DEFERRED ON SHEET G-7 ARE REQUIRED TO HAVE SEPARATE |
| | PERMITS, APPLICATIONS AND REVIEWS. SEPARATE PERMITS ARE |
| | REQUIRED FOR GENERATORS, IRRIGATION, LANDSCAPE, POOLS |
| | AND FENCES. THESE ITEMS REQUIRING SEPARATE PERMITS |
| | SHOULD NOT BE LISTED AS DEFERRED (NO FEE) SUBMITTALS. |
| | PROVIDE A LIST OF THE ITEMS THAT WILL BE DEFERRED ON |
| | THE PLANS. FBC 107.3.4.1 DEFERRED SUBMITTALS. FOR THE |
| | PURPOSES OF THIS SECTION, DEFERRED SUBMITTALS ARE |
| | DEFINED AS THOSE PORTIONS OF THE DESIGN THAT ARE NOT |
| | SUBMITTED AT THE TIME OF THE APPLICATION AND THAT ARE |
| | TO BE SUBMITTED TO THE BUILDING OFFICIAL WITHIN A |
| | SPECIFIED PERIOD. DEFERRAL OF ANY SUBMITTAL ITEMS SHALL |
| | HAVE THE PRIOR APPROVAL OF THE BUILDING OFFICIAL. THE |
| | REGISTERED DESIGN PROFESSIONAL IN RESPONSIBLE CHARGE |
| | SHALL LIST THE DEFERRED SUBMITTALS ON THE CONSTRUCTION |
| | DOCUMENTS FOR REVIEW BY THE BUILDING OFFICIAL. |
| | |
| | 41) DEFERRED. W. P. B. 107.3.4.1 PRODUCT APPROVALS. |
| | THOSE PRODUCTS WHICH ARE REGULATED BY THE DCA RULE |
| | 9N-03 SHALL BE REVIEWED AND APPROVED IN WRITING BY THE |
| | DESIGNER OF RECORD PRIOR TO SUBMITTAL FOR |
| | JURISDICTIONAL APPROVAL. FL 61G1-23.015 (2) THE |
| | ARCHITECT IS RESPONSIBLE FOR SUPERVISING AND REVIEWING |
| | ALL PROJECT DATA, REPORTS, SHOP DRAWINGS ETC. |
| | DOCUMENTS FOR DEFERRED SUBMITTAL ITEMS SHALL BE |
| | SUBMITTED TO THE REGISTERED DESIGN PROFESSIONAL IN |
| | RESPONSIBLE CHARGE WHO SHALL REVIEW THEM AND FORWARD |
| | THEM TO THE BUILDING OFFICIAL WITH A NOTATION |
| | INDICATING THAT THE DEFERRED SUBMITTAL DOCUMENTS HAVE |
| | BEEN REVIEWED AND FOUND TO BE IN GENERAL CONFORMANCE TO |
| | THE DESIGN OF THE BUILDING. THE DEFERRED SUBMITTAL |
| | ITEMS SHALL NOT BE INSTALLED UNTIL THE DEFERRED |
| | SUBMITTAL DOCUMENTS HAVE BEEN APPROVED BY THE BUILDING |
| | OFFICIAL. |
| | |
| | 42) PARTIAL COMPLIANCE. THIS NOTE IS INCORRECTLY WORDED |
| | AND NEEDS TO BE REVISED. FBC 1207.2 ADDRESSES |
| | AIR-BOURNE SOUND THAT WHEN TESTED IN ACCORDANCE WITH |
| | ASTM E90 IS REQUIRED TO HAVE A SOUND TRANSMISSION CLASS |
| | (STC) OF NOT LESS THAN 50 OR NOT LESS THAN 45 IF TESTED |
| | IN THE FIELD. FBC 1207.3 ADDRESSES STRUCTURE-BOURNE |
| | SOUND THAT WHEN TESTED IN ACCORDANCE WITH ASTM E492 IS |
| | REQUIRED TO HAVE AN IMPACT INSULATION CLASS (IIC) |
| | RATING OF NOT LESS THAN 50 OR NOT LESS THAN 45 WHEN |
| | TESTED IN THE FIELD. REVISE THE NOTE ON THE PLAN TO |
| | INCLUDE ASTM E 492. SHOW COMPLIANCE WITH FBC 1207.2 FOR |
| | AIR-BORNE SOUND TRANSMISSION AND FBC 1207.3 FOR |
| | STRUCTURE BORNE SOUND INSULATION. |
| | |