Plan Review Notes For Permit 18071320
Permit Number 18071320
Review Stop P
Sequence Number 1
Notes
Date Text
2018-09-28 12:55:319/29/18 PROVISO COMPLIED CONTRACTOR SUBMITTED
 LETTERS/GPJ
2018-08-28 14:47:41APPROVED WITH PROVISO PROVIDE THE FOLLOWING BEFORE NEXT
 INSPECTION.
  
 I CAN APPROVE THE DELETION OF THE DECONTAMINATION
 HOLDING TANK UNDER THE FOLLOWING CONDITIONS:
 PROVIDE THE FOLLOWING DOCUMENTS:
  
 1) TWO ORIGINAL SIGNED AND SEALED COPIES OF A LETTER
 FROM THE DESIGN PROFESSIONAL OF RECORD FOR THIS PERMIT
 REQUESTING THE DELETION OF THE TANK SHALL BE SUBMITTED
 TO THE CITY OF WEST PALM BEACH BUILDING DEPARTMENT FOR
 REVIEW AND APPROVAL.
  
 2) TWO ORIGINAL SIGNED COPIES OF THE LETTER FROM
 GREGORY A. DALTON SHALL ALSO BE SUBMITTED WITH THE PLAN
 REVISION. PLEASE REVISE THE LETTER TO READ " FACILITY
 GUIDELINES INSTITUTE" IN LIEU OF THE ACRONYM "FGI".
  
  
 GEORGE JOHNSON
 PLUMBING PLANS EXAMINER
 CITY OF WEST PALM BEACH
  561-805-6711
 [email protected]
  