Plan Review Notes
Plan Review Notes For Permit 18060566
Permit Number 18060566
Review Stop P
Sequence Number 1
Notes
Date Text
2018-07-02 14:39:4107/02/18 1ST PLUMBING REVIEW**DENIED**
  
 1) ONLY WORK RELATED TO THE POOL ITSELF ARE PERMITTED
 ON THIS PERMIT AND PLAN. SUMMER KITCHEN IS REQUIRED TO
 BE ON IT'S OWN MAIN PERMIT. FBC 107.2.1.
  
 2) SUPPLY GAS POOL HEATER MANUFACTURE INSTALLATION
 MANUAL. FBC 107.2.1
  
 3) PROVIDE THE EXISTING POOL PUMP HP. CITY RECORDS WILL
 BE CHECKED TO VERIFY. IF PUMP HP IS TO BE CHANGED
 PLEASE SUBMIT A COMPLETE (TDH) TOTAL DYNAMIC HEAD OF
 THE POOL PIPING SYSTEM. FBC 107.2.1
  
  
 TIM HUNT
 PLUMBING INSPECTOR / PLUMBING PLAN REVIEWER
 CITY OF WEST PALM BEACH DEVELOPMENT SERVICES DEPARTMENT
 BUILDING DIVISION
 561-805-6695
 [email protected]