| 2018-06-13 07:19:00 | 2ND GAS REVIEW**DENIED** WITH COMMENTS NOTE - A |
| | COMPREHENSIVE REVIEW COULD NOT BE DONE AT THIS TIME AND |
| | ADDITIONAL PLAN REVIEW COMMENTS MAY BE GENERATED UPON |
| | THE RE-REVIEW OF SUBMITTED CORRECTIONS. SOME COMMENT |
| | MAY NOT APPLY BUT ARE PROVIDED FOR REFERENCES. |
| | |
| | 1. WATER HEATER WILL REQUIRE A SEPARATE IGNITION SOURCE |
| | AND IT IS BEING LABELED ON AS A ELECTRICAL LOAD, PLEASE |
| | REMOVE AND ADD A SEPARATE CIRCUIT FOR IGNITION ON |
| | TANKLESS, WPB AMENDMENTS TO THE FBC SEC.107.2.1 |
| | INFORMATION ON CONSTRUCTION DOCUMENTS. |
| | 2. A SECOND REQUEST FOR FIREPLACE ON MANUFACTURES |
| | SPECIFICATION, FBC FG R2434.1 GENERAL. |
| | 3. SHOW 2 PSI REGULATOR ON ISOMETRIC AND ALL REGULATORS |
| | DOWNSTREAM, SHOW THE LOCATION OF ALL MP (STEP-DOWN) |
| | REGULATORS. A LISTED SHUTOFF VALVE SHALL BE INSTALLED |
| | IMMEDIATELY AHEAD OF EACH MP REGULATOR ON ISOMETRIC. |
| | 2017 FBC FUEL GAS RES. SEC. G2420.4. SUBMIT |
| | MANUFACTURER?S SPECIFICATIONS FOR THE PRESSURE |
| | REGULATORS. REGULATORS INSTALLED ON THE EXTERIOR OF THE |
| | BUILDING SHALL BE APPROVED FOR OUTDOOR INSTALLATION. |
| | 2017 FBC FUEL GAS RES. SEC. G2421.1. |
| | 4. TYPE OF GAS (LP OR NATURAL) NEED TO BE LABELED ON |
| | ISOMETRIC. WPB AMENDMENTS TO THE FBC SEC. 107.2.1 |
| | INFORMATION ON CONSTRUCTION DOCUMENTS. |
| | 5. SECOND REQUEST, PLEASE SUBMIT A DETAIL SHOWING THE |
| | TYPE, LOCATION, SIZE, TERMINATION POINT, HEIGHT ABOVE |
| | THE ROOF AND ANCHORING DETAILS OF THE GAS VENT(S) PER |
| | 2017 FBC FUEL GAS SECS. 502 THRU 505 OR 2017 FBC FUEL |
| | GAS RES. SECS. G2426 THRU G2429.1 |
| | 6. SECOND REQUEST, PLEASE SUBMIT TWO COPIES OF THE |
| | APPLICABLE SIZING TABLES USED TO SIZE THE GAS SYSTEM OR |
| | PLACE A NOTE ON THE PLANS/DRAWINGS SPECIFYING WHICH |
| | SIZING TABLE(S) FROM THE GAS CODE OR ANOTHER STANDARD |
| | THAT WAS USED IN THE DESIGN OF THIS GAS SYSTEM. REFER |
| | TO THE 2017 FBC FUEL GAS RES. SEC. G2412.4, G2412.8, |
| | G2413.1, G2413.2, & G2413.3. |
| | 7. SECOND REQUEST, SUBMIT COMBUSTION AIR CALCULATIONS |
| | FOR DRYER GAS APPLIANCES. WHERE IS COMBUSTION AIR |
| | PROVIDED BY THE BUILDING?S MECHANICAL VENTILATION |
| | SYSTEM, THE SYSTEM SHALL PROVIDE THE SPECIFIED |
| | COMBUSTION AIR RATE IN ADDITION TO THE REQUIRED |
| | VENTILATION AIR? 2017 FBC R G2407.9.3. COMBINED |
| | COMBUSTION AIR AND VENTILATION AIR SYSTEM. |
| | |
| | 1ST PLUMBING REVIEW**DENIED** WITH COMMENTS NOTE - A |
| | COMPREHENSIVE REVIEW COULD NOT BE DONE AT THIS TIME AND |
| | ADDITIONAL PLAN REVIEW COMMENTS MAY BE GENERATED UPON |
| | THE RE-REVIEW OF SUBMITTED CORRECTIONS. |
| | |
| | LUIS A. CRESPO |
| | PLUMBING INSPECTOR / |
| | PLUMBING PLAN REVIEW |
| | AVAILABLE FROM 1:00 PM TO 4:00 PM |
| | [email protected] |
| | 561-805-6720 |
| | |