| Date |
Text |
| 2018-06-21 07:54:45 | GAS PLAN REVIEW |
| | A GAS PLAN HAS NOT BEEN INCLUDED IN THIS SUBMITTAL |
| | PACKAGE. A GAS PLAN REVIEW HAS NOT BEEN PERFORMED AT |
| | THIS TIME. A SEPARATE GAS PERMIT AND PLANS WILL BE |
| | REQUIRED FOR A CONTRACTOR TO PERFORM THE RELATED WORK. |
| | PROVIDE COMPLETE PLANS, APPLIANCE/ EQUIPMENT |
| | SPECIFICATIONS AND GAS RISER THAT REFLECT THE ENTIRE |
| | SCOPE OF GAS WORK TO BE DONE. WPB AMEND. TO FBC SEC. |
| | 107.2.1. |
| | |
| | GAS APPLIANCES SHALL BE LISTED AND LABELED PER THE |
| | FBC-R, SEC. G2404.3. |
| | GAS APPLIANCES SHALL BE LISTED AND LABELED PER FBC-FUEL |
| | GAS SEC. 301.3. |
| | |
| | A SEPARATE PERMIT AND PLANS IS REQUIRED FOR THE GAS |
| | INSTALLATION OR MODIFICATION OF SYSTEM. |
| | |
| | |
| | GEORGE JOHNSON |
| | PLUMBING PLANS EXAMINER |
| | CITY OF WEST PALM BEACH |
| | 561-805-6711 |
| | [email protected] |
| | |
| | GAS PERMIT APPLICATION REQUIREMENTS |
| | |
| | EFFECTIVE IMMEDIATELY THE FOLLOWING INFORMATION SHALL |
| | BE SHOWN ON ALL GAS DRAWINGS SUBMITTED FOR PERMITTING |
| | IN THE CITY OF WEST PALM BEACH: |
| | |
| | 1. SUBMIT AN ISOMETRIC DRAWING THAT CLEARLY SHOWS THE |
| | LENGTH OF ALL CUT SECTIONS OF PIPE PER 2017 FBC-FUEL |
| | GAS, SECS. 402.4.1, 402.4.2. OR 2017 FBC-RES SEC. |
| | G2413.4.1, G2413.4.2. |
| | |
| | 2. SHOW THE TYPE OF PIPE MATERIAL BEING INSTALLED, ALL |
| | PIPE SIZES, AND THE CORRESPONDING EHD NUMBER OF THE |
| | CORRUGATED STAINLESS STEEL TUBING |
| | |
| | (IF APPLICABLE) FOR EACH PIPE SIZE. WPB AMENDMENTS TO |
| | FBC SEC.107.2.1. |
| | |
| | 3. TYPE OF GAS (LP OR NATURAL).WPB AMEND. TO FBC SEC. |
| | 107.2.1. |
| | |
| | 4. LIST THE BTU LOAD OF EACH APPLIANCE AND THE TOTAL |
| | BTU LOAD ON THE SYSTEM. REFER TO THE 2017 FBC-FUEL GAS |
| | SECS.401.8, 402.2, AND TABLES 402.4 (1) THRU 402.4 (37) |
| | OR 2017 FBC-RES. SEC. G2413.3, G2413.4 AND TABLES |
| | G2413.4 (1 ) THROUGH G2413.4 (21). |
| | |
| | 5. SHOW THE DISTANCE FROM THE POINT OF DELIVERY, (GAS |
| | METER / MP REGULATOR / LP TANK) TO THE MOST REMOTE |
| | OUTLET IN THE BUILDING AND / OR SYSTEM PER THE 2017 |
| | FBC-FUEL GAS SEC.402.4.1, 402.4.2, OR 2017 FBC-RES. |
| | SEC. G 2413.4.1, G2413.4.2. |
| | |
| | 6. SUBMIT CALCULATIONS FOR COMBUSTION AIR PER THE 2017 |
| | FBC-FUEL GAS CODE SEC.304.1, 614.6 (CLOTHES DRYERS) OR |
| | 2017 FBC-RES. SEC. G 2407.1 AND G2439.4 (CLOTHES |
| | DRYERS). |
| | |
| | 7. INDICATE THE DELIVERY PRESSURE (PSI) OF THE SYSTEM |
| | ON THE PLAN PER 2017 FBC-FUEL GAS SEC.402.1, 402.4.3 |
| | THRU 402.6 OR 2017 FBC RES. SEC. G2413.2, G2413.4.3. |
| | |
| | 8. SUBMIT A DETAIL SHOWING THE TYPE OF VENT, LOCATION, |
| | SIZE, TERMINATION POINT, HEIGHT ABOVE THE ROOF AND |
| | ANCHORING DETAILS OF THE GAS VENT(S) PER 2017 FBC-FUEL |
| | GAS SECS. 502 THRU 505 OR 2017 FBC-RES. SEC.G2426 |
| | THROUGH G2439. |
| | |
| | 9. SUBMIT MANUFACTURER?S SPECIFICATION SHEETS / |
| | INSTALLATION MANUAL FOR ALL GAS EQUIPMENT TO VERIFY |
| | COMPLIANCE WITH STANDARDS NFPA 54, NFPA 58, AND |
| | FBC-2017 FUEL GAS CODE SEC. 402.2, AND 301.3 OR 2017 |
| | FBC-RES. SEC. G2404.3. GAS APPLIANCES SHALL BE LISTED |
| | AND LABELED. THE INSTALLATION MANUALS FOR ALL GAS |
| | APPLIANCES / EQUIPMENT SHALL BE ONSITE AT THE TIME OF |
| | INSPECTION. FGC SEC.305.1, FBC-RES. SEC.G2408.1. |
| | |
| | 10. CLEARLY SHOW THE LOCATION AND CAPACITY OF LP |
| | TANK(S), TYPE OF TANK (DOT OR ASME), THE DISTANCE OF |
| | THE TANK FROM THE EXTERIOR BUILDING WALL AND ADJACENT |
| | PROPERTY LINES, THE DISTANCE OF THE TANK FROM ALL |
| | SOURCES OF IGNITION, OTHER CONTAINERS, BUILDINGS, AND |
| | THE LOCATION OF ANY BUILDING OPENINGS BELOW THE RELIEF |
| | VALVE OF THE TANK PER NFPA 58, TABLE 3-2.2.2. |
| | |
| | 11. CLEARLY INDICATE ON THE PLAN IF THE LP TANK IS |
| | ABOVE GROUND OR BELOW GROUND, AND SHOW THE METHOD OF |
| | REQUIRED PROTECTION FOR THE LP TANK AND APPURTENANCES |
| | PER NFPA 58. IF THE TANK IS BELOW GROUND IT SHALL BE |
| | ANCHORED PER NFPA 58 SEC.3-2.2.7 (H). IF ABOVE GROUND, |
| | THE TANK SHALL BE SECURELY ANCHORED TO WITHSTAND 170 |
| | MPH ULT WIND LOAD PER THE FLORIDA BUILDING CODE. |
| | |
| | 12. EMERGENCY HOOD SHUT DOWN SHUT OFF VALVE SHALL BE |
| | BELOW THE CEILING. THE MANUAL SHUTOFF VALVE SHALL BE |
| | UPSTREAM. UNION TO BE DOWN STREAM OF MANUAL VALVE. |
| | SECS. 10.4, 10.5 OF NFPA 96-08. |
| | |
| | 13. INDICATE ON THE PLAN IF THE TANKLESS WATER HEATER |
| | IS THE ONLY GAS APPLIANCE ON THIS SYSTEM? IF NOT, |
| | SUBMIT A COMPLETE GAS RISER SHOWING ALL PIPE SIZES, |
| | TYPE OF PIPE, THE DEVELOPED LENGTH TO THE FURTHEST GAS |
| | OUTLET, THE BTU LOAD OF EACH APPLIANCE, THE PSI OF THE |
| | SYSTEM, THE TYPE OF GAS AND THE TOTAL BTU LOAD ON THE |
| | SYSTEM. THESE REQUIREMENTS ALSO APPLY TO A NEW GAS |
| | SYSTEM. |
| | |
| | |