| Date |
Text |
| 2018-12-07 08:53:52 | RESIDENTIAL (R3) REVISION, FOURTH BUILDING REVIEW |
| | CHECKLIST. |
| | |
| | |
| | ORIGINAL COMMENT: |
| | (1)- ENERGY CALCULATIONS ARE TAKING THE CEILING FAN |
| | CREDIT. REVISE GREAT ROOM CEILING FAN SIZE TO COMPLY |
| | WITH SEC. R405.7.6 FBC-ENERGY CONSERVATION. |
| | |
| | RESPONSE: |
| | |
| | IT LOOKS LIKE THERE IS CONFUSION BETWEEN ENERGY |
| | CALCULATIONS AND EQUIPMENT LOAD CALCULATIONS. THEY ARE |
| | TWO DIFFERENT THINGS. CALCULATIONS SUBMITTED ARE FOR |
| | THE A/C EQUIPMENT SIZING. THEY ARE NOT THE ENERGY |
| | CALCULATIONS. ENERGY CALCULATIONS ARE ON FORM |
| | R405-2014. THESE ARE THE ONES THAT ARE TAKEN THE EXTRA |
| | CREDIT BY ADDING THE CEILING FANS. THAT'S WHY THE |
| | CEILING FANS MUST BE INSTALLED. IF CEILING FAN CREDIT |
| | IS NOT GOING TO BE TAKEN, THEN THE ENERGY CALCULATIONS |
| | (FORM R405-2014) ARE THE ONES THAT NEED TO BE REVISED |
| | NOT THE A/C EQUIPMENT SIZING CALCULATIONS. |
| | NOTE: PLEASE MAKE SURE REVISED ENERGY CALCULATIONS HAVE |
| | THE NAME OF THE PERSON DOING THE CALCULATIONS AND ARE |
| | CERTIFIED AT THE BOTTOM OF THE FORM BY THE OWNER OR |
| | LEGAL AGENT TO AVOID MORE CONFLICTS/DELAYS. |
| | |
| | |
| | ****PLEASE PROVIDE RESPONSE LETTER ADDRESSING EACH |
| | COMMENT TO HELP EXPEDITE THE REVIEW PROCESS. |
| | |
| | ****PLEASE INSERT ANY REVISED DRAWING AND REMOVE OLD |
| | DRAWING. SUBMIT OLD DRAWINGS FOR REFERENCE OF ALREADY |
| | REVIEWED DRAWINGS. DO NOT STAPLE OLD DRAWINGS TO PLANS. |
| | |
| | |
| | IF YOU HAVE ANY QUESTIONS, PLEASE CONTACT |
| | JULIO GOMEZ |
| | COMMERCIAL COMBINATION PLANS EXAMINER |
| | DEVELOPMENT SERVICES DEPARTMENT |
| | BUILDING DIVISION |
| | (561)805-6712 |
| | [email protected] |