| 2019-03-21 11:18:49 | 4TH REVIEW FBC-2017 MECHANICAL |
| | PERMIT #18070030 |
| | 9/19/18 |
| | |
| | CODES IN EFFECT: |
| | |
| | FBC B- FLORIDA BUILDING CODE SIXTH EDITION 2017 |
| | FBC M- FLORIDA MECHANICAL CODE SIXTH EDITION 2017 |
| | FBC EC- FLORIDA ENERGY CONSERVATION CODE SIXTH EDITION |
| | 2017 |
| | FBC FG- FLORIDA FUEL GAS CODE SIXTH EDITION 2017 |
| | FBC EX- FLORIDA EXISTING BUILDING CODE SIXTH EDITION |
| | 2017 |
| | FS- FLORIDA STATUTES |
| | FAC- FLORIDA ADMINISTRATIVE CODE |
| | WPB- WEST PALM BEACH AMENDMENTS TO THE FBC SIXTH |
| | EDITION 2017 |
| | |
| | PLAN REVIEW RESULTS: DENIED. |
| | |
| | 1) SHEET M-102: VERIFY THE DESIGN AND OPERATION OF THE |
| | HAZARDOUS EXHAUST VENTILATION SYSTEM (AHU-1 AND EF-1) |
| | IN THE DISTILLERY SHALL BE SUCH THAT FLAMMABLE |
| | CONTAMINANTS ARE DILUTED IN NONCONTAMINATED AIR TO |
| | MAINTAIN CONCENTRATIONS IN THE EXHAUST FLOW BELOW 25 |
| | PERCENT OF THE CONTAMINANT'S LOWER FLAMMABILITY LIMIT. |
| | HAS CAPTURE AND CONTAINMENT OF FLAMABLE VAPORS IN THEIR |
| | HEAVIEST CONCENTRATIONSAROUND THE STILLS AND TANKS BEEN |
| | TAKING INTO CONSIDERATION?- SECTION 502.1.1 FBC M. |
| | |
| | A) DESCRIBE THE SEQUENCE OF OPERATION FOR THE SYSTEM. |
| | WILL THE SYSTEM RUN CONTINUOUSLY, OR INTERMITTENTLY |
| | WHEN DISTILLERY OPERATIONS ARE BEING CONDUCTED? HOW |
| | WILL THE NEW GAS SENSORS AFFECT THE OPERATION OF THE |
| | VENTILATION SYSTEM. WILL THESE SENSORS BE LINKED TO THE |
| | SYSTEM AND ALSO TO THE FIRE ALARM? |
| | |
| | 2) SUBMIT A REVISED ENERGY COMPLIANCE REPORT THAT |
| | INLCUDES THE NEW AC SYSTEM AND THE CHANGES TO THE |
| | BUILDING ENVELOPE. |
| | |
| | 3) PLEASE ADJUST THE TOTAL VALUE OF THE PROPOSED |
| | PROJECT TO INCLUDE THE INCREASED COSTS ASSOCIATED WITH |
| | THE NEW EXHAUST VENTILATION SYSTEM AND SENSORS IN THE |
| | DISTILLERY- SECTION 109.3 FBC M. |
| | |
| | 4) PLEASE NOTE THE LIST OF PROVISOS FROM THE PREVIOUS |
| | REVIEW. |
| | |
| | MECHANICAL PROVISOS. |
| | 11/13/28 |
| | |
| | 1) PRESSURE TESTS FOR CHILLED WATER AND STEAM PIPING |
| | REQUIRED. REQUIRED TEST PRESSURES SHALL BE PROVIDED BY |
| | THE DISTILLERY SYSTEM MANUFACTURER AND THE ENGINEER OF |
| | RECORD. |
| | |
| | 2) PROVIDE A LETTER FROM THE DISTILLERY SYSTEM |
| | MANUFACTURER (CORSON) CERTIFYING THE EQUIPMENT- STILLS, |
| | TANKS, PROCESS PIPINGS ETC.- ARE INSTALLED AND |
| | FUNCTIONING IN ACCORDANCE WITH THE MANUFACTURER'S |
| | GUIDELINES AND SPECIFICATIONS. THE LETTER SHALL BEAR |
| | THE APPROVAL STAMPS OF THE ENGINEER AND ARCHITECT OF |
| | RECORD. |
| | |
| | 3) SITE SPECIFIC WIND LOAD ENGINEERING FOR INSTALLATION |
| | OF THE GLYCOL CHILLER AND OUTDOOR BOILER AND ASSOCIATED |
| | EQUIPMENT SHALL BE SUBMITTED PRIOR TO INSPECTION. |
| | |
| | 6) MANUFACTURER'S SPECIFICATIONS AND INSTALLATION |
| | INSTRUCTIONS FOR THE CHILLER, BOILER, AND THE CORSON |
| | DISTILLERY SYSTEM SHALL BE ONSITE AT TIME OF |
| | INSPECTION. |
| | |
| | WHEN RESUBMITTING, IT IS HELPFUL TO PROVIDE A RESPONSE |
| | LETTER ADDRESSING EACH ITEM ALONG WITH THE CITY |
| | RE-SUBMITTAL FORM. ADDITIONALLY, PLEASE INSERT |
| | CORRECTED PLAN SHEETS INTO THE SETS, REMOVE THE |
| | PREVIOUSLY REVIEWED SHEETS AND MARK VOID ON THEM, AND |
| | KEEP THEM WITH THE SUBMITTALS |
| | |
| | CHRISTOPHER L. COLE |
| | MECHANICAL PLANS EXAMINER |
| | 401 CLEMATIS STREET |
| | WEST PALM BEACH FL 33401 |
| | 561-805-6719 |
| | [email protected] |