| 2018-12-03 15:31:59 | ****CORRECTIONS**** |
| | W.P.B. PERMIT: 18071301 |
| | REVIEWED: AUGUST 24, 2018 |
| | |
| | DYLAN BATTLES |
| | BUILDING PLANS EXAMINER |
| | [email protected] |
| | 561-805-6718 |
| | |
| | FBC = FLORIDA BUILDING CODE, 6TH EDITION (2017) |
| | FBC B = FBC BUILDING |
| | FBC A = FBC ACCESSIBILITY |
| | FBC EC = FBC ENERGY CONSERVATION |
| | FBC R = FBC RESIDENTIAL |
| | FLOOD ZONE = X |
| | |
| | 2ND REVIEW |
| | DECEMBER 03,2018 |
| | |
| | 1. [FBC R401.3]PROVIDE SITE DRAINAGE PLAN. |
| | |
| | 2ND REVIEW - DRAINAGE PLAN HAS NOT BEEN SUBMITTED. |
| | IT SHOULD INCLUDE KEY ELEVATIONS SUCH AS BASE FLOOR |
| | ELEVATION (B.F.E.) SINCE GRADE NEEDS TO BE 4 INCHES |
| | BELOW SLAB YOU WOULD START DRAINAGE FROM FOUNDATION -4 |
| | INCHES. |
| | OTHER KEY POINTS ARE 2% GRADE FROM BACK YARD TO STORM |
| | DRAIN AT STREET. |
| | PLEASE CALL IF ANY QUESTIONS ABOUT DRAINAGE PLAN. |
| | |
| | [FBC R403.1.7.3] FOUNDATION ELEVATION. ON GRADED SITES, |
| | THE TOP OF ANY EXTERIOR FOUNDATION SHALL EXTEND ABOVE |
| | THE ELEVATION OF THE STREET GUTTER AT POINT OF |
| | DISCHARGE OR THE INLET OF AN APPROVED DRAINAGE DEVICE A |
| | MINIMUM OF 12 INCHES (305 MM) PLUS 2 PERCENT. ALTERNATE |
| | ELEVATIONS ARE PERMITTED SUBJECT TO THE APPROVAL OF THE |
| | BUILDING OFFICIAL, PROVIDED IT CAN BE DEMONSTRATED THAT |
| | REQUIRED DRAINAGE TO THE POINT OF DISCHARGE AND AWAY |
| | FROM THE STRUCTURE IS PROVIDED AT ALL LOCATIONS ON THE |
| | SITE. |
| | |
| | [FBC AMENDED 107.2.5] 107.2.5 SITE PLAN. THE |
| | CONSTRUCTION DOCUMENTS SUBMITTED WITH THE APPLICATION |
| | FOR PERMIT SHALL BE ACCOMPANIED BY A SITE PLAN SHOWING |
| | TO SCALE THE SIZE AND LOCATION OF NEW CONSTRUCTION AND |
| | EXISTING STRUCTURES ON THE SITE, DISTANCES FROM LOT |
| | LINES, THE ESTABLISHED STREET GRADES AND THE PROPOSED |
| | FINISHED GRADES, DEPICTING THE PROPOSED LOT DRAINAGE |
| | AND, AS APPLICABLE, FLOOD HAZARD AREAS, FLOODWAYS, AND |
| | DESIGN FLOOD ELEVATIONS; AND IT SHALL BE DRAWN IN |
| | ACCORDANCE WITH AN ACCURATE AND INCLUDED ON A BOUNDARY |
| | LINE SURVEY. |
| | |
| | 2. [FBC R401.4]PROVIDE SOIL REPORT TO SHOW BEARING |
| | CAPACITY AND FOUNDATION RECOMMENDATIONS. |
| | |
| | 2ND REVIEW - SOIL REPORT NOT PROVIDED. ACCORDING TO |
| | SOIL MAP WE MAINTAIN AT BLDG. DEPT. YOUR SITE IS IN AN |
| | AREA THAT DOES REQUIRE SOIL REPORT. |
| | PLEASE PROVIDE SOIL REPORT WITH RE-SUBMITTAL. |
| | |
| | 3. OK |
| | |
| | 4. OK |
| | |
| | |