| 2019-01-17 18:31:19 | NEW BUILDING (GROUP B) SECOND BUILDING REVIEW |
| | CHECKLIST. |
| | CODE: FBC 6TH EDITION (2017) AND CITY AMENDMENTS. |
| | |
| | |
| | PROVISO NOTE: |
| | BUILDING REVIEW MAY BE APPROVED WITH PROVISO. PROVISO |
| | MEANS CONTRACTOR WILL SUBMIT REQUIRED INFORMATION AFTER |
| | THE PERMIT IS ISSUED BUT BEFORE INSPECTIONS TO AVOID |
| | CONFLICTS/DELAYS. REVISION FEES MAY APPLY. CONTRACTOR |
| | TO ADVICE IF PROVISO OPTION IS PREFERRED AT THIS TIME |
| | OR IF RE-SUBMITTING REQUIRED INFORMATION BEFORE PERMIT |
| | ISSUANCE. |
| | |
| | |
| | 1- OK. |
| | |
| | 2- TO BE DONE LATER BEFORE ISSUING PERMIT. |
| | |
| | 3- SOIL TEST REPORT SUBMITTED NEEDS SURVEYORS ORIGINAL |
| | SEAL AND SIGNATURE OR DIGITAL SIGNATURE WHEN SUBMITTING |
| | DOCUMENTS FOR PUBLIC RECORDS. CHAPTER 472 F.S. |
| | |
| | 4- OK. |
| | |
| | 5- ENERGY CALCULATIONS FORM SUBMITTED: |
| | A) PLANS NEED TO SPECIFY THE INSULATION R VALUE OF |
| | EXTERIOR WALLS. NOTE: ARCHITECT AND ENGINEER PREPARING |
| | THE ENERGY CALCULATIONS TO COORDINATE INFORMATION TO |
| | AVOID CONFLICTS/DELAYS. THIS APPLIES TO CEILING |
| | INSULATION ALSO. SEC. C103.2 FBC-ENERGY CONSERVATION. |
| | |
| | RESPONSE: |
| | PARTIALLY DONE. ARCHITECT PROVIDED INFORMATION ON SHEET |
| | A.05 BUT INFORMATION SHOWN ON THE ENERGY CALCULATIONS |
| | AND ARCHITECTURAL PLANS DON'T MATCH. ARCHITECT AND |
| | ENGINEER TO COORDINATE TO AVOID MORE CONFLICTS/DELAYS. |
| | |
| | B)ARCHITECT OF RECORD TO CERTIFY (SIGNATURE AND LICENSE |
| | NUMBER) ON ENERGY FORM AS REQUIRED BY SEC. C103.1.1.1.2 |
| | FBC-ENERGY CONSERVATION. |
| | |
| | RESPONSE: |
| | REPEAT COMMENT. NOT DONE. |
| | |
| | C) THE BUILDING OWNER OR LEGALLY AUTHORIZED AGENT NEEDS |
| | TO CERTIFY THAT THE BUILDING IS IN COMPLIANCE WITH THE |
| | ENERGY CODE AS REQUIRED BY SEC. C103.1.1.2 FBC-ENERGY |
| | CONSERVATION PRIOR TO RECEIVING THE PERMIT TO BEGIN |
| | CONSTRUCTION. |
| | |
| | RESPONSE: |
| | REPEAT COMMENT. NOT DONE. |
| | |
| | D) ENGINEER OF RECORD PERFORMING THE ENERGY |
| | CALCULATIONS TO COORDINATE WITH ARCHITECTURAL PLANS TO |
| | AVOID CONFLICTS/DELAYS. INFORMATION FOR WALLS AND |
| | CEILING INSULATION R VALUE DOESN'T MATCH. SEC. 107.2.1 |
| | CITY AMENDMENTS. ALSO, CHECK THE PROPER BOXES IN THE |
| | MANDATORY SECTION. |
| | |
| | RESPONSE: |
| | REPEAT COMMENT. NOT DONE. |
| | |
| | 6- PROVIDE COMPLETE DETAILS AND SPECIFICATIONS FOR |
| | INTERIOR WINDOWS SHOWN ON FLOOR PLANS. INCLUDE FRAMING |
| | DETAILS AND GLAZING SPECIFICATIONS. SEC. 2406 FBC. |
| | |
| | RESPONSE: |
| | RESPONSE LETTER STATES ""PLEASE SEE REVIEWED NOA". |
| | CLARIFY IF INSTALLING SAME TYPE OF WINDOWS AS THE ONES |
| | USED FOR THE EXTERIOR. PROVIDE CLEAR SPECIFICATIONS IN |
| | THE WINDOW SHELLED ON SHEET A.13. |
| | |
| | 7- OK. |
| | |
| | 8- OK. |
| | |
| | 9- OK. |
| | |
| | 10- DUMPSTER STRUCTURAL PLANS SHOWN ON SHEET A.03 DON'T |
| | MATCH STRUCTURAL PLANS SHOWN ON SHEET S.01. REVISE AS |
| | REQUIRED TO MATCH. SEC. 107.2.1 CITY AMENDMENTS. |
| | |
| | RESPONSE: |
| | STILL DON'T MATCH. REVISE AS REQUIRED TO MATCH (SEE |
| | DIMENSIONS AND STRUCTURAL SPECIFICATIONS) OR PROVIDE |
| | ONLY ONE DETAIL TO AVOID CONFLICTS. |
| | |
| | 11- PROVIDE PRODUCT APPROVAL AS REQUIRED BY FAC |
| | 61G20-3.001 FOR: |
| | (NOTE: THIS MAY BE SUBMITTED LATER AS A DEFERRED |
| | SUBMITTAL) |
| | |
| | A)GAF SINGLE PLY PLY ROOFING SYSTEMS NOA 18-0523.05 |
| | SUBMITTED. PROVIDE SIGNED AND SEALED RAS 117 |
| | CALCULATIONS AS REQUIRED BY GENERAL LIMITATION #7. |
| | SEC. 1609 FBC. |
| | |
| | |
| | |
| | PLEASE NOTE THAT SUBMITTAL OF ADDITIONAL AND/OR REVISED |
| | MATERIALS MAY RESULT IN NEW PLAN REVIEW COMMENTS. |
| | WHEN RESUBMITTING, IT IS HELPFUL TO PROVIDE A RESPONSE |
| | LETTER ADDRESSING EACH ITEM ALONG WITH THE CITY |
| | RE-SUBMITTAL FORM. |
| | |
| | IF YOU HAVE ANY QUESTIONS, PLEASE CONTACT |
| | JULIO GOMEZ |
| | COMMERCIAL COMBINATION PLANS EXAMINER |
| | DEVELOPMENT SERVICES DEPARTMENT |
| | BUILDING DIVISION |
| | (561)805-6712 |