| 2018-11-26 14:42:36 | 2ND REVIEW FBC-2017 MECHANICAL |
| | PERMIT #18050277 |
| | 11/26/18 |
| | |
| | CODES IN EFFECT: |
| | |
| | FBC B- FLORIDA BUILDING CODE SIXTH EDITION 2017 |
| | FBC M- FLORIDA MECHANICAL CODE SIXTH EDITION 2017 |
| | FBC EC- FLORIDA ENERGY CONSERVATION CODE SIXTH EDITION |
| | 2017 |
| | FBC FG- FLORIDA FUEL GAS CODE SIXTH EDITION 2017 |
| | FS- FLORIDA STATUTES |
| | FAC- FLORIDA ADMINISTRATIVE CODE |
| | WPB- WEST PALM BEACH AMENDMENTS TO THE FBC SIXTH |
| | EDITION 2017 |
| | |
| | PLAN REVIEW RESULTS: DENIED. |
| | |
| | 1) A-1.0.05, A-2.0.02, A-5.0.01, A-6.0.00, & M-1.3.01: |
| | THE EXTERIOR DOORS AND INTERIOR DOORS ENCLOSING THE |
| | POOL EQUIPMENT STORAGE AND ELECTRICAL ROOMS SHALL BE |
| | FIRE-RATED PER SECTION 707.6 FBC B. ( CORRECTED |
| | ARCHITECTURAL PLANS NOW SHOW THE EXTERIOR WALLS TO BE |
| | 3HR FIRE-RATED). FIRE DAMPERS SHALL BE PROVIDED FOR THE |
| | MAKEUP AIR LOUVERS ON THE EAST WALLS, AND FOR THE AC-1 |
| | OUTDOOR AIR INTAKE LOUVER, THE FOOD PREP EXHAUST |
| | OUTLET, AND THE EXHAUST HOOD MAKEUP AIR INLET- SECTION |
| | 607.5.2 FBC M. |
| | |
| | 2) SHEET M-1.3.01: THE STAINLESS STEEL EXHAUST DUCKWORK |
| | IN THE POOL EQUIPMENT STORAGE ROOM IS NOT IN COMPLIANCE |
| | WITH SECTION 510.9 FBC M WHICH REQUIRES THE DUCT TO BE |
| | G90 GALVANIZED OR NON-METALLIC MATERIALS THAT EXHIBIT A |
| | FLAME SPREAD/SMOKE-DEVELOPED INDEX OF 25/50. |
| | |
| | 3) M-1.3.01: SUBMIT MANUFACTURER'S SPECIFICATIONS FOR |
| | EF-1 WITH AN APPROVAL STAMP BY THE ENGINEER OF RECORD. |
| | THE SPECS SHALL INDICATE THE FAN HAS BEEN TESTED FOR |
| | USE IN CONVEYING CORROSIVE OR HAZARDOUS EXHAUST FUMES- |
| | SECTION 304.1 FBC M. A) CLARIFY THE LOCATION OF THE |
| | FAN- ABOVE OR BELOW THE CEILING. IF LOCATED ABOVE THE |
| | CEILING PROVIDE AN ACCESS PANEL FOR SERVICE AND |
| | REPLACEMENT- SECTION 306.1 FBC M. |
| | |
| | 4) A-2.0.02 & M-1.3.01: AS INDICATED BY NOTE #6 ON |
| | M-1.3.01 PLEASE SHOW THE EXACT LOCATION OF THE EF-1 |
| | EXHAUST OUTLET TO VERIFY COMPLIANCE WITH SECTION |
| | 501.3.1(2) FBC M. (PLEASE NOTE THIS OUTLET SHALL NOT BE |
| | PROTECTED WITH A FIRE DAMPER- SECTION 510.6.7 FBC M). |
| | |
| | 5) M-1.3.01: COMMENT #3(E) FROM THE 1ST TREVIEW STILL |
| | EXISTS- PLEASE SUBMIT SPECS FOR THE CHEMICAL TANKS IN |
| | THE POOL EQUIPMENT STORAGE ROOM. |
| | |
| | 6) COMMENT #2 FROM THE 1ST REVIEW REQUESTING EVIDENCE |
| | OF ENERGY EFFICIENCY COMPLIANCE WAS NOT ADDRESSED- THE |
| | PROPOSED BUILDING SHALL BE IN COMPLIANCE WITH THE FBC |
| | EC. REFER TO SECTIONS C101.2 -SCOPE AND C401.2 |
| | APPLICATION (COMPLIANCE PATHS). PROVIDE A COMPLIANCE |
| | SUBMITTAL C101.5.1- COMPLIANCE MATERIALS. |
| | |
| | 7) COMMENT #6 FROM THE 1ST REVIEW STILL EXISTS. IF THE |
| | REQUESTED WIND LOAD ENGINEERING IS TO BE A DEFERRED |
| | SUBMITTAL PLEASE INDICATE THAT ON THE CORRECTED PLANS, |
| | OR IN THE RESPONSE NARRATIVE. |
| | |
| | 8) COMMENT #8 FROM THE 1ST REVIEW HAS NOT BEEN |
| | COMPLETELY ADDRESSED. WHEN USING A MECHANICAL |
| | VENTILATION SYSTEM TO PROVIDE COMBUSTION AIR, THE |
| | SYSTEM SHALL PROVIDE THE SPECIFIED COMBUSTION RATE IN |
| | ADDITION TO THE REQUIRED VENTILATION AIR- SECTION |
| | 304.9.3 FBC FG. BASED ON THE AIR BALANCE CALCULATION ON |
| | M-1.3.01, IT APPEARS THAT ALL VENTILATION AIR FROM AC-1 |
| | WILL BE UTILIZED AS MAKEUP AIR FOR THE EXHAUST SYSTEMS. |
| | |
| | 9) M-1.3.01: THE LOCATION OF THE MAKEUP AIR OPENING FOR |
| | THE EXHAUST HOOD SHALL BE A MINIMUM 3' AWAY FROM THE |
| | FOOD PREP EXHAUST OUTLET- SECTION 501.3.1 (3) FBC M. |
| | |
| | |
| | WHEN RESUBMITTING, IT IS HELPFUL TO PROVIDE A RESPONSE |
| | LETTER ADDRESSING EACH ITEM ALONG WITH THE CITY |
| | RE-SUBMITTAL FORM. ADDITIONALLY, PLEASE INSERT |
| | CORRECTED PLAN SHEETS INTO THE SETS, REMOVE THE |
| | PREVIOUSLY REVIEWED SHEETS AND MARK VOID ON THEM, AND |
| | KEEP THEM WITH THE SUBMITTALS |
| | |
| | CHRISTOPHER L. COLE |
| | MECHANICAL PLANS EXAMINER |
| | 401 CLEMATIS STREET |
| | WEST PALM BEACH FL 33401 |
| | 561-805-6719 |
| | [email protected] |
| | |